February 2005 Monthly Operating Report for Point Beach Nuclear Plant, Unit 1 & 2
ML052360306
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 08/19/2005
From: Koehl D
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2005-0080
Download: ML052360306 (6)


Text

Committed to Nuclear Excellence Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC August 19, 2005 NRC 2005-0080 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Revised Monthly Operating Report This letter provides corrected data previously submitted in the Monthly Operating Report (MOR) for Unit 1 from December 2003 through February 2005, and Unit 2 for February 2005.

During April 2005, a comparison of data was performed as part of the transition from submittal of the MOR data to utilization of the INPO database, Consolidated Data Entry (CDE), for quarterly data submittal to INPO.

Discrepancies were identified in the Net Electrical Energy data for December 2003 through February 2005 for Unit 1 and February 2005 for Unit 2. The discrepancies were found to be from the software program that was used for the Monthly Operating Report.

Enclosure 1 is a table that provides the correct data for Net Electrical Energy Generated for Unit 1 from December 2003 through February 2005. Enclosure 2 is the revised Operating Data Report for February 2005 for Units 1 and 2. The March 2005 submittal for February 2005 data was the last time the MOR was submitted by NMC prior to receipt of NRC Safety Evaluation, dated April 1, 2005, which eliminated the requirement of PBNP TS 5.6.3 to submit the MOR.

6590 Nuclear Road

  • Two Rivers, Wisconsin 54241 Telephone: 920.755.2321

- -

Document Control Desk Page 2 This letter contains no new commitments and no revisions to existing commitments.

Dennis L. Koehl Site Vice-President, Point Beach Nuclear Plant Nuclear Management Company, LLC Enclosure cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW INPO Records Center

ENCLOSURE I DECEMBER 2003 - FEBRUARY 2005 REVISED MONTHLY OPERATING REPORT NET ELECTRICAL ENERGY GENERATED DATA Point Beach Nuclear Plant Corrections to Unit I Net Electrical Energy (MWH)

M ONTH_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Month Year to Date Cumulative Dec-03 381,368.5 4,348,003.0 109,899,312.0 Jan-04 381,232.0 381,232.0 110,280,544.0 Feb-04 353,743.0 734,975.0 110,634,287.0 Mar-04 374,893.5 1,109,868.5 111,009,180.5 Apr-04 20,584.5 1,130,453.0 111,029,765.0 May-04 0.0 1,130,453.0 111,029,765.0 Jun-04 245,574.5 1,376,027.5 111,275,339.5 Jul-04 378,638.0 1,754,665.5 111,653,977.5 Aug-04 380,023.5 2,134,689.0 112,034,001.0 Sep-04 365,470.5 2,500,159.5 112,399,471.5 Oct-04 381,554.5 2,881,714.0 112,781,026.0 Nov-04 368,551.0 3,250,265.0 113,149,577.0 Dec-04 380,778.5 3,631,043.5 113,530,355.5 Jan-05 381,083.5 381,083.0 113,911,439.0 Feb-05 342,868.0 723,951.0 114,254,307.0 Page I of I

ENCLOSURE 2 UNIT 2 REVISED FEBRUARY 2005 MONTHLY OPERATING REPORT 2 pages follow

OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 05/20/05 COMPLETED BY Kim M. Locke TELEPHONE 920-755-7655 REPORTING PERIOD February - 2005

1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 516.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 672.0 1,416.0 248,786.3
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 672.0 1,416.0 245,199.4
5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 846.9
6. NET ELECTRICAL ENERGY (MWH) 342,868.0 723,951.5 114,254,307.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997

OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 2 DATE 05/20/05 COMPLETED BY Kim M. Locke TELEPHONE 920-755-7655 REPORTING PERTOD February - 2005

1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 518.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 672.0 1,416.0 243,374.2
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 672.0 1,416.0 240,213.2
5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 302.2
6. NET ELECTRICAL ENERGY (MWH) 344,135.0 729,718.5 113,615,683.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997