Nucl Committed to Nuclear Excellence Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC NRC 2002-0078 GL 97-02 September 9, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:

Dockets 50-266 And 50-301 Point Beach Nuclear Plant, Units I And 2 Monthly Operating Reports Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of August 2002.

Sincerely, T. J. Webb Regulatory Affairs Manager KML Attachment cc: J. D. Loock, PSCW NRC Region EIl NRC Senior Resident Inspector NRC Project Manager 6590 Nuclear Road 0 Two Rivers, Wisconsin 54241 Telephone: 920.755 2321

Docket 50-266 and 50-301 NRC-2002-0078 ATTACHMENT 1 Letter from Thomas J. Webb (NMC)

To Document Control Desk (NRC)

Dated September 09, 2002 Re: Monthly Operating Report -August 2002

OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 09/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERI OD August - 2002

1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 510.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 5,831.0 229,440.8
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 5,831.0 225,925.0
5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 846.9
6. NET ELECTRICAL ENERGY (MWH) 372,657.0 2,931,491.5 104,507,011.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997

UNIT SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit I DATE: 09/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: August 2002 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G. Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit 1 average daily power for the month of August was 500.9 MWe.

There were no Licensee Event Reports (LERs) submitted to the NRC.

There were no Significant Operating Events.

OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 2 DATE 09/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD August - 2002

1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 512.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 5,042.4 222,824.1
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 5,006.6 219,836.7
5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 302.2
6. NET ELECTRICAL ENERGY (MWH) 378,938.0 2,506,750.5 103,290,259.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997

UNIT SHUTDOWNS DOCKET NO. 50-301 UNIT NAME: Point Beach, Unit 2 DATE: 09/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: August 2002 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G .Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit 2 average daily power for the month of August was 509.3 MWe.

There were no Licensee Event Reports (LERs) submitted to the NRC.

There were no Significant Operating Events.

Text

Nucl Committed to Nuclear Excellence Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC NRC 2002-0078 GL 97-02 September 9, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Ladies/Gentlemen:

Dockets 50-266 And 50-301 Point Beach Nuclear Plant, Units I And 2 Monthly Operating Reports Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of August 2002.

Sincerely, T. J. Webb Regulatory Affairs Manager KML Attachment cc: J. D. Loock, PSCW NRC Region EIl NRC Senior Resident Inspector NRC Project Manager 6590 Nuclear Road 0 Two Rivers, Wisconsin 54241 Telephone: 920.755 2321

Docket 50-266 and 50-301 NRC-2002-0078 ATTACHMENT 1 Letter from Thomas J. Webb (NMC)

To Document Control Desk (NRC)

Dated September 09, 2002 Re: Monthly Operating Report -August 2002

OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 09/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERI OD August - 2002

1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 510.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 5,831.0 229,440.8
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 5,831.0 225,925.0
5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 846.9
6. NET ELECTRICAL ENERGY (MWH) 372,657.0 2,931,491.5 104,507,011.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997

UNIT SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit I DATE: 09/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: August 2002 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G. Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit 1 average daily power for the month of August was 500.9 MWe.

There were no Licensee Event Reports (LERs) submitted to the NRC.

There were no Significant Operating Events.

OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 2 DATE 09/05/02 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD August - 2002

1. DESIGN ELECTRICAL RATING (MWE-NET) 515.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 512.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 5,042.4 222,824.1
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 5,006.6 219,836.7
5. UNIT RESERVER SHUTDOWN HOURS 0.0 0.0 302.2
6. NET ELECTRICAL ENERGY (MWH) 378,938.0 2,506,750.5 103,290,259.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997

UNIT SHUTDOWNS DOCKET NO. 50-301 UNIT NAME: Point Beach, Unit 2 DATE: 09/05/2002 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: August 2002 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G .Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit 2 average daily power for the month of August was 509.3 MWe.

There were no Licensee Event Reports (LERs) submitted to the NRC.

There were no Significant Operating Events.