NRC 2003-0054, May 2003 Monthly Operating Report for Point Beach Units 1 and 2

From kanterella
Jump to navigation Jump to search
May 2003 Monthly Operating Report for Point Beach Units 1 and 2
ML031690346
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/09/2003
From: Cayia A
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, NRC 2003-0054
Download: ML031690346 (5)


Text

iN Committed to Nuclear Excele Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC NRC 2003-0054 GL 97-02 June 09, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 DOCKETS 50-266 AND 50-301 POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 MONTHLY OPERATING REPORTS Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of May 2003.

Sincerely, Site resident KML Attachment cc: J. D. Loock, PSCW NRC Regional Administrator NRC Resident Inspector NRC Project Manager e-LI--,

Ie3q 6590 Nuclear Road

  • Two Rivers, Wisconsin 54241 Telephone: 920.755.2321

1, UNII SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit 1 DATE: 6/06/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: Mav 2003 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUITING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G. Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit I average daily power for the month of May was 513.6 MWe.

No Significant Operating Event occurred on Unit in May:

There were no LER's on Unit I in the month of May.

I, I OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 06/03/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD May - 2003

1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 516.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 3,623.0 235,222.4
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 3,623.0 231,681.5
5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 846.9
6. NET ELECTRICAL ENERGY (MWH) 382,114.5 1,849,246.0 107,400,555.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997

UNIT SHUTDOWNS DOCKET NO. 50-301 UN1T NAME: Point Beach, Unit 2 DATE: 6/06/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: May 2003 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G .Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit 2 average daily power for the month of May was 485.1 MWe.

The following Significant Operating Event occurred on Unit 2 in May:

Steam Leak from 2P-28A, Steam Generator Feed Pump casing.

The following LER's were sent to the NRC in the month of May:

2003-002 TS Required shutdown due to TSAC 3.1.6.B.2 not met 2003-001 Containment Accident Fan Backfraft Damper Fan Failure 2003-003 Failure to place instrument channel in trip as specified by LCO 3.3.1

OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNll 2 DATE 06/03/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD May - 2003

1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 518.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 3,577.0 229,330.1
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 3,535.4 226,301.1
5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 302.2
6. NET ELECTRICAL ENERGY (MWH) 360,884.5 1,785,159.0 106,572,962.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15,1997

Text

iN Committed to Nuclear Excele Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC NRC 2003-0054 GL 97-02 June 09, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 DOCKETS 50-266 AND 50-301 POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 MONTHLY OPERATING REPORTS Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of May 2003.

Sincerely, Site resident KML Attachment cc: J. D. Loock, PSCW NRC Regional Administrator NRC Resident Inspector NRC Project Manager e-LI--,

Ie3q 6590 Nuclear Road

  • Two Rivers, Wisconsin 54241 Telephone: 920.755.2321

1, UNII SHUTDOWNS DOCKET NO. 50-266 UNIT NAME: Point Beach, Unit 1 DATE: 6/06/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: Mav 2003 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUITING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G. Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit I average daily power for the month of May was 513.6 MWe.

No Significant Operating Event occurred on Unit in May:

There were no LER's on Unit I in the month of May.

I, I OPERATING DATA REPORT DOCKET NO. 50-266 UNIT NAME POINT BEACH NUCLEAR PLANT - UNIT 1 DATE 06/03/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD May - 2003

1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 516.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 3,623.0 235,222.4
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 3,623.0 231,681.5
5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 846.9
6. NET ELECTRICAL ENERGY (MWH) 382,114.5 1,849,246.0 107,400,555.0 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15, 1997

UNIT SHUTDOWNS DOCKET NO. 50-301 UN1T NAME: Point Beach, Unit 2 DATE: 6/06/2003 COMPLETED BY: Kim M. Locke TELEPHONE: 755-6420 REPORTING PERIOD: May 2003 (Month/Year)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTIVE ACTIONS F: FORCED (HOURS) SHUTING S: SCHEDULED DOWN (2) COMMENTS N/A N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A. Equipment Failure (Explain) 1 Manual B. Maintenance or Test 2 Manual Trip/Scram C. Refueling 3 Automatic Trip/Scram D. Regulatory Restriction 4. Continuation E. Operator Training/license Examination F .Administrative 5. Other (Explain)

G .Operational Error (Explain) H .Other (Explain)

SUMMARY

Unit 2 average daily power for the month of May was 485.1 MWe.

The following Significant Operating Event occurred on Unit 2 in May:

Steam Leak from 2P-28A, Steam Generator Feed Pump casing.

The following LER's were sent to the NRC in the month of May:

2003-002 TS Required shutdown due to TSAC 3.1.6.B.2 not met 2003-001 Containment Accident Fan Backfraft Damper Fan Failure 2003-003 Failure to place instrument channel in trip as specified by LCO 3.3.1

OPERATING DATA REPORT DOCKET NO. 50-301 UNIT NAME POINT BEACH NUCLEAR PLANT - UNll 2 DATE 06/03/03 COMPLETED BY Kim M. Locke TELEPHONE 920-755-6420 REPORTING PERIOD May - 2003

1. DESIGN ELECTRICAL RATING (MWE-NET) 522.0
2. MAXIMUM DEPENDABLE CAPACITY (MWE-NET) 518.0 MONTH YEAR TO DATE CUMULATIVE
3. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 3,577.0 229,330.1
4. NUMBER OF HOURS THE GENERATOR WAS ON LINE 744.0 3,535.4 226,301.1
5. UNIT RESERVED SHUTDOWN HOURS 0.0 0.0 302.2
6. NET ELECTRICAL ENERGY (MWH) 360,884.5 1,785,159.0 106,572,962.5 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC GENERIC LETTER 97-02 DATED MAY 15,1997