Letter Sequence RAI |
---|
|
|
MONTHYEAR2CAN011402, License Amendment Request - Containment Building Emergency Escape Air Lock Testing and Exemption from Certain Requirements of 10 CFR 50, Appendix J2014-01-21021 January 2014 License Amendment Request - Containment Building Emergency Escape Air Lock Testing and Exemption from Certain Requirements of 10 CFR 50, Appendix J Project stage: Request 2CAN031402, ANO, Unit 2, LAR Supplemental Containement Building Emergency Escape Air Lock Testing and Exemption from Certain Requirements of 10 CFR 50, App J2014-03-17017 March 2014 ANO, Unit 2, LAR Supplemental Containement Building Emergency Escape Air Lock Testing and Exemption from Certain Requirements of 10 CFR 50, App J Project stage: Supplement ML14218A6022014-08-11011 August 2014 Request for Additional Information, License Amendment Request to Revise TS 6.5.16, Containment Leakage Rate Testing Program and Exemption Request, Requirements for Containment Building Emergency Escape Air Lock Doors Project stage: RAI 2CAN091401, Response to Request for Additional Information Containment Building Emergency Escape Air Lock Testing and Exemption from Certain Requirements of 10 CFR 50, Appendix J2014-09-24024 September 2014 Response to Request for Additional Information Containment Building Emergency Escape Air Lock Testing and Exemption from Certain Requirements of 10 CFR 50, Appendix J Project stage: Response to RAI ML14346A2402015-01-12012 January 2015 Exemption from 10 CFR Part 50, Appendix J, Primary Reactor Containment Leakage Testing for Water Cooled Power Reactor Project stage: Approval NRC-2015-0008, Exemption from 10 CFR Part 50, Appendix J, Primary Reactor Containment Leakage Testing for Water Cooled Power Reactor2015-01-12012 January 2015 Exemption from 10 CFR Part 50, Appendix J, Primary Reactor Containment Leakage Testing for Water Cooled Power Reactor Project stage: Approval ML14346A2102015-01-13013 January 2015 Letter, Exemption from 10 CFR Part 50, Appendix J, Primary Reactor Containment Leakage Testing for Water Cooled Power Reactors Project stage: Approval ML14350B2852015-01-22022 January 2015 Issuance of Amendment No. 299, Revise Technical Specification 6.5.16, Containment Leakage Rate Testing Program, for Requirements for Containment Building Emergency Escape Air Lock Doors Project stage: Approval 2014-09-24
[Table View] |
|
---|
Category:Letter
MONTHYEARML24295A1202024-10-21021 October 2024 Relief Request ANO2-RR-24-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 71 IR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20244042024-08-29029 August 2024 Cybersecurity Inspection Report 05000313/2024404 and 05000368/2024404 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20243012024-04-16016 April 2024 NRC Examination Report 05000313/2024301 ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23019A0672023-01-19019 January 2023 Inservice Inspection Request for Information ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22213A1662022-08-0101 August 2022 Information Request, Security IR 2022401 ML22208A0542022-07-26026 July 2022 Request for Information ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22159A3242022-06-0909 June 2022 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000313/2022003 and 05000368/2022003) and Request for Information ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21236A3222021-09-19019 September 2021 Request for Information ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21204A0842021-07-28028 July 2021 ANO Phase 4 2021013 RFI Gap ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 0CAN042105, Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description2021-04-30030 April 2021 Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program ML21071A2172021-03-10010 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Proposed Change to Quality Assurance Program Manual ML21026A2682021-01-26026 January 2021 Request for Information ML21022A0842021-01-22022 January 2021 Request for Additional Information - Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of Emergency Cooling Pond Supply Piping - Arkansas Nuclear One,Units 1 and 2 -Entergy Operations, Inc. NON-PROPRIETARY Redacted ML21019A5142021-01-14014 January 2021 March 2021 Emergency Preparedness Exercise Inspection - Request for Information ML20324A6412020-11-19019 November 2020 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-034 ML20316A0102020-11-0202 November 2020 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Concerning Relief Request EN-20-RR-01 ML20262H0752020-09-17017 September 2020 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20260H4762020-09-0909 September 2020 NRR E-mail Capture - ANO-1 Final RAI License Amendment Request to Revise Lov Relay Allowable Values ML20154K7622020-06-0101 June 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 ML20065H7992020-03-0606 March 2020 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Revise Loss of Voltage Relay Allowable Values ML20055E9092020-02-24024 February 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Revise Control Element Assembly Drop Time ML20036D3092020-02-0505 February 2020 NRR E-mail Capture - ANO-2 - Final RAI Alternative Request VRR-ANO2-2019-1 ML20013C7472020-01-10010 January 2020 NRR E-mail Capture - ANO-1 and 2 -- Final RAI #2 LAR to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19316A0242019-11-0707 November 2019 NRR E-mail Capture - ANO-1 - - Final RAI Concerning Relief Request ANO1-ISI-033 (L-2019-LLR-0100) ML19280A0402019-10-0707 October 2019 NRR E-mail Capture - ANO-1 and 2 - Final RAI #1 License Amendment Request to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19339F5902019-09-23023 September 2019 Request for Information: Arkansas Nuclear One, IR 05000313/2019-004 Occupational Radiation Safety Inspection ML19281E0032019-08-0505 August 2019 ANO 2019 PIR Request for Information ML19203A0122019-07-16016 July 2019 Request for Information - Inservice Inspection Activities (NRC Inspection Report 05000313/2019004) ML19106A4322019-04-16016 April 2019 NRR E-mail Capture - ANO-2 Final RAI Re LAR to Add TS Actions to Address Inoperability of the Containment Building Sump ML19058A8332019-02-27027 February 2019 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-032 2024-05-22
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 11, 2014 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT NO. 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT AND EXEMPTION REQUESTS FOR CHANGES TO EMERGENCY ESCAPE AIR LOCK TESTING (TAC NOS. MF3382 AND MF3383)
Dear Sir or Madam:
By letter dated January 21, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14021A085), supplemented by letter dated March 17, 2014 (ADAMS Accession No. ML14077A139), Entergy Operations, Inc. (Entergy, the licensee),
submitted a license amendment request and an exemption request regarding proposed changes to emergency escape air lock testing for Arkansas Nuclear One, Unit 2.
The Nuclear Regulatory Commission staff has been reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAJ). The questions were sent via electronic transmission on August 6, 2014, to Mr. David Bice, of your staff. The draft questions were sent to ensure that they were understandable, the regulatory basis was clear, and to determine if the information was previously docketed. Mr. Bice indicated that a clarification teleconference was not necessary for the questions, and it was agreed that a response would be submitted within 45 days of the date of this letter.
If you have any questions, please contact me at (301) 415-1081 or by e-mail at Andrea. George@nrc.gov.
Sincerely, Andrea E. George, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-368
Enclosure:
Request for Additional Information cc w/encl: Distribution via Listserv
REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT AND EXEMPTION REQUESTS REGARDING CONTAINMENT BUILDING EMERGENCY ESCAPE AIR LOCK TESTING ENTERGY OPERATIONS, INC.
ARKANSAS NUCLEAR ONE. UNIT 2 DOCKET NO. 50-368 By letter dated January 21, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14021A085), supplemented by letter dated March 17, 2014 (ADAMS Accession No. ML14077A139), Entergy Operations, Inc. (Entergy, the licensee),
submitted a license amendment request (LAR) proposing changes to the Technical Specifications (TSs) for Arkansas Nuclear One, Unit 2. The amendment would modify TS 6.5.16, "Containment Leakage Rate Testing Program," to require a seal contact verification in lieu of a seal pressure test with respect to the emergency escape air lock doors. The request also included a proposed exemption from certain requirements of Title 10 of the Code of Federal Regulations (1 0 CFR) Part 50, Appendix J, "Primary Reactor Containment Leakage Testing for Water Cooled Power Reactors," associated with the proposed testing protocol.
Specifically, the proposed exemption applies to the emergency escape air lock doors for which 10 CFR 50, Appendix J, Option B, Section Ill. B requires, in part, "Type B pneumatic tests to detect and measure local leakage rates across pressure retaining, leakage-limiting boundaries ... be conducted ... " In order for the Nuclear Regulatory Commission (NRC) staff to complete its review of the application, a response to the following request for additional information (RAI) is requested.
RAI-1: Overall Air Lock Test In the submittal dated March 17, 2014, the licensee stated that the overall air lock leak rate tests had been shown to be effective (e.g., third paragraph on page 7 of the attachment). Regarding these successful tests, please provide the following information:
(a) The typical test configuration in terms of whether the strong back is used with the air lock barrel or not.
(b) The directions of the forces applied to the seals by the air lock barrel pressure and/or the strong back. In addition, specify if the direction is the same as the one that would occur during a postulated loss of coolant accident.
(c) The pressures applied during the air lock pressure test.
Enclosure
RAI-2: Between-the-Seals-Test Regarding the between-the-seals tests:
(a) Please provide details about the test protocol that describe how the test pressure was supplied/applied.
(b) Please justify why the test pressure was applied in the opposite direction of accident pressure (see fourth paragraph on page 5 of the attachment to the letter dated March 17, 2014).
(c) Please explain whether the applied pressure in the between-the-seals-test would "lift" the door open or off its sealing surface leading to leakage.
(d) Please summarize the efforts (investigations, modifications, maintenance) in terms of seal design, seal material, seal shape, seal operation conditions, door modifications, test methods etc. that have been considered or conducted to resolve the failure of between-the-seals pressure test cases. Also, please include a description of other gasket materials/profiles that may have been considered that could be qualified for the application that might form a better sealing joint (and more set resistant) without the need for strongbacks.
RAI-3: Seal Contact Check In Section 2.2 of the attachment to the Jetter dated March 17, 2014, the licensee stated that the seal contact check method had been incorporated into and practiced through maintenance procedures. Please provide the information or historical records (if available) that can show the effectiveness of seal contact check on the overall air Jock full pressure leak test (i.e. provide information that shows how performance of seal contact check led to a successful full pressure leak test).
RAI-4: Strongback According to the licensee (attachment to the letter dated March 17, 2014, Section 3.0), NRC violations have been cited relating to the use of a strongback during air Jock door testing as potential test pre-conditioning. Also, according to the licensee (Attachment to Jetter dated March 17, 2014, Section 2.1), pressure testing without the strongback is beyond the approved vendor technical manual instructions. Please clarify whether the strongback will be used in future door leak testing.
RAI-5: Escape Hatch Please provide a description of historical escape hatch usage. Specifically, please clarify whether the escape hatches been operated such that they are only opened to allow emergency egress or to allow maintenance or testing of the hatch itself. Please provide an estimate of how often the escape hatches been used (opened) when containment integrity was required during the past 10 years (accurate enough count to determine never/rarely/often).
RAI-6: Escape Hatch Door Seal Pressure Test Section 4.0 of the attachment to the letter dated March 17, 2014, states, in part:
On rare occasions, minor modifications accompanied with significant maintenance efforts have resulted in successful performance of the as-left between-the-seals test; however, the following as-found tests grossly failed, even at low test pressures of approximately 12 psig [pounds per square inch gauge].
Given that the TS currently specifies testing the seals at a minimum pressure of 10 psig, please identify whether lower pressures were tried that would allow for repeatable determination of satisfactory seal "bead" and gasket contact; something that would be more definitive/
quantitative than a more qualitative chalk/ink contact line visual inspection.