Responds to NRC 800623 Ltr Re Violations Noted in IE Insp Rept 50-389/80-08.Explains Delay in Providing Test Data on sand-cement Mixtures Due to 28-day Curing Period of Samples
ML17266A248
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 07/17/1980
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML17208A918 List:
References
L-80-227, NUDOCS 8008220117
Download: ML17266A248 (2)


Text

P.O. BOX 529100 MIAMI,F L 33152 FLORIDA POWER & LIGHT COMPANY July 17, 1980 L-80-227 Mr. James P. O'Reilly, Director, Region II Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

Re: RII:JRH 50-389/80-08 As part of the referenced report, it was noted that certain test data verifying design requirements for sand-cement mixtures were not available.

FPL agreed to provide the test data; however, because some of the test

'amples require a 28-day curing P eriod, the data will not be available until July 18, 1980. ~

Upon receipt, the data will be forwarded to your office.

~

Such submittal is expected by July 24, 1980.

Very truly yours, l