ML19290F0046 March 1980Interim Deficiency Rept Re Rod Drop Analysis.Westinghouse Interim Solution Re Automatic Mode of Reactor Control Will Be Incorporated Into Operating Procedures If No long-term Solution Is Available Prior to Loading Fuel
ML19291B9155 December 1979Final Deficiency Rept Re Design Error in Sonicbar Pressure Resistant & Watertight Door Units Frame Anchorage.Door Frames Not Yet Installed.Design Mods Will Be Provided & Doors Will Be Installed by 800101Safe Shutdown
ML19291B9173 December 1979Final Deficiency Rept:On 791107,undetectable Failure in Engineered Safety Features Actuation Sys Occurred.Analysis Revealed Sys Ability to Initiate Safety Injection Could Be Lost Under Certain Conditions.Plant Procedures Were Revised
ML19294B48511 February 1980Final Deficiency Rept Re Electrical Conduit Supports Attached to Concrete Structures W/Anchor Bolts That Did Not Meet Tolerance Criteria.Engineering Change Implemented to Include Tables Developed in Specs.Supports Being Repaired
ML19294B49112 February 1980Interim Deficiency Rept Re Blades,Linkages & Arms Setscrews Coming Loose & Causing Damper Blades to Assume Improper Position.Caused by Excessive Hardness of Shaft Matl. Fillet Welds Being Provided to Prevent Slippage
ML19294C06712 February 1980Deficiency Rept:On 791228,during Startup Testing,Discovered Bahnson Design Did Not Account for Hardness of Shaft & Use of Excessively Hardened Matl.Fillet Welds Are Being Provided at Several Locations to Prevent Slipping
ML19294C25812 February 1980Final Deficiency Rept on Bahnson Co safety-related Automatic & Gravity Ventilation Damper Setscrews.Setscrew Matl Too Hard,Causing Possible Slippage & Consequent Improper Blade Position.Fillet Welds Installed to Prevent Slippage
ML19296A73211 February 1980Final Deficiency Rept Re Lightning Arrestors in 480-volt Load Ctrs Causing Reading Below Manufacturer Recommended Min Value.Cause Unstated.Damaged Arrestors Will Be Replaced & Resistance Checked
ML19296D3264 February 1980Final Deficiency Rept Re Leak in Bottom Plate of Condensate Storage Tank Caused by Crack Near Circumferential Weld Seam. Deformed Areas in Bottom Plates Cut Out & Replaced W/New PlatesBoric Acid
Loop seal
ML19305C44221 March 1980Deficiency Rept:On 800221,possibility of Undersize Welds for Branch Connections Was Discovered.Caused by Program Deviation of Piping Supplier Wherein Weld Sizes Were Not Translated Into Drawings & Spool Sizes.Insp Is Underway
ML19305C7533 March 1980Interim Deficiency Rept Re Main Steam Pipe Spools.Ge Issued Instructions to Restore Affected Wall Thickness to Original GE Spec Requirement.Final Rept Will Be Submitted by 800321
ML19305D1987 March 1980Part 21 Rept Re Emergency Feedwater Pump,Turbine Governor Valve Linkage.Governor Linkage Modified to Accommodate Spring Which Preloads Valve Linkage So Governor Valve Remains Open During StandbySafe Shutdown
ML19305D7748 April 1980Final Deficiency Rept Re Failure of Thrust Bearing on Diesel Generator Mfg by Colt Industries.Forwards Colt Industries 800305 Ltr Regarding Successful Completion of Shop Tests
ML19305D8118 April 1980Final Deficiency Rept Re Measurement of Steam Generator Water Level.Steam Generator Impulse Lines Are Being Thermally Insulated to Minimize Heatup.Mod Will Ensure Proper Accuracies W/O Requiring Large Setpoint Increase
ML19305D95427 March 1980Interim Deficiency Rept Re Potential Stress Corrosion Cracking of Control Rod Guide Tube Support Pins.Cause Unstated.Westinghouse Will Perform Ultrasonic Insp of Support Pins in Two or More Operating Domestic Plants
ML19305D99021 March 1980Deficiency Rept 50-395/80-05-07 Re Piping Supplier Drawings of Reinforcing Fillet Weld for Branch Connections & Contractor Revisions Not Providing Min Throat Thickness for Specified Weld Sizes.Caused by Program Deviation
ML19309A9846 March 1980Part 21 Rept:Insp Completed on Crackshaft Thrust Bearing on Generator A.Plugs Properly Installed & Unit Free of Potential Defect
ML19309E44010 March 1980Part 21 Rept:On 800304,received Notification of Potential Problems w/Bergen-Patterson Mechanical Shock Arrestor Assemblies.Defective Assemblies Located on RCS,safety- Related Component Cooling Sys & Reactor Bldg Spray Sys
ML19309F1058 April 1980Final Deficiency Rept Re Measurement of Steam Generator Water Level.Steam Generator Level Impulse Lines Being Thermally Insulated to Minimize Heatup During Time Required to Perform Trip Function,After High Energy Line Break
ML19309F74627 March 1980Part 21 Rept Re Control Rod Guide Tube Support Pin Cracking Due to Possible Stress Corrosion Cracking.Broken Support Pin Could Prevent Proper Control Rod Operation
ML19309G7662 May 1980Potential Significant Deficiency Rept Re Discrepancy in Procurement of Weld Wire.Wire Used in post-weld,heat-treated Weldments Was Tested for Only as-welded Condition
ML19309H12311 April 1980Final Deficiency Rept Per 10CFR21,re Svc Water Booster Pump Motor Failure.Motors Were Taken Out of Svc & Sent to Factory for Repair
ML19312D41325 February 1980Final Deficiency Rept Re Feedwater Check Valves.Check Valves Will Not Be Modified But Replaced W/Rockwell Intl Control Closure Piston Check Valves.Installation Should Be Completed by 801031
ML19312E33028 May 1980Final Deficiency Rept Re Broken Insulators on 7kV Speed & Transfer Switches.Mfg Will Provide New,Heavier Shafts on Operating Mechanism & Welded Cranks to Reduce Deflection. Operating Angle of Cranks Will Also Be Changed
ML19312E36228 May 1980Final Deficiency Rept Re Incorrect Current Sensor in 480- Volt Load Ctr Circuit breaker.Safety-related 480-volt Breakers Inspected Visually.One Sensor Replaced.Manufacturer Notified
ML19312E51228 May 1980Final Deficiency Rept Re Inadequate Electrical Separation. Power Feeder Circuit (Dc) Was Routed from safety-related Distribution Panel to nonsafety-related Panel W/No Isolation Device.Design Control Program Requirements Reviewed
ML19318A05913 June 1980Deficiency Rept Re Substantial Safety Hazard in Westinghouse Centrifugal Charging Pump Operation.Interim Mods Suggested
ML19318A59319 May 1980Deficiency Rept Re ASME Code Class 1 Piping Ordered W/O Stipulating Proper Testing.Caused by Misinterpretation of FSAR Requirements.Purchase Order Changed to Require Examination
ML19318A60927 May 1980Final Deficiency Rept Re Shelf Life of Tapes Used for 480 Volt Terminations Not Being Addressed in Site Procedures. Terminations Are Being Redone.Shelf Lives Have Been Obtained & Are Included in Site Storage Procedures.Details Encl
ML19318C32927 June 1980Deficiency Rept Re Possible Improper Rocker Arm Prelube Pump Operation.Pump Could Fail to Start as Result of Hydraulic Lock in Cylinder.Instituting Further Review of Other Installation Electrical Schematics & Instruction Manuals
ML19318C42626 June 1980to Part 21 Rept Re Failed Thrust Bearing.Insp Complete.Crankshaft Thrust Bearings on Two Diesel Generators Are Free of Reported Potential Defect
ML19322E58521 March 1980Final Deficiency rept:safety-related Class 3 Butt Welds & Class 1,2 & 3 Attachment Welds Generically Contain Undersize Welds & Other Defects.Caused by Failure to Comply W/Asme Insp Program.Personnel Retrained
ML19322E8005 March 1980Part 21 Rept:On 800114,Colt Industries Reported Failure of Thrust Bearing in Diesel Generator Due to Omission of Plugs from Oil Supply Sys.Thrust Bearing & Thrust Collar Are Being Replaced & Plugs Installed
ML19322E82010 March 1980Deficiency Rept Re Problems Identified in Bergen-Patterson Part 2540 Strut Assembly Used W/Pacific Scientific Mechanical Shock Arrestors.Cause Unstated.Larger Assemblies Being Replaced.Smaller Assemblies Modified
ML19323E2399 May 1980Part 21 Rept Re Failure of Adaptor in Air Start Mod Package for Emergency Diesel Generator,Mfg by Colt Industries. Recommends That Purchasers &/Or Licensees Inspect Fittings Fabricated by Colt for Similar ConditionsSafe Shutdown
ML19323E42619 May 1980Deficiency Rept Re RHR Valve Failure.During RCS Heatup for Cold Hydro, a Train RHR Heat Exchanger Flow Control Valve Closed.Caused by Separating Stem Conductor Due to Excessive Bolt Penetration.New Bolts Being Procured
ML19323F74222 May 1980Final Deficiency Rept Re Electrical Penetrations W/Incorrect Blinding Pin Installations in Plug Assemblies.Assembly & Insp Procedures Changed.Proper Blinding Pins Will Be Installed & Inspected
ML19323G13725 April 1980Interim Deficiency Rept Re Primary Containment Relief Valves Potential Significant Deficiency.Determination of Corrective Action Scheduled for 800522
ML19323G42323 May 1980Second Interim Rept Re Potential Deficiency in Primary Containment Relief Valves.Initial Analysis Indicates Hinge Block Mounting Studs Inadequate.Revised Analysis by 800630
ML19323H06629 May 1980Significant Deficiency Rept:On 800222,discovered Chiller Unit Could Not Be Fully Loaded Before Unit Would Trip Out on Low Evaporator Pressure.Low Svc Water Flow Cutout Deleted
ML19323J3196 June 1980Part 21 Rept Re Failed Engine Thrust Bearing.Diesel Generator Sets Were Inspected in Accordance W/Written Procedures & Revised Drawings.Generators Are Free of Reported Potential Defect
ML19326E03521 July 1980Final Deficiency Rept Re Diesel Generator Prelube Oil Pump Continuous Operation.Pump Controls Will Be Revised to Operate for Short Period of Time Each Day.Length of Time to Be Determined by Mfg
ML19329G0324 June 1980Part 21 Rept Re Defective Woodward Governor Supplied on Terry Turbines.Turbine May Trip on Overspeed If Restarted within 30 Minutes After Shutdown.Restart Procedure Revised & Label Applied to Governor
ML19330B28125 June 1980Potential Significant Deficiency Rept Re Primary Containment Relief Valves Supplied by Gpe Controls.Bechtel Has Completed Review of Revised Stress Analysis Calculations.Expected Completion Date of Actions Is 800815
ML19330B75530 July 1980Final Significant Deficiency Rept Re Incorrectly Specified & Installed Flange Matl,Originally Discussed W/Nrc on 800708. All 304 Stainless Steel Flanges Will Be Removed & Replaced w/316 Stainless Steel Flanges
ML19331D33225 August 1980Final Rept,Per 10CFR21 & IE Bulletin 80-16,re Rosemount Model 1152 Pressure Transmitter Safety Hazards.Twelve Transmitters Could Have False Instrument Outputs Caused by Overrange Condition.Instruments to Be Modified or Replaced
ML19331D82728 August 1980Interim Deficiency Rept Re Lack of Full Penetration Welds for Attachments to Class I Pipe.Attachment Welds Will Be Reworked Providing Full Penetration.Class II & III Attachments Will Be Evaluated & Rept FurnishedLiquid penetrant
ML19332A03730 July 1980Interim Deficiency Rept Re Class 1 Pipe Installed W/O Having Required 4-way Ultrasonic Exam.Piping Not Properly Examined Presented for Shipment.Caused by Failure to Perform & Comply W/Procedures to Verify Matl Acceptability
ML19332A6742 September 1980Part 21 Rept Re Con/Chem Epoxy Surfacer Sys.Suppls 800812 Ltr Re Subj Item Reported by Bechtel Power Corp.Will Advise of Schedule Dates of Completion When Bechtel Engineering Studies Finalized
ML19332C58320 November 1989Part 21 Rept Re Misapplication of Magnetrol Level Switches Supplied by GE W/Hpci & RCIC Turbine Assemblies.Switches Declared Inoperable & Electrically Disconnected.Magnetrol Will Modify Spare Level Switch Assemblies