LICENSEE: NEXTERA ENERGY DUANE ARNOLD, LLC FACILITY: DUANE ARNOLD ENERGY CENTER
SUBJECT:
SUMMARY OF DECEMBER 10, 2015, PRE-APPLICATION MEETING WITH NEXTERA ENERGY DUANE ARNOLD, LLC, FOR DUANE ARNOLD SPENT FUEL CRITICALITY ANALYSES (CAC NO. MF6998) On December 10, 2015, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of NextEra Energy Duane Arnold, LLC (NEE) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss Spent Fuel Pool (SFP) criticality analyses for Duane Arnold Energy Center (DAEC). The meeting notice and agenda, dated October 26, 2015, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML 15336A598. A list of attendees is provided as Enclosure 1. The licensee presented information (See ADAMS Accession No. ML 15335A322). The licensee discussed a potential DAEC license amendment request (LAR) to change its SFP storage requirements. DAEC is preparing a SFP storage license amendment because 2013 in situ measurements of the boron-10 (1°B) areal density of one of its SFP storage designs indicate the 10B areal density is below that modeled in its analysis of record for some portions of the SFP. The DAEC presentation included the following aspects:
- Two different SFP storage rack designs,
- The intention to reanalyze both SFP storage rack designs,
- Current DEAC technical specifications and anticipated changes for the SFP and eliminating the new fuel storage vault as an option.
- Plans for the analysis to state that it will follow the guidance in interim staff guidance DSS-ISG-2010-01.
- Schedule for submitting the LAR.
- Suggested future meetings to promote an efficient review. The NRC staff provided feedback on the following items:
- Whether both SFP storage rack designs need to be reanalyzed as opposed to just the design with the 10B areal density below that modeled in its analysis of record.
- The potential for current industry and NRC research into SFP neutron-absorbing material degradation to affect the submittal.
- Justification for the computer codes being used in the analysis.
- Review recent SFP storage license amendments for potential lessons to be learned and to identify any aspects of the DAEC that might be new and unique.
The meeting concluded with both DAEC and NRC staff stating a desire to maximize efficiency in the preparation and review of the submittal. DAEC agreed to consider the NRC feedback. Both DAEC and NRC staff agreed to continue the communication started at this meeting. To that end DAEC proposed a teleconference in early January 2016 to provide an update to its plans. No regulatory decisions were made at this meeting. Members of the public were not in attendance. Public Meeting Feedback forms were provided but not requested by anyone. Please direct any inquiries to me at 301-415-8371, or Mahesh.Chawla@nrc.gov. Docket No. 50-331
Enclosure:
List of Attendees cc: Distribution via Listserv Mahesh Chawla, Project Manager Plant Licensing Branch LPL 3-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation NAME Mahesh Chawla Kent Wood Scott Krepel LIST OF ATTENDEES DECEMBER 10. 2015. PRE-APPLICATION MEETING WITH NEXTERA ENERGY DUANE ARNOLD. LLC REGARDING DUANE ARNOLD ENERGY CENTER SFP CRITICALITY ANALYSES ORGANIZATION NUCLEAR REGULATORY COMMISSION NRC/NRR/DORL/LPL3-11 NRC/NRR/DSS/SRXB2 NRC/NRR/DSS/SRXB2 Matt Yoder (via phone) NRC/NRR/DE/ESGB3 Aloysius Obodoako NRC/NRR/DE/ESGB3 Khadijah West NRC/NRR/DSS/STSB4 NEXTERA ENERGY DUANE ARNOLD, LLC William Cross ReQulatorv ProQrams ManaQer Emilio Fuentes Fuel Manager Courtney Thomas Fuel ManaQer 1 Office of Nuclear Reactor Regulation, Division of Operating Reactor Licensing, LPL3-1 2 Office of Nuclear Reactor Regulation, Division of Safety Systems, Reactor Systems Branch 3 Office of Nuclear Reactor Regulation, Division of Engineering, Steam Generator Tube Integrity and Chemical Engineering Branch 4 Office of Nuclear Reactor Regulation, Division of Safety Systems, Technical Specifications Branch Enclosure The meeting concluded with both DAEC and NRC staff stating a desire to maximize efficiency in the preparation and review of the submittal. DAEC agreed to consider the NRC feedback. Both DAEC and NRC staff agreed to continue the communication started at this meeting. To that end DAEC proposed a teleconference in early January 2016 to provide an update to its plans. No regulatory decisions were made at this meeting. Members of the public were not in attendance. Public Meeting Feedback forms were provided but not requested by anyone. Please direct any inquiries to me at 301-415-8371, or Mahesh.Chawla@nrc.gov. Docket No. 50-331
Enclosure:
List of Attendees cc: Distribution via Listserv DISTRIBUTION: PUBLIC Branch Reading RidsACRS_MailCTR Resource RidsNrrDorlLpl3-1 Resource RidsNrrPMMChawla Resource RidsNrrLAMHenderson Resource RidsRgn3MailCenter Resource IRA/ Mahesh Chawla, Project Manager Plant Licensing Branch LPL 3-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation TWertz, NRR KWood, NRR SKrepel, NRR KWest, NRR AObodoako, NRR MYoder, NRR Janelle Jessie, EDO Region 3 ADAMS Accession Nos. Meeting Notice: ML 15336A598 Handouts: ML 15335A322 Meeting Summary: ML 16006A042 *via email OFFICE NRR/DORL/LPLlll-1/PM NRR/DORL/LPLlll-1/LA NRR/DSS/SRXB/BC (A) NRR/DE/ESGB/BC NAME MChawla MHenderson EOesterle* GKulesa* DATE 1/06/2016 1/06/2016 1/05/2016 12/24/2015 OFFICE NRR/DSS/STSB/BC NRR/DORL/LPLlll-1/BC NRR/DORL/LPLlll-1/PM NAME RElliott* DPelton MChawla DATE 1/05/2016 1/07/2016 1/07/2016 OFFICIAL RECORD COPY