Line 3: |
Line 3: |
| | issue date = 03/05/2012 | | | issue date = 03/05/2012 |
| | title = Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2011007) | | | title = Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2011007) |
| | author name = Pederson C D | | | author name = Pederson C |
| | author affiliation = NRC/RGN-III/ORA | | | author affiliation = NRC/RGN-III/ORA |
| | addressee name = Larson E | | | addressee name = Larson E |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter: | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 5, 2012 |
| [[Issue date::March 5, 2012]]
| |
|
| |
|
| Mr. Eric Larson Acting Site Vice President | | Mr. Eric Larson Acting Site Vice President |
|
| |
|
| FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, 10 Center Road, A-PY-A290 Perry, OH 44081-0097 | | FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, 10 Center Road, A-PY-A290 Perry, OH 44081-0097 SUBJECT: ANNUAL ASSESSMENT LETTER FOR PERRY NUCLEAR POWER PLANT (REPORT 05000440/2011007) |
| | |
| SUBJECT: ANNUAL ASSESSMENT LETTER FOR PERRY NUCLEAR POWER PLANT (REPORT 05000440/2011007) | |
|
| |
|
| ==Dear Mr. Larson:== | | ==Dear Mr. Larson:== |
Line 64: |
Line 61: |
| Please contact John B. Giessner at 630-829-9619 with any questions you have regarding this letter. | | Please contact John B. Giessner at 630-829-9619 with any questions you have regarding this letter. |
|
| |
|
| Sincerely,/RA/ | | Sincerely, |
| | /RA/ |
| Cynthia D. Pederson | | Cynthia D. Pederson |
|
| |
|
| Acting Regional Administrator Docket No. 50-440 License No. NPF-58 | | Acting Regional Administrator Docket No. 50-440 License No. NPF-58 |
|
| |
|
| ===Enclosure:===
| | Enclosure: Perry Nuclear Power Plant Inspection/Activity Plan cc w/encl: Distribution via ListServ |
| Perry Nuclear Power Plant Inspection/Activity Plan cc w/encl: Distribution via ListServ | |
| }} | | }} |
Similar Documents at Perry |
---|
Category:Inspection Plan
MONTHYEARML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) IR 05000440/20220062023-03-0101 March 2023 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2022006) ML23026A2112023-01-26026 January 2023 Notification of Nrc Baseline Inspection and Request for Information Inspection Report 05000440/2023002 ML22336A1222022-12-0505 December 2022 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000440/2023010 IR 05000440/20220052022-08-26026 August 2022 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2022005) ML22234A1482022-08-22022 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-22-052, Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines2022-03-16016 March 2022 Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines IR 05000440/20210062022-03-0202 March 2022 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2021006) ML21257A4602021-09-15015 September 2021 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Perry Nuclear Power Plant IR 05000440/20210052021-09-0101 September 2021 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2021005) ML21168A0662021-06-17017 June 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000440/2021010 ML21099A0872021-04-0808 April 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000440/2021012 IR 05000440/20200062021-03-0404 March 2021 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2020006) ML21020A0392021-01-20020 January 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000440/2021010 ML21004A0922021-01-0404 January 2021 Notification of NRC Baseline Inspection and Request for Information, Inspection Report 05000440/2021001 ML20294A0462020-10-19019 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000440/20200052020-09-0101 September 2020 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2020005) IR 05000440/20190062020-03-0303 March 2020 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2019006) IR 05000440/20190052019-08-28028 August 2019 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2019005) ML19205A4252019-07-23023 July 2019 Ltr. 07/23/19 Perry Nuclear Power Plant, Unit 1 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000440/2019004 (DRS-L.Rodriguez) IR 05000440/20180062019-03-0404 March 2019 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2018006) IR 05000440/20180052018-08-28028 August 2018 Updated Inspection Plan for Perry, Unit 1 (Report 05000440/2018005) IR 05000440/20170062018-03-0202 March 2018 Annual Assessment Letter for Perry Nuclear Power Plant; Report 05000440/2017006 ML18005A6092018-01-0505 January 2018 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000440/20170072017-12-21021 December 2017 NRC Problem Identification and Resolution Inspection Report 05000440/2017007 IR 05000440/20170052017-08-28028 August 2017 Updated Inspection Plan for Perry Nuclear Plant, Unit 1 (Report 05000440/2017005) IR 05000440/20160062017-03-0101 March 2017 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2016006) IR 05000440/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2016005) ML16237A0812016-08-24024 August 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000440/2016004 IR 05000440/20150062016-03-0202 March 2016 Annual Assessment Letter for Perry, Unit 1 (Inspection Report 05000440/2015006) ML16042A1672016-02-10010 February 2016 Ltr. 02/10/16 Perry Nuclear Power Plant - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (MOD/50.59) Baseline Inspection 05000440/2016007 (AAS) IR 05000440/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2015005) ML15204A8292015-07-23023 July 2015 IR 05000440/2015008, 09/21/15, Perry Nuclear Power Plant - Notification of NRC Triennial Fire Protection Baseline ML15062A6042015-03-0404 March 2015 Annual Assessment Letter for Perry Nuclear Power Plant (Report 050003440/2014001) ML14245A3172014-09-0202 September 2014 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant IR 05000440/20130012014-03-0404 March 2014 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2013001) ML13351A3232013-12-16016 December 2013 CDBI Request for Information ML13246A2372013-09-0303 September 2013 2013 Perry Nuclear Power Plant Mid-Cycle Letter Combined IR 05000440/20120012013-03-0404 March 2013 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2012001) ML12248A3122012-09-0404 September 2012 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant ML12166A1902012-06-11011 June 2012 Temporary Instruction 2515/177 Inspection Document Request IR 05000220/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000220/2011001 and 05000440/2011001) IR 05000440/20110072012-03-0505 March 2012 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2011007) IR 05000440/20110062011-09-0101 September 2011 Inspection Plan 05000440-11-006, 9/1/2011 - 12/31/2012, for Perry Nuclear Power Plant ML1106203062011-03-0404 March 2011 EOC Annual Assessment Letter and Inspection/Activity Plan ML1024400842010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Perry Nuclear Power Plant ML1006102812010-03-0303 March 2010 EOC Assessment Letter, Inspection/Activity Plan ML0924404092009-09-0101 September 2009 Perry - Mid-Cycle Performance Review and Inspection Plan IR 05000440/20090012009-03-0404 March 2009 Annual Assessment Letter - Perry Nuclear Plant (050000440/2009001) 2024-01-03
[Table view] Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report 2024-01-30
[Table view] |
Inspection Report - Perry - 2011007 |
---|
|
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 5, 2012
Mr. Eric Larson Acting Site Vice President
FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, 10 Center Road, A-PY-A290 Perry, OH 44081-0097 SUBJECT: ANNUAL ASSESSMENT LETTER FOR PERRY NUCLEAR POWER PLANT (REPORT 05000440/2011007)
Dear Mr. Larson:
On February 15, 2012, the U.S. Nuclear Regulatory Commission (NRC) staff completed its end-of-cycle performance review of Perry Nuclear Power Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions for the period from January 1, 2011, through December 31, 2011. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan does not
include security information. A separate letter will include the NRC's assessment of your performance in the Security Cornerstone and its security-related inspection plan.
The NRC determined that the performance at the Perry Nuclear Power Plant during the most
recent quarter was within the Degraded Cornerstone Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because of one finding having a low-to-moderate safety significance (i.e., White) from the second quarter of 2011 and a White Occupational Exposure Control Effectiveness Performance Indicator (PI) with four occurrences (the threshold for Green-to-White is more than 2 occurrences) during the second and third quarters of 2011. The finding and the performance indicator were both in the Occupational Radiation Safety Cornerstone. One of the PI occurrences was in November 2010 and, therefore, no longer counted in the fourth quarter 2011. Additionally, one of the remaining three PI occurrences from the second quarter of 2011 had the same underlying cause as the White finding (a situation which could result in double counting the PI and the finding as White). Therefore, for the fourth quarter of 2011, in accordance with the guidance in Section 11.03 of Inspection Manual Chapter 0305, "Operating Reactor Assessment Program," the White PI is not considered an Action Matrix input. Despite having only the single White finding as an input to the Action Matrix, Perry will remain in the Degraded Cornerstone Column of the ROP until a supplemental inspection in accordance with Inspection Procedure (IP) 95002, "Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area" is completed. We will schedule and conduct the inspection after you have completed your investigation on the reasons for the White performance indicator and White finding in the same cornerstone, and after you have advised us, in writing, that you are ready for the inspection. This supplemental inspection is in addition to ROP baseline inspections at your facility.
Performance at the Perry Nuclear Power Plant during the assessment period continued to exhibit weaknesses in the area of human performance (HP) with 12 findings identified. This assessment period is the ninth consecutive assessment period identifying a substantive cross-cutting issue in the HP cross-cutting area. In our mid-cycle assessment letter
[ADAMS ML112440084] dated September 1, 2011, we advised you of substantive cross-cutting issues (SCCIs) in the HP area with cross-cutting themes in Work Planning, H.3(a), and Documentation/Procedures, H.2(c). In addition, we advised you that the HP SCCIs would remain open until the number of findings in the H.3(a) and H.2(c) aspects were reduced and you demonstrated the implementation of effective corrective actions that resulted in sustained performance improvement in the HP area.
Regarding H.3 (a), at the time of the mid-cycle assessment, this SCCI was open for eight consecutive assessment periods. We performed an inspection [ADAMS ML120190153] in December 2011, and determined your corrective actions on this SCCI had been successful in reducing the findings and addressing the underlying causes. There were no findings in this aspect during this assessment cycle and there has been sustained performance improvement. For this reason, the SCCI in Work Planning, H.3(a), is closed.
During the same inspection performed in December 2011, regarding the SCCI in H.2(c), evaluations and actions had not been completed to allow NRC review. Your staff informed us that your facility was ready for the inspection in December; however, we determined while onsite that several key evaluations were not completed. We concluded the site was not ready for us to inspect your actions in regards to this SCCI. To date, the actions implemented by your staff have not resulted in sustained performance improvement in this aspect. Specifically, three inspection findings were identified with this aspect as the most significant contributing cause.
As a result, the H.2(c) SCCI will remain open.
During this assessment period, the NRC staff identified a new SCCI in the HP area in the aspect of Conservative Assumptions, H.1(b). There were four findings during this assessment cycle which identified this aspect as the most significant contributing cause. At the close of 2011, your staff was performing a cause evaluation and the actions taken had not yet proven you were effective at mitigating the theme.
Therefore, the NRC is opening an SCCI in Conservative Assumptions, H.1(b).
The SCCIs in H.1(b) and H2(c) will remain open until the number of findings in the H.1(b) and H.2(c) aspects are reduced and you demonstrate the implementation of effective corrective actions that result in sustained performance improvement in each of these aspects of HP. Although we noted some improvement in specific areas of HP during this assessment cycle, concerns with the SCCIs identified by this letter continue to exist. Because we were not able to inspect these SCCIs at the end of 2011 [since you had not completed your actions], we are asking you to provide to us within 30 days of this letter, in writing, the causes and corrective action planned and completed for the two SCCIs addressed in this letter. The plan should provide projected dates for actions, and you s hould provide any metrics you are using to determine whether sustained improvement has been achieved. In addition, you should be prepared to discuss these actions at the end-of-cycle assessment meeting. Based on the level of progress demonstrated at the end-of-cycle meeting, we will determine if additional meetings are needed.
The enclosed inspection plan lists the inspections scheduled through June 30, 2013.
Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should
circumstances warrant any changes.
In addition to the ROP baseline and IP 95002 inspections, inspections are planned for Temporary Instruction (TI) 2515/177, "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems"; TI 2515/182, "Buried Piping and Tanks"; TI 2515/185, "Follow-up of NEI Groundwater Protection Initiative"; and Independent Spent Fuel Storage Installation (ISFSI) inspections: IP 60854.1, "Preoperational Testing of ISFSIs at Operating Plants"; IP 60855.1, "Operation of an ISFSI at Operating Plants"; and IP 60856.1, "Review of 10 CFR 72.212(b) Evaluations at Operating Plants."
In accordance with 10 CFR 2.390 of the NRC
=s A Rules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact John B. Giessner at 630-829-9619 with any questions you have regarding this letter.
Sincerely,
/RA/
Cynthia D. Pederson
Acting Regional Administrator Docket No. 50-440 License No. NPF-58
Enclosure: Perry Nuclear Power Plant Inspection/Activity Plan cc w/encl: Distribution via ListServ