{{#Wiki_filter:From: Feintuch, Karl Sent: Thursday, August 05, 2010 11:29 AM To: 'Jack Gadzala' Cc: Bedi, Gurjendra
 
==Subject:==
RE: Snubber Replacement Reporting
 
I contacted the cognizant technical branch (CPTB = Component Performance and Testing Branch) about this matter and identified the affected items to them:
* Containment Spray 6 inch line (qty 1)
* Reactor Coolant System 2 inch line (qty 2)
* CVCS 2 inch line (qty 1)
* Safety Injection 2 inch line (qty 1)
Your action to enter this condition into the Kewaunee Power Station corrective action program and include the missing (replaced) snubbers in the next routine report is acceptable.
Karl Feintuch Project Manager USNRC 301-415-3079 From: Jack Gadzala [mailto:jack.gadzala@dom.com]  Sent: Monday, August 02, 2010 2:50 PM To: Feintuch, Karl
 
==Subject:==
Snubber Replacement Reporting Karl,  Attached is the KPS 2009 ISI Summary Report that was submitted to NRC on January 4, 2010.
 
As we discussed, 5 snubber replacements were not included in that report (Form NIS-2 Owner's Report For Repair/Replacement Activity) as required by paragraph IWA-6230 of ASME Section XI. This condition has been entered into the KPS corrective action program. Unless the staff desires the information sooner, we plan to report the 5 snubber replacements in the next routine report.
Jack Dominion KPS Licensing 920-388-8604 CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of th e contents of this info rmation is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.
E-mail Properties Mail Envelope Properties (26E42474DB238C408C94990815A02F090A76C3F588)
 
==Subject:==
RE: Snubber Replacement Reporting
 
Sent Date:        8/5/2010 11:33:29 AM Received Date:        8/5/2010 11:33:00 AM From:                Feintuch, Karl
 
Created By:        Karl.Feintuch@nrc.gov
 
Recipients:
jack.gadzala@dom.com ('Jack Gadzala')
Tracking Status: None Gurjendra.Bedi@nrc.gov (Bedi, Gurjendra)
Tracking Status: None
 
Post Office:
HQCLSTR01.nrc.gov
 
Files                Size        Date & Time MESSAGE        12514        8/5/2010
 
Options Expiration Date:
Priority:                        olImportanceNormal ReplyRequested:        False Return Notification:        False
 
Sensitivity:        olNormal Recipients received:}}

Revision as of 07:19, 19 September 2018

E-mail MD7112 Snubber Replacement Reporting Response 2010-08-05
ML102210331
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 08/05/2010
From: Feintuch K
Plant Licensing Branch III
To: Gadzala J
Dominion Energy Kewaunee
Feintuch K D, NRR/DORL/LPL3-1, 415-3079
References
TAC MD7112
Download: ML102210331 (2)


Text

From: Feintuch, Karl Sent: Thursday, August 05, 2010 11:29 AM To: 'Jack Gadzala' Cc: Bedi, Gurjendra

Subject:

RE: Snubber Replacement Reporting

I contacted the cognizant technical branch (CPTB = Component Performance and Testing Branch) about this matter and identified the affected items to them:

  • CVCS 2 inch line (qty 1)
  • Safety Injection 2 inch line (qty 1)

Your action to enter this condition into the Kewaunee Power Station corrective action program and include the missing (replaced) snubbers in the next routine report is acceptable.

Karl Feintuch Project Manager USNRC 301-415-3079 From: Jack Gadzala [1] Sent: Monday, August 02, 2010 2:50 PM To: Feintuch, Karl

Subject:

Snubber Replacement Reporting Karl, Attached is the KPS 2009 ISI Summary Report that was submitted to NRC on January 4, 2010.

As we discussed, 5 snubber replacements were not included in that report (Form NIS-2 Owner's Report For Repair/Replacement Activity) as required by paragraph IWA-6230 of ASME Section XI. This condition has been entered into the KPS corrective action program. Unless the staff desires the information sooner, we plan to report the 5 snubber replacements in the next routine report.

Jack Dominion KPS Licensing 920-388-8604 CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of th e contents of this info rmation is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.

E-mail Properties Mail Envelope Properties (26E42474DB238C408C94990815A02F090A76C3F588)

Subject:

RE: Snubber Replacement Reporting

Sent Date: 8/5/2010 11:33:29 AM Received Date: 8/5/2010 11:33:00 AM From: Feintuch, Karl

Created By: Karl.Feintuch@nrc.gov

Recipients:

jack.gadzala@dom.com ('Jack Gadzala')

Tracking Status: None Gurjendra.Bedi@nrc.gov (Bedi, Gurjendra)

Tracking Status: None

Post Office:

HQCLSTR01.nrc.gov

Files Size Date & Time MESSAGE 12514 8/5/2010

Options Expiration Date:

Priority: olImportanceNormal ReplyRequested: False Return Notification: False

Sensitivity: olNormal Recipients received: