MONTHYEARML1022103312010-08-0505 August 2010 E-mail MD7112 Snubber Replacement Reporting Response 2010-08-05 Project stage: Other ML1201100282012-01-0303 January 2012 NRR E-mail Capture - Kewaunee Part 26 Question Project stage: Other ML12306A0822012-10-31031 October 2012 NRR E-mail Capture - FW: Dominion New(S) Release Announcing Kewaunee Shutdown - October 22, 2012 Project stage: Other ML12319A4022012-11-15015 November 2012 Notice of Forthcoming Meeting with Dominion Energy Kewaunee to Discuss Plans by Kewaunee Power Station to Implement Orders from Lessons Learned from Events in Fukushima, Japan Project stage: Meeting ML12328A1042012-11-21021 November 2012 NRR E-mail Capture - Kewaunee Public Meeting Call in Information - Response Contains Conference Call and Pass Code Information Project stage: Meeting ML12346A2472012-12-11011 December 2012 NRR E-mail Capture - MD7112 - November 27, 2012 Kewaunee Public Meeting - Presentation Notes (for Meeting Summary) Project stage: Meeting ML12352A2822012-12-31031 December 2012 Summary of Meeting with Dominion Energy Kewaunee on Implementation of Orders Japan Lessons Learned Effort Project stage: Meeting ML13014A0972013-01-13013 January 2013 NRR E-mail Capture - MD7112 - Kewaunee Plant Closure - Reply to Part 171 Fee Reduction Questions Project stage: Other ML13036A3042013-01-30030 January 2013 NRR E-mail Capture - FW: Conference Call Attendees - and Presentation Powerpoint (Attached) Project stage: Other ML13063A2482013-02-26026 February 2013 Redacted - Kewaunee Power Station, Post-Shutdown Decommissioning Activities Report Project stage: Other ML13053A3612013-03-0707 March 2013 Request for Withholding Information from Public Disclosure for DNC, DEK, Virginia Kewaunee Unit 1, Millstone Power Station, Units 1, 2 & 3, North Anna Units 1 & 2, Surry Units 1 & 2 Information Pertaining to Foreign Interests Project stage: Withholding Request Acceptance ML13116A3262013-04-30030 April 2013 Forthcoming Closed Meeting with Dominion Energy Kewaunee Staff to Discuss Planning for Physical Security at Kewaunee Power Station Project stage: Meeting ML13128A3612013-05-0707 May 2013 NRR E-mail Capture - MD7112 - Record of Permanent Cessation of Operations 10CFR50.4(b)(8), 10CFR50.82, and the Scheduling of Certain Future Decommissioning Events Project stage: Other ML13134A5272013-05-14014 May 2013 NRR E-mail Capture - ML13133A086 = MF1438 - KPS - Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) - Acceptance Review Results Project stage: Acceptance Review ML13144A1002013-05-23023 May 2013 NRR E-mail Capture - Record of Docketing of Outgoing NRC Correspondence Serial No. 13-293: Certification of Permanent Removal of Fuel -- Confirming Successful EIE Docketing Project stage: Other ML13143A3682013-05-29029 May 2013 Notice of Forthcoming Meeting with Dominion Energy Kewaunee to Discuss Plans for Kewaunee Power Station Regarding Emergency Preparedness Project stage: Meeting ML13170A3692013-06-14014 June 2013 Record of Discussion of Regulations for Parent Financial Guarantees Project stage: Other 2013-01-30
[Table View] |
Text
From:
Feintuch, Karl Sent:
Thursday, August 05, 2010 11:29 AM To:
'Jack Gadzala' Cc:
Bedi, Gurjendra
Subject:
RE: Snubber Replacement Reporting I contacted the cognizant technical branch (CPTB = Component Performance and Testing Branch) about this matter and identified the affected items to them:
Containment Spray 6 inch line (qty 1)
Reactor Coolant System 2 inch line (qty 2)
CVCS 2 inch line (qty 1)
Safety Injection 2 inch line (qty 1)
Your action to enter this condition into the Kewaunee Power Station corrective action program and include the missing (replaced) snubbers in the next routine report is acceptable.
Karl Feintuch Project Manager USNRC 301-415-3079 From: Jack Gadzala [1]
Sent: Monday, August 02, 2010 2:50 PM To: Feintuch, Karl
Subject:
Snubber Replacement Reporting
- Karl, Attached is the KPS 2009 ISI Summary Report that was submitted to NRC on January 4, 2010.
As we discussed, 5 snubber replacements were not included in that report (Form NIS-2 Owners Report For Repair/Replacement Activity) as required by paragraph IWA-6230 of ASME Section XI. This condition has been entered into the KPS corrective action program. Unless the staff desires the information sooner, we plan to report the 5 snubber replacements in the next routine report.
Jack Dominion KPS Licensing 920-388-8604 CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and
may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.
E-mail Properties Mail Envelope Properties (26E42474DB238C408C94990815A02F090A76C3F588)
Subject:
RE: Snubber Replacement Reporting Sent Date: 8/5/2010 11:33:29 AM Received Date: 8/5/2010 11:33:00 AM From: Feintuch, Karl Created By: Karl.Feintuch@nrc.gov Recipients:
jack.gadzala@dom.com ('Jack Gadzala')
Tracking Status: None Gurjendra.Bedi@nrc.gov (Bedi, Gurjendra)
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 12514 8/5/2010 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: