ML17223A875: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 5
| page count = 5
}}
}}
See also: [[followed by::IR 05000335/1990014]]


=Text=
=Text=
{{#Wiki_filter:(ACCELERATED
{{#Wiki_filter:(ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM I~~'REGULATORY INFORMATION DISTRIBUTION SYSTEM (R1DS)ACCESSION NBR:9008140504 DOC.DATE: 90/08/09 NOTARIZED:
DISTRIBUTION
NO FACIL:50-335 St.Lucie Plant, Unit 1, Florida Power 6 Light Co.AUTH.NAME AUTHOR AFFILIATION GOLDBERG,J.H.
DEMONSTRATION
Florida Power&Light, Co.RECIP.NAME RECIPIENT AFFIL1ATION Document Control Branch (Document Control Desk)
SYSTEM I~~'REGULATORY
 
INFORMATION
==SUBJECT:==
DISTRIBUTION
Responds to violations noted in Insp Rept 50-335/90-14.
SYSTEM (R1DS)ACCESSION NBR:9008140504
DISTRIBUTION CODE: IEOID COPIES RECEIVED:LTR i ENCL j SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice of VioTation Response NOTES: DOCKET ,05000335 D RECIPIENT ID CODE/NAME PD2-2 PD INTERNAL: ACRS AEOD/DEIIB DEDRO NRR SHANKMAN,S NRR/DOEA DIR 11 NRR/DRIS/DIR
DOC.DATE: 90/08/09 NOTARIZED:
.NRR/PMAS/ILRB12 OE.D EXTERNAL: LPDR NSIC COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1.1 1 1'1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME NORRIS,J AEOD AEOD/TPAD NRR MORISSEAU,D NRR/DLPQ/LPEB10 NRR/DRE P/PE PB9 D NRR/DST/DIR 8E2 NUDOCS-ABSTRACT OGC/HDS2 RGN2 FILE 01 NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 A D D S D NOTE TO ALL"RIDS" RECIPIENTS:
NO FACIL:50-335
D D PLEASE HELP US TO REDUCE O'ASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOiiI Pl-37 (EXT.20079)TO ELIMINATE YOUR NAME FROiv!DISTRIBUTIOiV LISTS FOR DOCUi>IENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24 PO.Box 14000,Juno Beach,FL 33408 0420 AUGUST.9 1990 L-90-291 10 CFR 2.201 U.S.Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.20555 Gentlemen:
St.Lucie Plant, Unit 1, Florida Power 6 Light Co.AUTH.NAME AUTHOR AFFILIATION
Re: St.Lucie Unit 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 Florida Power and Light Company has reviewed the subject inspection report and pursuant to 10 CFR 2.201 the response is attached.Very truly yours,":.b WX~~:~J;H.Goldberg President-Nuclear Division JHG/GRM Attachment A cc: Stewart D.Ebneter, Regional Administrator, USNRC Region II Senior Resident Inspector, USNRC, St.Lucie Plant900-:;,40.".;Ot'C>r>80a>
GOLDBERG,J.H.
Florida Power&Light, Co.RECIP.NAME
RECIPIENT AFFIL1ATION
Document Control Branch (Document Control Desk)SUBJECT: Responds to violations
noted in Insp Rept 50-335/90-14.
DISTRIBUTION
CODE: IEOID COPIES RECEIVED:LTR
i ENCL j SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice
of VioTation Response NOTES: DOCKET ,05000335 D RECIPIENT ID CODE/NAME PD2-2 PD INTERNAL: ACRS AEOD/DEIIB
DEDRO NRR SHANKMAN,S
NRR/DOEA DIR 11 NRR/DRIS/DIR
.NRR/PMAS/ILRB12
OE.D EXTERNAL: LPDR NSIC COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1.1 1 1'1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME NORRIS,J AEOD AEOD/TPAD NRR MORISSEAU,D
NRR/DLPQ/LPEB10
NRR/DRE P/PE PB9 D NRR/DST/DIR
8E2 NUDOCS-ABSTRACT
OGC/HDS2 RGN2 FILE 01 NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 A D D S D NOTE TO ALL"RIDS" RECIPIENTS:
D D PLEASE HELP US TO REDUCE O'ASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOiiI Pl-37 (EXT.20079)TO ELIMINATE YOUR NAME FROiv!DISTRIBUTIOiV
LISTS FOR DOCUi>IENTS
YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24  
PO.Box 14000,Juno
Beach,FL 33408 0420 AUGUST.9 1990 L-90-291 10 CFR 2.201 U.S.Nuclear Regulatory
Commission
Attn: Document Control Desk Washington, D.C.20555 Gentlemen:
Re: St.Lucie Unit 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 Florida Power and Light Company has reviewed the subject inspection
report and pursuant to 10 CFR 2.201 the response is attached.Very truly yours,":.b WX~~:~J;H.Goldberg President-Nuclear Division JHG/GRM Attachment
A cc: Stewart D.Ebneter, Regional Administrator, USNRC Region II Senior Resident Inspector, USNRC, St.Lucie Plant900-:;,40.".;Ot'C>r>80a>
F'1:<AZ>GCc,'-C~i>j>.".:;:
F'1:<AZ>GCc,'-C~i>j>.".:;:
>-D>".an FPL Grov>>compacv+/  
>-D>".an FPL Grov>>compacv+/
Re: St.Lucie Units 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 FINDING:.Unit 1 Technical Specification (TS)6.8.1.a requires that written procedures
Re: St.Lucie Units 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 FINDING:.Unit 1 Technical Specification (TS)6.8.1.a requires that written procedures shall be established, implemented and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978.Appendix A, paragraph 1.d, includes procedures addressing procedure adherence and temporary change method.Procedure QI 5-PR/PSL-l, Rev 37, Preparation, Revision, Review/Approval of Procedures, section 5.5, implemented TS 6.8.1 and required that procedures be strictly adhered to.It also provided the method to obtain approved temporary procedure changes and, if appropriate, subsequent permanent changes.Procedure OP-1-0120051, Rev 10, RCS Flow Determination by Calorimetric Procedure, steps 8.3 through 8.6, directed certain action sequences involving coordination with the Reactor Control Operator at the control board, control board loop temperature meter function selection using switches, and confirmation that measurements were being made=only on channels that had the meter switched out and isolated.Cont'rary to the above, on May 14, 1990, During the performance of procedure OP 1-0120051, the licensee's staff did not follow instruction steps 8.3 through 8.6 The test persons instead utilized an unapproved method to isolate all the meters to simultaneously isolate the involved loop temperature meters and complete the data collection without.the described coordination.
shall be established, implemented
and maintained
covering the activities
recommended
in Appendix A of Regulatory
Guide 1.33, Revision 2, February 1978.Appendix A, paragraph 1.d, includes procedures
addressing
procedure adherence and temporary change method.Procedure QI 5-PR/PSL-l, Rev 37, Preparation, Revision, Review/Approval
of Procedures, section 5.5, implemented
TS 6.8.1 and required that procedures
be strictly adhered to.It also provided the method to obtain approved temporary procedure changes and, if appropriate, subsequent
permanent changes.Procedure OP-1-0120051, Rev 10, RCS Flow Determination
by Calorimetric
Procedure, steps 8.3 through 8.6, directed certain action sequences involving coordination
with the Reactor Control Operator at the control board, control board loop temperature
meter function selection using switches, and confirmation
that measurements
were being made=only on channels that had the meter switched out and isolated.Cont'rary to the above, on May 14, 1990, During the performance
of procedure OP 1-0120051, the licensee's
staff did not follow instruction
steps 8.3 through 8.6 The test persons instead utilized an unapproved
method to isolate all the meters to simultaneously
isolate the involved loop temperature
meters and complete the data collection
without.the described coordination.
RESPONSE: 2~3~Florida Power and Light Company concurs with the violation.
RESPONSE: 2~3~Florida Power and Light Company concurs with the violation.
The reason for the violation was failure to follow QI 5-PR/PSL-1.Test personnel failed to process a Procedure Change Request (PCR)prior to,implementing
The reason for the violation was failure to follow QI 5-PR/PSL-1.Test personnel failed to process a Procedure Change Request (PCR)prior to,implementing an improved method of collecting the temperature data.The Reactor Coolant System flow determination by calorimetric
an improved method of collecting
.procedure was repeated with the individual's supervisor observing.
the temperature
4, The following actions have been implemented to avoid further violations:
data.The Reactor Coolant System flow determination
a.The individual was counselled by his supervisor.'.
by calorimetric
.procedure was repeated with the individual's
supervisor
observing.
4, The following actions have been implemented
to avoid further violations:
a.The individual
was counselled
by his supervisor.'.
A PCR was submitted to clarify and authorize the'improved method of data collection.  
A PCR was submitted to clarify and authorize the'improved method of data collection.  
 
Re: St.Lucie Units 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 c.All individuals
Re: St.Lucie Units 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 c.All individuals in the Test Group were reminded of the importance of following procedures and the need for processing a PCR and/or a Temporary Change (TC)followed by a PCR prior to implementation of the change.5.All the corrective actions were completed by August 1, 1990.}}
in the Test Group were reminded of the importance
of following procedures
and the need for processing
a PCR and/or a Temporary Change (TC)followed by a PCR prior to implementation
of the change.5.All the corrective
actions were completed by August 1, 1990.
}}

Revision as of 16:13, 17 August 2019

Responds to Violations Noted in Insp Rept 50-335/90-14. Corrective Actions:Rcs Flow Determination by Calorimetric Procedure Repeated W/Supervisor of Individual Observing & Individual Counseled by Supervisor
ML17223A875
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 08/09/1990
From: Goldberg J
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
L-90-291, NUDOCS 9008140504
Download: ML17223A875 (5)


Text

(ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM I~~'REGULATORY INFORMATION DISTRIBUTION SYSTEM (R1DS)ACCESSION NBR:9008140504 DOC.DATE: 90/08/09 NOTARIZED:

NO FACIL:50-335 St.Lucie Plant, Unit 1, Florida Power 6 Light Co.AUTH.NAME AUTHOR AFFILIATION GOLDBERG,J.H.

Florida Power&Light, Co.RECIP.NAME RECIPIENT AFFIL1ATION Document Control Branch (Document Control Desk)

SUBJECT:

Responds to violations noted in Insp Rept 50-335/90-14.

DISTRIBUTION CODE: IEOID COPIES RECEIVED:LTR i ENCL j SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice of VioTation Response NOTES: DOCKET ,05000335 D RECIPIENT ID CODE/NAME PD2-2 PD INTERNAL: ACRS AEOD/DEIIB DEDRO NRR SHANKMAN,S NRR/DOEA DIR 11 NRR/DRIS/DIR

.NRR/PMAS/ILRB12 OE.D EXTERNAL: LPDR NSIC COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1.1 1 1'1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME NORRIS,J AEOD AEOD/TPAD NRR MORISSEAU,D NRR/DLPQ/LPEB10 NRR/DRE P/PE PB9 D NRR/DST/DIR 8E2 NUDOCS-ABSTRACT OGC/HDS2 RGN2 FILE 01 NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 A D D S D NOTE TO ALL"RIDS" RECIPIENTS:

D D PLEASE HELP US TO REDUCE O'ASTE!CONTACT THE DOCUMENT CONTROL DESK, ROOiiI Pl-37 (EXT.20079)TO ELIMINATE YOUR NAME FROiv!DISTRIBUTIOiV LISTS FOR DOCUi>IENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24 PO.Box 14000,Juno Beach,FL 33408 0420 AUGUST.9 1990 L-90-291 10 CFR 2.201 U.S.Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.20555 Gentlemen:

Re: St.Lucie Unit 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 Florida Power and Light Company has reviewed the subject inspection report and pursuant to 10 CFR 2.201 the response is attached.Very truly yours,":.b WX~~:~J;H.Goldberg President-Nuclear Division JHG/GRM Attachment A cc: Stewart D.Ebneter, Regional Administrator, USNRC Region II Senior Resident Inspector, USNRC, St.Lucie Plant900-:;,40.".;Ot'C>r>80a>

F'1:<AZ>GCc,'-C~i>j>.".:;:

>-D>".an FPL Grov>>compacv+/

Re: St.Lucie Units 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 FINDING:.Unit 1 Technical Specification (TS)6.8.1.a requires that written procedures shall be established, implemented and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978.Appendix A, paragraph 1.d, includes procedures addressing procedure adherence and temporary change method.Procedure QI 5-PR/PSL-l, Rev 37, Preparation, Revision, Review/Approval of Procedures, section 5.5, implemented TS 6.8.1 and required that procedures be strictly adhered to.It also provided the method to obtain approved temporary procedure changes and, if appropriate, subsequent permanent changes.Procedure OP-1-0120051, Rev 10, RCS Flow Determination by Calorimetric Procedure, steps 8.3 through 8.6, directed certain action sequences involving coordination with the Reactor Control Operator at the control board, control board loop temperature meter function selection using switches, and confirmation that measurements were being made=only on channels that had the meter switched out and isolated.Cont'rary to the above, on May 14, 1990, During the performance of procedure OP 1-0120051, the licensee's staff did not follow instruction steps 8.3 through 8.6 The test persons instead utilized an unapproved method to isolate all the meters to simultaneously isolate the involved loop temperature meters and complete the data collection without.the described coordination.

RESPONSE: 2~3~Florida Power and Light Company concurs with the violation.

The reason for the violation was failure to follow QI 5-PR/PSL-1.Test personnel failed to process a Procedure Change Request (PCR)prior to,implementing an improved method of collecting the temperature data.The Reactor Coolant System flow determination by calorimetric

.procedure was repeated with the individual's supervisor observing.

4, The following actions have been implemented to avoid further violations:

a.The individual was counselled by his supervisor.'.

A PCR was submitted to clarify and authorize the'improved method of data collection.

Re: St.Lucie Units 1 Docket Nos.50-335 Response to Notice of Violation Ins ection Re ort 90-14 c.All individuals in the Test Group were reminded of the importance of following procedures and the need for processing a PCR and/or a Temporary Change (TC)followed by a PCR prior to implementation of the change.5.All the corrective actions were completed by August 1, 1990.