ML19003A475: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 9: Line 9:
| docket = 05000387, 05000388
| docket = 05000387, 05000388
| license number = NPF-014, NPF-022
| license number = NPF-014, NPF-022
| contact person = Hood T E, NRR/DORL/LPL1-2, 301-415-1387
| contact person = Hood T, NRR/DORL/LPL1-2, 301-415-1387
| case reference number = EPID L-2018-LLA-0496
| case reference number = EPID L-2018-LLA-0496
| document type = Acceptance Review Letter, E-Mail
| document type = Acceptance Review Letter, E-Mail

Revision as of 17:24, 14 June 2019

Acceptance Review Susquehanna Units 1 and 2 License Amendment Request for TSTF-501
ML19003A475
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 01/03/2019
From: Tanya Hood
Plant Licensing Branch 1
To: Cimorelli K
Susquehanna
Hood T, NRR/DORL/LPL1-2, 301-415-1387
References
EPID L-2018-LLA-0496
Download: ML19003A475 (2)


Text

From: Hood, Tanya To: Kevin.Cimorelli@TalenEnergy.com Cc: Jennings, Jason (Jason.Jennings@TalenEnergy.com)

Krick, Melisa

Subject:

Acceptance Review: Susquehanna Units 1 and 2 License Amendment Request for TSTF-501 (EPID: L-2018-LLA-0496)Date: Thursday, January 03, 2019 9:54:00 AM

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST TO REVISE TECHNICAL SPECIFICATIONS TO ADOPT TSTF-501, REVISION 1, "RELOCATE STORED FUEL OIL AND LUBE OIL VOLUME VALUES TO LICENSEE CONTROL." (EPID: L-2018-LLA-0496) By letter dated December 4, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18339A002), Susquehanna Nuclear, LLC (the licensee) submitted a license amendment request (LAR) for Susquehanna Steam Electric Station (SSES), Units 1 and 2. The proposed LAR would revise Technical Specification (TS) 3.8.3, "Diesel Fuel Oil, Lube Oil, and Starting Air," Surveillance Requirement (SR)3.8.3.1. The proposed changes revise TS 3.8.3 by relocating the current stored diesel fuel oil numerical requirements from the TS to the TS Bases so that it may be modified under licensee control. The proposed changes are based on Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, "Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control." The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the TSs) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications.

Section 50.34 of 10 CFR addresses the content of technical information required.

This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.

Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 129 hours0.00149 days <br />0.0358 hours <br />2.132936e-4 weeks <br />4.90845e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 6 months, which is July 2019. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staff's initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

If you have any questions regarding this matter, please contact me at 301-415-1387 or by e-mail. Tanya E. Hood Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, Maryland 20852-2738 301-415-1387 T anya.Hood@nrc.gov