Acceptance of Requested Licensing Action License Amendment Request to Address Secondary Containment Access Openings
ML16263A344
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 09/23/2016
From: Tanya Hood
Plant Licensing Branch 1
To: Franke J
Susquehanna, Talen Energy
Hood T, NRR/DORL/LPL1-2, 301-415-1387
References
CAC MF8214, CAC MF8215, PLA-7528
Download: ML16263A344 (3)


Text

Mr. Jon A. Franke Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 23, 2016

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 -

ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST TO ADDRESS SECONDARY CONTAINMENT ACCESS OPENINGS (CAC NOS. MF8214 AND MF8215)

Dear Mr. Franke:

By letter dated July 27, 2016, as supplemented by letter dated September 13, 2016 (Agencywide Documents Access and Management System Accession Nos. ML16210A001 and ML16257A598, respectively), Susquehanna Nuclear, LLC (the licensee) submitted a license amendment for Susquehanna Steam Electric Station, Units 1 and 2. The proposed amendment would provide an allowance for brief, inadvertent, simultaneous opening of redundant secondary containment access doors during normal entry and exit conditions.

The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications), must fully describe the changes requested, and following, as far as applicable, the form prescribed for original applications. Section 50.34 of 1 O CFR addresses the content of technical information required.

This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application, along with the supplemental information, and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in

which issues that impact the NRC staff's ability to complete the detailed technical review are identified, despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

If you have any questions, please contact me at 301-415-1387 or Tanya.Hood@nrc.gov.

\\ Sincerely, Docket Nos. 50-387 and 50-388 cc: Distribution via Listserv

('

\\

_,, 1/

~~

~

Hood, Pr~ect Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

which issues that impact the NRC staff's ability to complete the detailed technical review are identified, despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

If you have any questions, please contact me at 301-415-1387 or Tanya.Hood@nrc.gov.

Docket Nos. 50-387 and 50-388 cc: Distribution via Listserv DISTRIBUTION:

Sincerely, IRA/

Tanya E. Hood, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation PUBLIC LPL 1-2 Reading File RidsNrrLALRonewicz Resource RidsNrrDssStsb Resource KBucholtz, NRR RidsACRS_MailCTR Resource RidsNrrPMSusquehanna Resource RidsNrrDraArcb Resource RidsNrrDssSbpb Resource MChernoff, NRR RidsRgn 1 MailCenter Resource RidsNrrDorlLpl1-2 Resource NKaripineni, NRR RidsNrrDorl Resource ADAMS A ccess1on N o.: ML16263A344

  • b
  • 1

'e-ma1 OFFICE DORL/LPL 1-2/PM DORL/LPL 1-2/LA NRR/DRA/ARCB/BC*

DSS/SBPB/BC*

NAME THood LRonewicz US hoop RDennig DATE 9/19/16 9/23/16 9/20/16 9/21/16 OFFICE DSS/STSB/BC*

DORL/LPL 1-2/BC DORL/LPL 1-2/PM NAME AKlein DBroaddus THood

~*

DATE 9/21/16 9/22/16 9/23/16

.i' OFFICIAL RECORD COPY