| number = ML21232A017
| number = ML21232A017
| issue date = 08/20/2021
| issue date = 08/20/2021
| title = Licensee'S Non-Proprietary Presentation (2 of 2) for August 23 and 25, 2021 Public Meeting
| title = Licensees Non-Proprietary Presentation (2 of 2) for August 23 and 25, 2021 Public Meeting
| author name =  
| author name =  
| author affiliation = Florida Power & Light Co
| author affiliation = Florida Power & Light Co
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:Turkey Point Unit 3 and Unit 4 Reactor Protection System Engineered Safety Feature Actuation System Nuclear Instrumentation System Replacements Safety System Replacement Project LAR NRC 7th Pre-submittal Meeting Telecon August 23 and August 25, 2021 CLOSED MEETING 1              Non-proprietary information suitable for public disclosure
{{#Wiki_filter:1 Turkey Point Unit 3 and Unit 4 Reactor Protection System Engineered Safety Feature Actuation System Nuclear Instrumentation System Replacements Safety System Replacement Project LAR NRC 7th Pre-submittal Meeting Telecon August 23 and August 25, 2021 CLOSED MEETING Non-proprietary information suitable for public disclosure


2 Non-proprietary information suitable for public disclosure Agenda - Closed Portion- Aug 23 and 25
2 Non-proprietary information suitable for public disclosure
* Closed Session - Aug 23rd
    - Components not Addressed in Approved SER
    - Equipment Qualification and Dedication
    - Human Factors Engineering Program Update
* Closed Session - Aug 25th
    - Application of Leak Detection in D3 Evaluation
    - Command Prioritization
    - Surveillance Reduction Activities
    - Schedule Update
    - Action Items and Follow-up 3          Non-proprietary information suitable for public disclosure


Components Not Addressed in Approved Tricon SER 4            Non-proprietary information suitable for public disclosure
3 Agenda - Closed Portion-Aug 23 and 25 Closed Session - Aug 23rd
- Components not Addressed in Approved SER
- Equipment Qualification and Dedication
- Human Factors Engineering Program Update Closed Session - Aug 25th
- Application of Leak Detection in D3 Evaluation
- Command Prioritization
- Surveillance Reduction Activities
- Schedule Update
- Action Items and Follow-up Non-proprietary information suitable for public disclosure


Safety Video Display Unit (SVDU) 5    Non-proprietary information suitable for public disclosure
4 Components Not Addressed in Approved Tricon SER Non-proprietary information suitable for public disclosure


Proposed Nuclear Instrumentation Signal Processing 6              Non-proprietary information suitable for public disclosure
5 Safety Video Display Unit (SVDU)
Non-proprietary information suitable for public disclosure


NIS Components (TXS) - Framatome GmbH 7        Non-proprietary information suitable for public disclosure
6 Proposed Nuclear Instrumentation Signal Processing Non-proprietary information suitable for public disclosure


New Manufactured NIS Components - Framatome Inc.
7 NIS Components (TXS) - Framatome GmbH Non-proprietary information suitable for public disclosure
end of topic 8              Non-proprietary information suitable for public disclosure


Equipment Qualification 9 Non-proprietary information suitable for public disclosure
8 New Manufactured NIS Components - Framatome Inc.
end of topic Non-proprietary information suitable for public disclosure


Evaluation and Acceptance of Commercial Equipment for Safety Related Applications end of topic 10                Non-proprietary information suitable for public disclosure
9 Equipment Qualification Non-proprietary information suitable for public disclosure


Human Factors Engineering - Overview 11      Non-proprietary information suitable for public disclosure
10 Evaluation and Acceptance of Commercial Equipment for Safety Related Applications end of topic Non-proprietary information suitable for public disclosure


Human Factors Engineering - Elements 12      Non-proprietary information suitable for public disclosure
11 Human Factors Engineering - Overview Non-proprietary information suitable for public disclosure


Action Items and Follow-up for August 23rd Closed Meeting
12 Human Factors Engineering - Elements Non-proprietary information suitable for public disclosure
* Action Items and Follow-up 13                  Non-proprietary information suitable for public disclosure


Turkey Point Unit 3 and Unit 4 Reactor Protection System Engineered Safety Feature Actuation System Nuclear Instrumentation System Replacements Safety System Replacement Project LAR NRC 7th Pre-submittal Meeting Telecon August 25, 2021 CLOSED MEETING 14              Non-proprietary information suitable for public disclosure
13 Action Items and Follow-up for August 23rd Closed Meeting Action Items and Follow-up Non-proprietary information suitable for public disclosure


Agenda
14 Turkey Point Unit 3 and Unit 4 Reactor Protection System Engineered Safety Feature Actuation System Nuclear Instrumentation System Replacements Safety System Replacement Project LAR NRC 7th Pre-submittal Meeting Telecon August 25, 2021 CLOSED MEETING Non-proprietary information suitable for public disclosure
* Closed Session - Aug 25th
      - Application of Leak Detection in D3 Evaluation
      - Command Prioritization
      - Surveillance Reduction Activities
      - Schedule Update
      - Action Items and Follow-up 15          Non-proprietary information suitable for public disclosure


Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 16                Non-proprietary information suitable for public disclosure
15 Agenda Closed Session - Aug 25th
- Application of Leak Detection in D3 Evaluation
- Command Prioritization
- Surveillance Reduction Activities
- Schedule Update
- Action Items and Follow-up Non-proprietary information suitable for public disclosure


Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 17                Non-proprietary information suitable for public disclosure
16 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Non-proprietary information suitable for public disclosure


Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 18                Non-proprietary information suitable for public disclosure
17 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Non-proprietary information suitable for public disclosure


Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Leak Detection Capability 19                Non-proprietary information suitable for public disclosure
18 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Non-proprietary information suitable for public disclosure


Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 end of topic 20                Non-proprietary information suitable for public disclosure
19 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Leak Detection Capability Non-proprietary information suitable for public disclosure


Command Prioritization end of topic 21 Non-proprietary information suitable for public disclosure
20 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 end of topic Non-proprietary information suitable for public disclosure


Technical Specification Surveillance Reduction Update 22              Non-proprietary information suitable for public disclosure
21 Command Prioritization end of topic Non-proprietary information suitable for public disclosure


Tech Spec Surveillance Test Extension/Reduction For RPS/ESFAS/NIS LAR - Coverage Boundary 23              Non-proprietary information suitable for public disclosure
22 Technical Specification Surveillance Reduction Update Non-proprietary information suitable for public disclosure


Tech Spec Surveillance Test Extension/Reduction For RPS/ESFAS/NIS LAR - Coverage Analysis end of topic 24              Non-proprietary information suitable for public disclosure
23 Tech Spec Surveillance Test Extension/Reduction For RPS/ESFAS/NIS LAR - Coverage Boundary Non-proprietary information suitable for public disclosure


Framatome Lifecycle Project Schedule end of topic 25      Non-proprietary information suitable for public disclosure
24 Tech Spec Surveillance Test Extension/Reduction For RPS/ESFAS/NIS LAR - Coverage Analysis end of topic Non-proprietary information suitable for public disclosure


Action Items and Follow-up for August 25th Closed Meeting
25 Framatome Lifecycle Project Schedule end of topic Non-proprietary information suitable for public disclosure
* Action Items and Follow-up 26                  Non-proprietary information suitable for public disclosure


Questions?
26 Action Items and Follow-up for August 25th Closed Meeting Action Items and Follow-up Non-proprietary information suitable for public disclosure
27 Non-proprietary information suitable for public disclosure


Acronym List Actuation Logic Testing                                              ALT Alternate Review                                                      AR Branch Technical Position                                            BTP Channel Operational Testing                                          COT Diverse Actuation System                                              DAS Defense-in-Depth and Diversity                                        D3 Distributed Control System                                            DCS Engineered Safety Features Actuation System                          ESFAS Failure Modes, Effects and Diagnostic Analysis                        FMEDA Florida Power and Light                                              FPL Foxboro Intelligent Automation                                        I/A Human Factor Engineering                                              HFE Instrumentation and Control                                          I&C 28                Non-proprietary information suitable for public disclosure
27 Questions?
Non-proprietary information suitable for public disclosure


Acronym List (continued)
28 Acronym List Non-proprietary information suitable for public disclosure Actuation Logic Testing ALT Alternate Review AR Branch Technical Position BTP Channel Operational Testing COT Diverse Actuation System DAS Defense-in-Depth and Diversity D3 Distributed Control System DCS Engineered Safety Features Actuation System ESFAS Failure Modes, Effects and Diagnostic Analysis FMEDA Florida Power and Light FPL Foxboro Intelligent Automation I/A Human Factor Engineering HFE Instrumentation and Control I&C
Institute of Electrical and Electronic engineers                      IEEE Interim Staff Guidance                                                ISG Leak-Before-Break                                                      LBB License Amendment Request                                              LAR Loss Of Coolant Accident                                              LOCA Non-Safety Related                                                    NSR Nuclear Instrumentation System                                        NIS Nuclear Regulatory Commission                                          NRC Priority Logic Module                                                  PLM Quality Assurance                                                      QA Regulatory Guide                                                      RG Reactor                                                                Rx 29                Non-proprietary information suitable for public disclosure


Acronym List (continued)
29 Acronym List (continued)
Reactor Coolant System                                                RCS Reactor Protection System                                            RPS Safety Evaluation Report                                              SER Safety Injection                                                      SI Safety Related                                                        SR Standard Review Plan                                                  SRP System Requirements Specification                                    SyRS Safety Visual Display Unit                                            SVDU Subsequent License Renewal                                            SLR Turkey Point                                                          PTN Vendor Oversight Program                                              VOP 30                Non-proprietary information suitable for public disclosure
Non-proprietary information suitable for public disclosure Institute of Electrical and Electronic engineers IEEE Interim Staff Guidance ISG Leak-Before-Break LBB License Amendment Request LAR Loss Of Coolant Accident LOCA Non-Safety Related NSR Nuclear Instrumentation System NIS Nuclear Regulatory Commission NRC Priority Logic Module PLM Quality Assurance QA Regulatory Guide RG Reactor Rx


Any reproduction, alteration, transmission to any third party or publication in whole or in part of this document and/or its content is prohibited unless Framatome has provided its prior and written consent.
30 Reactor Coolant System RCS Reactor Protection System RPS Safety Evaluation Report SER Safety Injection SI Safety Related SR Standard Review Plan SRP System Requirements Specification SyRS Safety Visual Display Unit SVDU Subsequent License Renewal SLR Turkey Point PTN Vendor Oversight Program VOP Non-proprietary information suitable for public disclosure Acronym List (continued)
This document and any information it contains shall not be used for any other purpose than the one for which they were provided. Legal action may be taken against any infringer and/or any person breaching the aforementioned obligations 31                  Non-proprietary information suitable for public disclosure}}
 
31 Any reproduction, alteration, transmission to any third party or publication in whole or in part of this document and/or its content is prohibited unless Framatome has provided its prior and written consent.
This document and any information it contains shall not be used for any other purpose than the one for which they were provided. Legal action may be taken against any infringer and/or any person breaching the aforementioned obligations Non-proprietary information suitable for public disclosure}}

Latest revision as of 17:03, 23 November 2024

Licensees Non-Proprietary Presentation (2 of 2) for August 23 and 25, 2021 Public Meeting
ML21232A017
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 08/20/2021
From:
Florida Power & Light Co
To:
Plant Licensing Branch II
Marshall M
References
L-2021-LRM-0007
Download: ML21232A017 (31)


Text

1 Turkey Point Unit 3 and Unit 4 Reactor Protection System Engineered Safety Feature Actuation System Nuclear Instrumentation System Replacements Safety System Replacement Project LAR NRC 7th Pre-submittal Meeting Telecon August 23 and August 25, 2021 CLOSED MEETING Non-proprietary information suitable for public disclosure

2 Non-proprietary information suitable for public disclosure

3 Agenda - Closed Portion-Aug 23 and 25 Closed Session - Aug 23rd

- Components not Addressed in Approved SER

- Equipment Qualification and Dedication

- Human Factors Engineering Program Update Closed Session - Aug 25th

- Application of Leak Detection in D3 Evaluation

- Command Prioritization

- Surveillance Reduction Activities

- Schedule Update

- Action Items and Follow-up Non-proprietary information suitable for public disclosure

4 Components Not Addressed in Approved Tricon SER Non-proprietary information suitable for public disclosure

5 Safety Video Display Unit (SVDU)

Non-proprietary information suitable for public disclosure

6 Proposed Nuclear Instrumentation Signal Processing Non-proprietary information suitable for public disclosure

7 NIS Components (TXS) - Framatome GmbH Non-proprietary information suitable for public disclosure

8 New Manufactured NIS Components - Framatome Inc.

end of topic Non-proprietary information suitable for public disclosure

9 Equipment Qualification Non-proprietary information suitable for public disclosure

10 Evaluation and Acceptance of Commercial Equipment for Safety Related Applications end of topic Non-proprietary information suitable for public disclosure

11 Human Factors Engineering - Overview Non-proprietary information suitable for public disclosure

12 Human Factors Engineering - Elements Non-proprietary information suitable for public disclosure

13 Action Items and Follow-up for August 23rd Closed Meeting Action Items and Follow-up Non-proprietary information suitable for public disclosure

14 Turkey Point Unit 3 and Unit 4 Reactor Protection System Engineered Safety Feature Actuation System Nuclear Instrumentation System Replacements Safety System Replacement Project LAR NRC 7th Pre-submittal Meeting Telecon August 25, 2021 CLOSED MEETING Non-proprietary information suitable for public disclosure

15 Agenda Closed Session - Aug 25th

- Application of Leak Detection in D3 Evaluation

- Command Prioritization

- Surveillance Reduction Activities

- Schedule Update

- Action Items and Follow-up Non-proprietary information suitable for public disclosure

16 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Non-proprietary information suitable for public disclosure

17 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Non-proprietary information suitable for public disclosure

18 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Non-proprietary information suitable for public disclosure

19 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 Leak Detection Capability Non-proprietary information suitable for public disclosure

20 Leak Detection Capability Analysis for PTN 3&4 D3 Report in Accordance with BTP 7-19, Rev 8 end of topic Non-proprietary information suitable for public disclosure

21 Command Prioritization end of topic Non-proprietary information suitable for public disclosure

22 Technical Specification Surveillance Reduction Update Non-proprietary information suitable for public disclosure

23 Tech Spec Surveillance Test Extension/Reduction For RPS/ESFAS/NIS LAR - Coverage Boundary Non-proprietary information suitable for public disclosure

24 Tech Spec Surveillance Test Extension/Reduction For RPS/ESFAS/NIS LAR - Coverage Analysis end of topic Non-proprietary information suitable for public disclosure

25 Framatome Lifecycle Project Schedule end of topic Non-proprietary information suitable for public disclosure

26 Action Items and Follow-up for August 25th Closed Meeting Action Items and Follow-up Non-proprietary information suitable for public disclosure

27 Questions?

Non-proprietary information suitable for public disclosure

28 Acronym List Non-proprietary information suitable for public disclosure Actuation Logic Testing ALT Alternate Review AR Branch Technical Position BTP Channel Operational Testing COT Diverse Actuation System DAS Defense-in-Depth and Diversity D3 Distributed Control System DCS Engineered Safety Features Actuation System ESFAS Failure Modes, Effects and Diagnostic Analysis FMEDA Florida Power and Light FPL Foxboro Intelligent Automation I/A Human Factor Engineering HFE Instrumentation and Control I&C

29 Acronym List (continued)

Non-proprietary information suitable for public disclosure Institute of Electrical and Electronic engineers IEEE Interim Staff Guidance ISG Leak-Before-Break LBB License Amendment Request LAR Loss Of Coolant Accident LOCA Non-Safety Related NSR Nuclear Instrumentation System NIS Nuclear Regulatory Commission NRC Priority Logic Module PLM Quality Assurance QA Regulatory Guide RG Reactor Rx

30 Reactor Coolant System RCS Reactor Protection System RPS Safety Evaluation Report SER Safety Injection SI Safety Related SR Standard Review Plan SRP System Requirements Specification SyRS Safety Visual Display Unit SVDU Subsequent License Renewal SLR Turkey Point PTN Vendor Oversight Program VOP Non-proprietary information suitable for public disclosure Acronym List (continued)

31 Any reproduction, alteration, transmission to any third party or publication in whole or in part of this document and/or its content is prohibited unless Framatome has provided its prior and written consent.

This document and any information it contains shall not be used for any other purpose than the one for which they were provided. Legal action may be taken against any infringer and/or any person breaching the aforementioned obligations Non-proprietary information suitable for public disclosure