Letter Sequence Request |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARPMNS20201328, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2020-12-0909 December 2020 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML20338A0472020-12-0909 December 2020 December 9, 2020 FPL Slides Rps/Esfas Nuclear Instrumentation Project stage: Request PMNS20201397, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2020-12-16016 December 2020 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21011A2382021-01-11011 January 2021 Slides for January 13, 2021 Presubmittal Meeting with NextEra Concerning Digital I&C Closed Non-Proprietary Project stage: Request ML21011A2232021-01-22022 January 2021 Requests for Withholding Information from Public Disclosure Project stage: Other PMNS20210136, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2021-02-0404 February 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21047A2102021-02-16016 February 2021 NRC Presubmittal Meeting Telecon February 18, 2021 Open Meeting - FPL Safety System Replacement Project LAR - Nonproprietary Project stage: Meeting PMNS20210305, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade at Turkey Point Nuclear Generating, Unit Nos. 3 and 42021-03-29029 March 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade at Turkey Point Nuclear Generating, Unit Nos. 3 and 4 Project stage: Request ML21054A0012021-03-29029 March 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade Project stage: Meeting ML21096A0772021-04-0808 April 2021 FPL Slides for Meeting with FPL-Turkey Point Units 3 and 4 Concerning Digital Instrumentation and Control Modification Project stage: Request ML21096A0612021-04-0808 April 2021 FPL Slides for Meeting with FPL-Turkey Point Units 3 and 4 Concerning Digital Instrumentation and Control Modification - Open Project stage: Request ML21099A1052021-04-23023 April 2021 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance PMNS20210737, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2021-05-28028 May 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21159A1652021-06-0404 June 2021 Affidavit for Nextera Tricon Presentation for Turkey Point 5th Presubmittal Meeting Project stage: Meeting ML21159A1892021-06-0909 June 2021 Non-Proprietary - FPL NRC Presubmittal Meeting June 9th Closed Slides Project stage: Meeting ML21159A1712021-06-0909 June 2021 FPL NRC Presubmittal Meeting June 10th Week Open Session Project stage: Meeting ML21176A0102021-06-29029 June 2021 Summary of Drop-in Meeting with NextEra-Florida Power and Light to Discuss Pending Submittals Related to Digital Instrumentation and Controls and Improved Standard Technical Specifications for Turkey Point Nuclear Plant, Units 3 & 4 (EPID L Project stage: Meeting ML21172A2712021-06-29029 June 2021 Request for Withholding Information from Public Disclosure for Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Withholding Request Acceptance PMNS20210933, Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and2021-07-12012 July 2021 Partially Closed Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control Upgrade and Standard Technical Specifications Update at Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Request ML21200A1472021-07-22022 July 2021 Nextera/Fpl Meeting Slides for July 22, 2021 Partially Closed Meeting Concerning Control Room Digital Modernization - Closed Public Project stage: Request ML21200A1562021-07-22022 July 2021 Nextera/Fpl Meeting Slides for July 22, 2021 Partially Closed Meeting Concerning Control Room Digital Modernization - Open Project stage: Request ML21190A1862021-08-0202 August 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 Project stage: Meeting ML21232A0172021-08-20020 August 2021 Licensees Non-Proprietary Presentation (2 of 2) for August 23 and 25, 2021 Public Meeting Project stage: Meeting ML21279A0962021-08-20020 August 2021, 23 August 2021, 15 October 2021 Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade for Turkey Point, Units 3 and 4 Project stage: Request ML21235A0932021-08-23023 August 2021 Licensees Non-Proprietary Presentation (1 of 2) for August 23 and 25, 2021 Public Meeting Project stage: Meeting PMNS20211047, Pre-submittal Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control License Amendment Request for Turkey Point Nuclear Generating Unit Nos. 3 and 42021-08-23023 August 2021 Pre-submittal Meeting with NextEra Energy/Florida Power & Light Company to Discuss a Pending Digital Instrumentation and Control License Amendment Request for Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Meeting ML21279A0432021-10-15015 October 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade for Turkey Point, Units 3 and 4 Project stage: Meeting ML21246A0212021-11-23023 November 2021 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point Units 3 and 4 Project stage: Meeting ML21214A1192021-11-23023 November 2021 Request for Withholding Information from Public Disclosure for Turkey Point Nuclear Generating Unit Nos. 3 and 4 Project stage: Withholding Request Acceptance ML21302A0052021-12-23023 December 2021 Email to Nextera/Fpl Re Discussion of Availability of Human Factor Validation Information to Support the Planned Turkey Point Digital I&C License Amendment Request Project stage: Other PMNS20220162, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Florida Power & Light Company (FPL) to Discuss Planned Digital Instrumentation and Controls License Amendment Request for Turkey Point Nuclear Generating, Units 3 and 42022-02-25025 February 2022 Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Florida Power & Light Company (FPL) to Discuss Planned Digital Instrumentation and Controls License Amendment Request for Turkey Point Nuclear Generating, Units 3 and 4 Project stage: Meeting ML22063A4482022-03-0202 March 2022 Nextera/Fpl Affidavit for Proprietary Presentation for March 7, 2022, Public Meeting Project stage: Meeting ML22082A2222022-03-23023 March 2022 Terrapower Slide Presentation for Met Tower Water Supply Public Meeting Project stage: Request PMNS20220150, Pre-application Meeting with Terrapower to Discuss the Meteorological Data and Plant Water Source for the Natrium Plant Design2022-03-28028 March 2022 Pre-application Meeting with Terrapower to Discuss the Meteorological Data and Plant Water Source for the Natrium Plant Design Project stage: Meeting ML22101A2042022-04-0606 April 2022 Nextera/Fpl Affidavit for Proprietary Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request Project stage: Meeting ML22101A2262022-04-11011 April 2022 NRC Staff Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request Project stage: Meeting ML22098A0932022-04-13013 April 2022 Nextera/Fpl Redacted Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request (Public Version) Project stage: Meeting ML22098A0902022-04-13013 April 2022 Nextera/Fpl Non-Proprietary Presentation for April 13, 2022 Public Meeting Re Planned Turkey Point Digital Instrumentation and Controls License Amendment Request (EPID L-2021-LRM-0007) (Slides) Project stage: Meeting ML22129A1812022-05-11011 May 2022 Summary of Pre-Application Meetings with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 Project stage: Meeting ML22137A2512022-05-19019 May 2022 Summary of Pre-Application Meeting with Florida Power and Light Concerning a Proposed Digital Instrumentation and Control Upgrade on Turkey Point, Units 3 and 4 Project stage: Meeting ML22189A2092022-07-20020 July 2022 March 30, 2022, Summary of Public Meeting with Terrapower, LLC to Discuss the Meteorological Data and Plant Water Source for the Natrium Reactor Project stage: Meeting 2021-06-09
[Table View] |
Text
1 Turkey Point Unit 3 and Unit 4 Reactor Protection System Engineered Safety Feature Actuation System Nuclear Instrumentation System Replacements Non-proprietary information suitable for public disclosure Safety System Replacement Project LAR NRC 6th Pre-submittal Meeting Telecon July 22, 2021 OPEN MEETING
2 Open Session
- FPL License Amendment Request (LAR) Submittals
- Vendor Oversight Plan Update and Detail Discussion
- Next Pre-submittal Meeting Agenda Items Closed Session
- Diverse Actuation System (DAS) Architecture and Reliability
- Leak-Before-Break Discussion on D3
- Modification Code Year Discussion for LAR Non-proprietary information suitable for public disclosure Agenda - Open and Closed Sessions
3
- Steve Catron - Licensing Fleet Manager
- Jarrett Mack - Fleet Licensing Lead
- David Stoia - Turkey Point Site Licensing Lead
- Bill Maher - Improved Technical Specification Project Director
- Brian Dunn - Fleet Design Director
- Phil Barnes - Design Engineering Manager
- Wes Frewin - Fleet Digital Design Supervisor
- Warren Busch - Project Engineer
- Phillip Tiemann - Fuels / Safety Analysis
- Ron Legrand - Project Manager
- Brian Haynes - Licensing Lead
- Taha Abdelnaeem - Engineering Lead
- Ted Quinn - Licensing Engineer
- Jerry Mauck - Licensing Engineer
- Ron Jarrett - Licensing Engineer
- Bill Hannaman - Licensing Engineer
- Michael Howard - Safety Analysis
- Tom Geary - Design Engineering
- Sargent & Lundy -Third Party Review
- Pareez Golub Introductions - Project Team Non-proprietary information suitable for public disclosure
4 Follow-up to remarks on resource and schedule challenges 3 submittals under NRC review concurrently for PTN; two apply to PTN for ITS and RPS/ESFAS System Replacements Improved Standard Technical Specification (ITS)
Changes within scope of NUREG 1431, Rev. 5 Regular communications with NRC TS Branch on scope control RPS/ESFAS System Replacements LAR approval Fall 2022 provides confidence in planning for PTN Unit 3 Spring 2023 outage. FPL supports:
Minimize applications that are first time NRC reviews Frequent interaction before submittal and during reviews Quick turnaround on requests for information Open to discuss other time-savings measures Non-proprietary information suitable for public disclosure FPL LAR Submittals
5 Vendor Oversight Plan Status Update Non-Proprietary Information suitable for public disclosure Plan issued, currently Revision 0, LAR summary in draft Oversight of Framatome issued documents in progress
- Documented in comment resolution forms
- Traceable transmittals between Framatome and FPL
- Review task reconciling with production schedule activities Audits and Inspections performed
- Performed at Lynchburg and Mansfield facilities
- Quality Assurance initial program audits
- Cyber Security inspection of Secure Development Environment
- Documented in Quality Assurance Reports
6 Vendor Oversight Plan and Summary Level of Detail Document Type Intended Process Level of detail intended to support LAR Summary Docketed, revised only upon deviation Basis for safety evaluation determinations Threshold for NRC notification of changes Vendor Oversight Plan (VOP)
Available, updated during project Basis for VOP LAR summary Planning of oversight activities, schedule Identifiers Document performed activities, roadmap Implementation Inspection, FPL maintained documents Specific document number and revision Specific reviewers Comments and resolutions/acceptance Corrective Action Program (not affecting LAR summary)
Non-Proprietary Information suitable for public disclosure
7 Vendor Oversight Plan Summary Detail (1 of 2)
Criteria/Content Evaluated for LAR Change (examples)
Not impacting LAR summary Organization Procedure structure Changes of oversight responsibility to different organization Oversight required outside the procedure structure Changes to personnel in defined roles Delegation of activities Scope of Activities Document or task of a type listed in the summary is removed from scope of review Addition of a significant document or task of a type not in summary Changes to the LAR that warrant update of VOP Summary Adding documents or tasks of a type listed Document revisions Changes to schedule Combination of documents into fewer Methods Use of other than QA audits, comment resolution forms, reports with FPL approval, or the corrective action program to document oversight Change to a procedure that effects responsibility or relaxes acceptance criteria for an oversight task Transmittal of oversight related information or results to vendor Procedure revisions that do not affect scope or acceptance criteria Non-Proprietary Information suitable for public disclosure
8 Vendor Oversight Plan Summary Detail (2 of 2)
Criteria/Content Evaluated for LAR Change (examples)
Not impacting LAR summary Acceptance criteria If oversight activities cannot be performed to completion or comprehensive of scope for software development activities If vendor conformance to LAR stated implementation cannot be achieved.
Justified changes to code and standards applicable to a document Changes to document specific acceptance criteria Corrective Action Corrective Action Program used to determine what actions necessary.
CR for defect in a document found after document issued final CR to document the performance/results of an oversight activity Non-Proprietary Information suitable for public disclosure end of topic
9 Future Pre-submittal Meeting Recommended Agenda Items Open items Equipment replacement scope outside Tricon SER Command Prioritization Commercial grade dedication/qualification status Human Factors Engineering and simulator schedule Implementation Items Attachments to the LAR Non-proprietary information suitable for public disclosure
10 Thank you!
Questions/Comments?
Non-proprietary information suitable for public disclosure