Meeting Slides, Turkey Point Nuclear Plant, Units 3 and 4, Extended Power Uprate (Epu), NRC and FPL Public Meeting
ML11178A068
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 06/23/2011
From:
Florida Power & Light Co
To: Jason Paige
Plant Licensing Branch II
Shared Package
ML11195A170 List:
References
TAC ME4907, TAC ME4908
Download: ML11178A068 (21)


Text

Agenda

  • Opening
  • Purpose
  • EPU License Amendment Request (LAR) Review Summary
  • Proposed Technical Specification Changes
  • Mechanical and Civil Outstanding Questions
  • Nuclear Performance and Code Review

- Boron Precipitation Analysis Discussion

  • Containment and Ventilation EPITOME Analysis
  • Reactor Systems Branch Questions
  • Questions
  • Closing I=PL.

2

Turkey Point -- Opening

  • Appreciate the Staff's support and participation today
  • Significant progress made to date
  • FPL seeks clarification and understanding of remaining Staff questions
  • Encourage open and active dialogue to address open items from the Staff's review a=pL.

3

Turkey Point -- Purpose

  • Review status of Requests for Additional Information (RAls)
  • Discuss remaining questions and/or open items

4

EPU LAR Review Summary

  • 6 draft SEs are complete for the 17 branches
  • 4 draft SEs are in branch concurrence
  • Draft Environmental Assessment scheduled for 7/15/1
  • Focus today is to resolve any questions and/or open items remaining

- Technical Specifications - Confirm no questions or comments on proposed Technical Specifications Mechanical and Civil Engineering - Follow-up questions

- Nuclear Performance and Code - PHOENIX-P/ANC benchmarking and boron precipitation

- Containment and Ventilation - EPITOME issue

- Reactor Systems - outstanding RAls and RETRAN deck F=PL, 5

e:

+' ° ca U

II U(1),...

c.:::::s UJO

_-C cue:

ucu

-c J:

.c:(1)

(.)(1)

(1)UJ

~I tn (l)Q) tnc) 0e:

c.cu eJ:

D..O

<0

-C

Mechanical and Civil Engineering

  • Received 6 follow-up RAls on 6/20/11

- Spent Fuel Pool Cooling and Component Cooling Water modification design information

- Normal containment cooler modification design information

- Containment penetration anchor margins

- Use of actual material properties for reactor vessel supports

- Allowable stresses for control rod drive mechanisms

- Steam Generator fluid steam mixture velocity information

  • Clarification discussion today
  • Preparing responses with a target of mid July 2011 I=PL.

7

Nuclear Performance and Code Review

  • Providing additional information regarding PHOENIX-PlANe benchmarking - Target early July

- Status of NRC confirmatory analysis Discuss and reach agreement on anticipated FPL actions based on lessons learned from the Point Beach EPU

-- Summarize conservatisms in the analysis

-- Provide additional discussion on operational considerations for small break LOCAs

-- Confirmation that charging pumps trip on safety injection

-- Provide at least 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> of margin between lineup for hot leg injection and the onset of boron precipitation

-- Other actions?

FPL.

8

Nuclear Performance and Code Review Boric Acid Precipitation Timeline

s::

a u..

Cf)

Injection Mode 1 RHR Pump, 2 HHSI Pumps

/

Injection Mode 2 HHSI Pumps

.j 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and 10 minutes 1

Hot Leg Recircu ation Mode 2 HHSI Pumps 2 HHSI P umps Cold Leg Red,,"',,'oO Mode I..

  • 1 Time After LOCA H DelaY1 LT - RWST Low Low Level z

Tl - RWST Low Level To - Event Initiation Tl - 15 minutes T - 45 minutes z

To-Event Initation T3 - 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />, 30 minutes T. - 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, 40 minutes DelaYl - 2 minutes (EPU)

Delay T. - Incipient Boric Acid z l Precipitation Without Hot Leg Recirculation T3 - HLSO Initiation Delay - 3 minutes (EPU) z I=PL.

9

Containment and Ventilation - EPITOME Analysis

  • EPITOME code error involves LOCA mass and energy release calculation
  • Turkey Point containment analysis is impacted
  • Plant operability has been addressed
  • EPU LOCA and MSLB analyses performed EPITOME code error correction Range for containment free volume
  • Technical specification change proposed to lower limit on normal operating containment pressure from 3 psig to.

1 psig Include ITS improvement for administrative control of instrument air bleed 10 I=PL.

Containment and Ventilation - EPITOME Analysis

  • Other changes Modify the Emergency Containment Cooler (ECC) Start Logic to ensure 2 ECCs operate (new commitment)

Reduce upper operating band on Tav9 from 3°F to 1.soF Other input changes

  • Draft Results 11 I=PL.

Containment and Ventilation - EPITOME LOCA Draft Results

--- Containment Pressure. OEPS MINSI


Containment Pressure, OEPS MINSI Rev ised r--...

(f)

D..

"-/

J D1 IJ)

OJ OO~I----------------------------------~

5{)

.Q' 40

~ YJ n=20

..... :....//.-:\\\\...... :........ :........:........ :........

  • \\
  • \\

.......*......... :........ :.l.\\... :........ :........ :........ :........

  • \\
\\

\\

.....*.. :........ :........ :.... '\\i ' ~:'.\\'... :........ :........ :........

..*................................ :.. \\, '.'\\:........ :........:........

\\....

. \\ X ***** ** *** *** ** **

  • 1Q1'.......................................... :...,,, ~.

oI

1111111, 11 11 1",

I! II,

I I ""'I

'I ""',

! '"1111 f IIII!I, 111""1

~

1 2

J

~

5

~

7 8

10 10 10 10 10 10 10 10 10 Time (3) 12 Contoinment Temperature. OEPS MINSI


Containment Temperoture, OEPS MINSI Revised jOO~I------------------------------------~

~

2 1;/\\

-.IlJ

\\. -...;' "...*....***...*. *.*.... *.*.., ***

l.L d

~,

'f 40

~

~

..2

~ 200 1.....*...................................~~....... :.....,.. :.......*

~

E OJ f-150-.......................,............................ -..................

I 11111111 1111111 1111111 1111111 11111111 11111111 11111111 11111111 100 I

I I

I I

I I

~

1 2

j 4

~

6 7

a 10 10 10 10 10 10 10 10 10 Time (s)

FPL.

Containment and Ventilation - EPITOME MSLB Draft Results Containment Pressure. 1*0 sq ft Split


. Co n tainment Pressure. 1.0 sq ft Split Revised 60-'-'--------------------,

50

~

.12' 40 (J)

Q

'---./

~ 30

s (J)

(J)

Q) ct 20 10 O +I~~~~~~~~~~~-L~~~~_.~--L-~

o 200 400 600 800 1000 Transient Time (sec)

Con tai nmen t Temperature. 30 % Power DER MSCV


. Containment Temperature. HZP DER MSCV Revised 3511 ~\\

300

/"'. 250 LL

~

J 200

+-'

0 L

~ 150 E

Q)

I 100 50 0

0 200 400 600 BOD 1000 Transient Time (sec) 13 FPL.

Containment and Ventilation - EPITOME

  • Areas requiring revised analysis (applicable LAR sections in parentheses)

Component Cooling Water Systems (2.5.4.3)

Primary Containment Functional Design (2.6.1)

Mass and Energy Release (2.6.3)

Containment Heat Removal (2.6.5)

  • Determined to be acceptable 14 FPL.

Containment and Ventilation - EPITOME

  • Other areas reviewed and determined no impact (applicable LAR sections in parentheses)

Protective Coating Systems (2.1.7)

Balance of Plant Piping, Components and Supports (2.2.2.2)

Safety-Related Valves and Pumps (2.2.4)

Environmental Qualification of Electrical Equipment (2.3.1)

Pressure Analysis for ECCS Performance Capability (2.6.6)

Containment Ventilation System (2.7.7)

ECCS and Loss-of-Coolant Accidents (2.8.5.6.3)

Radiological Consequences Analyses Using AST (2.9.2)

  • No change to LAR section conclusions for impact of EPU 15 FPL.

w

E 0

I-a..

w I

c:

0 CO -

c:

(1) >

-c c:

ca c

(1)

E c

ca c:

0 0

l 0

"'C c:

ca

.c:

(1)

(1)

(f)

I L.

(1)

(1)

..J (1) tn c:

0 c.

tn (1) a::::

'to0 (1).t:-.....

l 0

j ea

<D

Reactor Systems Branch Questions

  • Received 31 non-LOCA RAls on 6/10/11 Conducted clarification call on 6/20/11 Preparing responses with a target issue of mid-July 2011
  • Further discussion on the following:

NUREG 0800 requirement regarding credited reactor trips for loss of load analysis

- Analysis of credible main steam line breaks

- eves malfunction in Modes 3, 4, and 5 (j

17 I=PL.

Reactor Systems Branch Questions

  • Received additional RAls:

10on6/14/11

- 7on6/17/11

- Anticipate remaining questions by 6/23/11

- Clarification discussion today Preparing responses with a target of mid July 2011

  • Further discussion on the following:

Inadvertent opening of a PORV

- Additional information regarding LBLOCA nodalization 18 FPL..

Reactor Systems Branch Questions

  • RETRAN Deck Modified Turkey Point base deck to be compatible with RETRAN3D

- Westinghouse transmitted to NRC on 6/21/11 Personnel available today to assist the Staff with running RETRAN with the modified base deck to ensure its compatibility with Staff software 19 F=PL.

3:

Cl)

Cl)

Cl)

..s::...

0 0

tn tn C

Cl) 0 (J

~

c tn G) :s..c'"

Cl) a.c...

I 0

E c

0

.-o....s-

n.

tn c 0

~.- (""'-

G)

.... tn tn",

~ Cl)Cl)

s '
s Oca N

~

0

Turkey Point - Closing

  • FPL respond to remaining RAls and clarification requests
  • Staff to complete remaining draft SE input
  • Draft SE to ACRS Subcommittee in August
  • Prepare for ACRS Subcommittee meeting in September and ACRS Full Committee meeting in October 21 I=PL.