ML080380005: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
(2 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 04/16/2008 | | issue date = 04/16/2008 | ||
| title = Issuance of Amendment No. 215 Use of Optimized ZIRLO-TM Fuel Rod Cladding | | title = Issuance of Amendment No. 215 Use of Optimized ZIRLO-TM Fuel Rod Cladding | ||
| author name = Kalyanam N | | author name = Kalyanam N | ||
| author affiliation = NRC/NRR/ADRO/DORL/LPLIV | | author affiliation = NRC/NRR/ADRO/DORL/LPLIV | ||
| addressee name = | | addressee name = | ||
Line 19: | Line 19: | ||
=Text= | =Text= | ||
{{#Wiki_filter:April 16, 2008 | {{#Wiki_filter:April 16, 2008 Vice President, Operations Entergy Operations, Inc. | ||
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-3093 | |||
Vice President, Operations | |||
==SUBJECT:== | ==SUBJECT:== | ||
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - ISSUANCE OF AMENDMENT RE: | WATERFORD STEAM ELECTRIC STATION, UNIT 3 - ISSUANCE OF AMENDMENT RE: USE OF OPTIMIZED ZIRLO' FUEL ROD CLADDING (TAC NO. MD5370) | ||
==Dear Sir or Madam:== | ==Dear Sir or Madam:== | ||
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Amendment No. 215 to Facility Operating License No. NPF-38 for the Waterford Steam Electric Station, Unit 3. This amendment consists of changes to the Technical Specifications (TSs) in response to your application dated April 24, 2007, as supplemented by electronic mail dated February 12, 2008. | The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Amendment No. 215 to Facility Operating License No. NPF-38 for the Waterford Steam Electric Station, Unit 3. This amendment consists of changes to the Technical Specifications (TSs) in response to your application dated April 24, 2007, as supplemented by electronic mail dated February 12, 2008. | ||
The amendment changes TS 5.3.1, Fuel Assemblies, to add Optimized ZIRLO' as an acceptable fuel rod cladding material. In addition, you requested an exemption to the cladding material specified in pursuant to Part 50, Section 46 of Title 10 of the Code of Federal Regulations (10 CFR), AAcceptance criteria for emergency core cooling systems [ECCS] for light-water nuclear power reactors,@ and Appendix K to 10 CFR Part 50, AECCS Evaluation Models@ to allow the use of Optimized ZIRLO' fuel rod cladding material in future core reload applications. | |||
The amendment changes TS 5.3.1, | |||
The NRC staff authorized the exemption by letter dated March 11, 2008, and it was published in the Federal Register on March 18, 2008 (73 FR 14502). | The NRC staff authorized the exemption by letter dated March 11, 2008, and it was published in the Federal Register on March 18, 2008 (73 FR 14502). | ||
A copy of our related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice. Sincerely, | A copy of our related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice. | ||
Sincerely, | |||
/RA/ | |||
N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-382 | |||
==Enclosures:== | ==Enclosures:== | ||
: 1. Amendment No. 215 to NPF-38 | : 1. Amendment No. 215 to NPF-38 | ||
: 2. Safety Evaluation cc w/encls: See next page | |||
Pkg ML080380004, Amendment ML080380005, License/TS Pg ML080380006 | |||
(*) SE input memo (**) See previous concurrence OFFICE DORL/LPL4/PM DORL/LPL4/LA DSS/SNPB/BC DIRS/ITSB/BC OGC - no legal objection DORL/LPL4/BC NAME NKalyanam (**) JBurkhardt (**) AMendiola: EThrom for AM GWaig (**) RHolmes (**) THiltz DATE 2/21/08 2/19/08 2/21/08 2/25/08 2/27/08 4/15/08 Waterford Steam Electric Station, Unit 3 (2/25/08) cc: | |||
Parish President Council | Senior Vice President Mr. Timothy Pflieger Entergy Nuclear Operations Environmental Scientist - Supervisor P.O. Box 31995 REP&R-CAP-SPOC Jackson, MS 39286-1995 Louisiana Department of Environmental Quality Vice President, Oversight P.O. Box 4312 Entergy Nuclear Operations Baton Rouge, LA 70821-4312 P.O. Box 31995 Jackson, MS 39286-1995 Parish President Council St. Charles Parish Senior Manager, Nuclear Safety P.O. Box 302 | ||
& Licensing Hahnville, LA 70057 Entergy Nuclear Operations P.O. Box 31995 Chairman Jackson, MS 39286-1995 Louisiana Public Services Commission P.O. Box 91154 Senior Vice President Baton Rouge, LA 70825-1697 | |||
Resident Inspector Waterford NPS P.O. Box 822 | & Chief Operating Officer Entergy Operations, Inc. Mr. Richard Penrod, Senior Environmental P.O. Box 31995 Scientist/State Liaison Officer Jackson, MS 39286-1995 Office of Environmental Services Northwestern State University Associate General Counsel Russell Hall, Room 201 Entergy Nuclear Operations Natchitoches, LA 71497 P.O. Box 31995 Jackson, MS 39286-1995 Resident Inspector Waterford NPS Manager, Licensing P.O. Box 822 Entergy Operations, Inc. Killona, LA 70057-0751 Waterford Steam Electric Station, Unit 3 17265 River Road Regional Administrator, Region IV Killona, LA 70057-3093 U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 | ||
Regional Administrator, Region IV | |||
ENTERGY OPERATIONS, INC. | ENTERGY OPERATIONS, INC. | ||
DOCKET NO. 50-382 WATERFORD STEAM ELECTRIC STATION, UNIT 3 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 215 License No. NPF-38 | DOCKET NO. 50-382 WATERFORD STEAM ELECTRIC STATION, UNIT 3 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 215 License No. NPF-38 | ||
: 1. The Nuclear Regulatory Commission (the Commission) has found that: | : 1. The Nuclear Regulatory Commission (the Commission) has found that: | ||
A. The application for amendment by Entergy Operations, Inc. (EOI), dated April 24, 2007, as supplemented by electronic mail dated February 12, 2008, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and | A. The application for amendment by Entergy Operations, Inc. (EOI), dated April 24, 2007, as supplemented by electronic mail dated February 12, 2008, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied. | ||
: 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.2 of Facility Operating License No. NPF-38 is hereby amended to read as follows: | |||
E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied. | : 2. Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 215, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the license. EOI shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan. | ||
: 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.2 of Facility Operating License No. NPF-38 is hereby amended to read as follows: | |||
: 2. Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 215, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the license. EOI shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan. | |||
: 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days from the date of issuance. | : 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days from the date of issuance. | ||
FOR THE NUCLEAR REGULATORY COMMISSION | FOR THE NUCLEAR REGULATORY COMMISSION | ||
/RA/ | |||
Thomas G. Hiltz, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation | |||
==Attachment:== | ==Attachment:== | ||
Changes to the Facility Operating License No. NPF-38 and | Changes to the Facility Operating License No. NPF-38 and Technical Specifications Date of Issuance: April 16, 2008 | ||
Facility Operating License REMOVE | ATTACHMENT TO LICENSE AMENDMENT NO. 215 TO FACILITY OPERATING LICENSE NO. NPF-38 DOCKET NO. 50-382 Replace the following pages of the Facility Operating License and Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change. | ||
Facility Operating License REMOVE INSERT Technical Specifications REMOVE INSERT 5-5 5-5 | |||
Technical Specifications REMOVE | |||
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 215 TO FACILITY OPERATING LICENSE NO. NPF-38 ENTERGY OPERATIONS, INC. | SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 215 TO FACILITY OPERATING LICENSE NO. NPF-38 ENTERGY OPERATIONS, INC. | ||
WATERFORD STEAM ELECTRIC STATION, UNIT 3 DOCKET NO. 50-382 | WATERFORD STEAM ELECTRIC STATION, UNIT 3 DOCKET NO. 50-382 | ||
==1.0 INTRODUCTION== | ==1.0 INTRODUCTION== | ||
By letter dated April 24, 2007 (Reference 1), as supplemented by electronic mail dated February 12, 2008 (Reference 6), Entergy Operations, Inc. (Entergy), the licensee, submitted a request for an amendment for Waterford Steam Electric Station, Unit 3 (Waterford 3). The proposed change to Technical Specification (TS) 5.3.1, | By letter dated April 24, 2007 (Reference 1), as supplemented by electronic mail dated February 12, 2008 (Reference 6), Entergy Operations, Inc. (Entergy), the licensee, submitted a request for an amendment for Waterford Steam Electric Station, Unit 3 (Waterford 3). The proposed change to Technical Specification (TS) 5.3.1, Fuel Assemblies, would add Optimized ZIRLO' as an acceptable fuel rod cladding material. Within the license amendment request (LAR), the licensee also requested an exemption to the cladding material specified in Part 50, Section 46 of Title 10 of the Code of Federal Regulations (10 CFR), AAcceptance criteria for emergency core cooling [ECCS] systems for light-water nuclear power reactors,@ and Appendix K to 10 CFR Part 50, AECCS Evaluation Models,@ to allow the use of Optimized ZIRLO' fuel rod cladding material in future core reload applications. | ||
The U.S. Nuclear Regulatory Commission (NRC) staff authorized the exemption by letter dated March 11, 2008, and it was published in the Federal Register on March 18, 2008 (73 FR 14502). | The U.S. Nuclear Regulatory Commission (NRC) staff authorized the exemption by letter dated March 11, 2008, and it was published in the Federal Register on March 18, 2008 (73 FR 14502). | ||
The supplemental electronic mail dated February 12, 2008, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staff's original proposed no significant hazards consideration determination as published in the Federal Register on May 22, 2007 (72 FR 28720). | The supplemental electronic mail dated February 12, 2008, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staff's original proposed no significant hazards consideration determination as published in the Federal Register on May 22, 2007 (72 FR 28720). | ||
==2.0 REGULATORY EVALUATION== | ==2.0 REGULATORY EVALUATION== | ||
Part 50 of 10 CFR includes the | Part 50 of 10 CFR includes the NRCs requirement that TS shall be included by applicants for a license authorizing operation of a production or utilization facility. Paragraph 10 CFR 50.36(d) requires that TS include items in five specific categories related to station operation. These categories are (1) safety limits, limiting safety system settings, and limiting control settings; (2) limiting conditions for operations; (3) surveillance requirements; (4) design features; and (5) administrative controls. The proposed change to TS 5.3.1 is within the safety limits category. | ||
Regulatory guidance for the review of fuel rod cladding materials and fuel system designs and adherence to applicable General Design Criteria is provided in NUREG-0800, AStandard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants | Regulatory guidance for the review of fuel rod cladding materials and fuel system designs and adherence to applicable General Design Criteria is provided in NUREG-0800, AStandard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants@ (SRP), Section 4.2, AFuel System Design.@ In accordance with SRP Section 4.2, the objectives of the fuel system safety review are to provide assurance that: | ||
@ (SRP), Section 4.2, AFuel System Design. | |||
@ | |||
* The fuel system is not damaged as a result of normal operation and anticipated operational occurrences, | * The fuel system is not damaged as a result of normal operation and anticipated operational occurrences, | ||
* Fuel system damage is never so severe as to prevent control rod insertion when it is required, | * Fuel system damage is never so severe as to prevent control rod insertion when it is required, | ||
* The number of fuel rod failures is not underestimated for postulated accidents, and | * The number of fuel rod failures is not underestimated for postulated accidents, and | ||
* Coolability is always maintained. | * Coolability is always maintained. | ||
In addition to licensed reload methodologies, an approved mechanical design methodology is utilized to demonstrate compliance with SRP 4.2 fuel design criteria. The NRC staff has previously reviewed and approved Optimized ZILRO | In addition to licensed reload methodologies, an approved mechanical design methodology is utilized to demonstrate compliance with SRP 4.2 fuel design criteria. The NRC staff has previously reviewed and approved Optimized ZILRO' cladding material for application in Westinghouse and Combustion Engineering fuel assembly designs (Reference 2). | ||
The LAR involves adding Optimized ZIRLO' as an acceptable fuel rod cladding material. The NRC staff=s review of TS 5.3.1 will verify that Optimized ZIRLO' fuel cladding material is applicable to the licensee and its implementation is done in accordance with established conditions and limitations. | |||
The LAR involves adding Optimized ZIRLO | Pursuant to 10 CFR 50.12, ASpecific Exemptions,@ Entergy has requested an exemption to 10 CFR 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors, and Appendix K to 10 CFR Part 50, ECCS Evaluation Models. The regulation in 10 CFR 50.46 contains acceptance criteria for ECCS for reactors fueled with zircaloy or ZIRLO' cladding. In addition, Appendix K to 10 CFR Part 50 requires that the Baker-Just equation be used to predict the rates of energy release, hydrogen concentration, and cladding oxidation from the metal-water reaction. | ||
Pursuant to 10 CFR 50.12, ASpecific Exemptions,@ Entergy has requested an exemption to 10 CFR 50.46, | The exemption request relates solely to the specific types of cladding material specified in these regulations. As written, the regulations presume the use of zircaloy or ZIRLO' fuel rod cladding. Thus, an exemption from the requirements of 10 CFR 50.46 and Appendix K to 10 CFR Part 50 is needed to allow a cladding alloy other than zircaloy or ZIRLO'. | ||
The exemption request relates solely to the specific types of cladding material specified in these regulations. As written, the regulations presume the use of zircaloy or ZIRLO | Note that a recent revision to 10 CFR 50.44 removed any specification of cladding material (e.g., zircaloy or ZIRLO'). This regulation specifies requirements for the control of hydrogen gas generated after a postulated loss-of-coolant accident for reactors fueled with zirconium cladding. As a result of this revision, an exemption to 10 CFR 50.44 is no longer required for different zirconium cladding alloys. | ||
Note that a recent revision to 10 CFR 50.44 removed any specification of cladding material (e.g., zircaloy or ZIRLO | |||
==3.0 TECHNICAL EVALUATION== | |||
= | |||
= | |||
The proposed change to TS 5.3.1, AFuel Assemblies,@ was provided in Attachment 2 of Reference 1. The proposed change consists of adding the text Aor Optimized ZIRLO'@ within the sentence describing fuel rods. In Reference 2, the NRC staff had approved Optimized ZIRLO' fuel cladding based on (1) similarities with standard ZIRLO', (2) demonstrated material performance, and (3) a commitment to provide irradiated data and validate fuel performance models ahead of burnups achieved in batch application. | |||
The NRC staff=s safety evaluation (SE) for Optimized ZIRLO' (contained within Reference 2) includes ten conditions and limitations. The licensee has documented compliance with these ten conditions and limitations in Attachment 1 of Reference 1 and has committed to ensuring compliance for future reloads in Attachment 4 of Reference 1. With the exception of Condition #6 and #7, the NRC staff has reviewed the licensee=s compliance with each of the ten SE conditions and limitations and finds each acceptable. | |||
SE Condition #6 and #7 relate to validating in-reactor performance and fuel performance models based on Lead Test Assembly (LTA) data ahead of batch application. In Attachment 1 of Reference 1, the licensee refers to a Westinghouse letter (Reference 3) to demonstrate compliance with these two SE conditions up through the projected burnup of the first cycle. | |||
Citing the availability of more recent data, the NRC staff requested that the Westinghouse compliance letter be updated. The revised SE compliance letter (Reference 4) contains LTA pool-side measurements from more recent fuel outages. | |||
In response to a NRC staff request, the Westinghouse provided a revised LTA compliance letter (Reference 5) which added model predictions along with measured parameters. This information was necessary to confirm the adequacy of current fuel performance models. After reviewing the LTA data, the NRC staff finds that the licensee has demonstrated acceptable in-reactor performance and the adequacy of model predictions up through the first cycle burnup. | In response to a NRC staff request, the Westinghouse provided a revised LTA compliance letter (Reference 5) which added model predictions along with measured parameters. This information was necessary to confirm the adequacy of current fuel performance models. After reviewing the LTA data, the NRC staff finds that the licensee has demonstrated acceptable in-reactor performance and the adequacy of model predictions up through the first cycle burnup. | ||
One of the main objectives of the ongoing Westinghouse creep program was to confirm the adequacy of the PAD creep models (same as FATES) for Optimized | One of the main objectives of the ongoing Westinghouse creep program was to confirm the adequacy of the PAD creep models (same as FATES) for Optimized ZIRLOTM and verify that the steady state irradiation creep rate is the same in tension and compression. After review of the creep program measurements, the NRC staff is not convinced that these objectives were fulfilled. Based upon the profilometry data in Figures 3 through 6 of Reference 5, the NRC staff finds that the creep models are adequate for the first operating cycle where the fuel rod cladding is predominately in compressive creep. However, based upon the material in Section 3.3.2 of Reference 5, the NRC staff has concerns with respect to tensile creep predictions and potential impacts on cladding liftoff pressure. Cladding liftoff is a concern toward end-of-life, and therefore, is of little concern during the first operating cycle. The licensee has committed to provide further demonstration of model accuracy prior to subsequent cycles. For the next reload, the licensee should scrutinize the tensile creep model predictions with respect to the latest creep program data in order to ensure that the underlying objectives of the Westinghouse creep program are fulfilled. | ||
Based upon information contained in the revised compliance letter (Reference 5), the NRC staff finds the licensee=s compliance with SE Condition #6 and #7 acceptable. The licensee has committed to confirm that Westinghouse has provided confirmatory LTA data and validated fuel | |||
Based upon information contained in the revised compliance letter (Reference 5), the NRC staff finds the licensee | |||
=s compliance with SE Condition #6 and #7 acceptable. The licensee has committed to confirm that Westinghouse has provided confirmatory LTA data and validated fuel | |||
== | performance to the NRC prior to subsequent cycles. The licensee has proposed to add WCAP-12610-P-A and CENPD-404-P-A, Addendum 1-A, AOptimized ZIRLOTM,@ July 2006, which contain SE conditions #6 and #7 to TS 6.6.5, Core Operating Limits Report (COLR).@ | ||
COMMITMENTS | The addition of the WCAP to TS 6.6.5 will require that the SE conditions will be met by the licensee for subsequent refueling cycles. | ||
: 1. The reload process for Waterford 3 will ensure the conditions and limitations of the NRC SER for Optimized | Based upon the NRC staff=s prior approval of Optimized ZIRLO' and the licensees current and future compliance with the SE conditions and limitations, the NRC staff finds the proposed change to TS 5.3.1 acceptable along with the future use of Optimized ZIRLO' fuel cladding material at Waterford 3. | ||
: 2. Entergy will confirm that Westinghouse will provide additional confirmatory data associated with LTA programs at other facilities prior to subsequent cycles of operation with Optimized | The NRC staff recognizes that implementing a new cladding material (and/or assembly design) along with its supporting analytical methods may impact calculated results for many design-basis accidents. Based on the NRC staff=s prior review and approval (Reference 2), the licensee will continue to comply with regulatory criteria. | ||
4.0 REGULATORY COMMITMENTS | |||
: 1. The reload process for Waterford 3 will ensure the conditions and limitations of the NRC SER for Optimized ZIRLOTM as addressed in Attachment 1 of Reference 1 are met when a batch of Optimized ZIRLOTM is implemented. | |||
: 2. Entergy will confirm that Westinghouse will provide additional confirmatory data associated with LTA programs at other facilities prior to subsequent cycles of operation with Optimized ZIRLOTM fuel rod cladding. Confirmation will continue until average burnup for the LTA programs at the other facilities reach the licensed average fuel rod burnup for Waterford 3 (60 gigawatt days per metric ton). | |||
The NRC staff finds that reasonable controls for the implementation and for subsequent evaluation of proposed changes pertaining to the regulatory commitments are best provided by the licensee's administrative processes, including its commitment management program. The regulatory commitments do not warrant the creation of regulatory requirements (items requiring prior NRC approval of subsequent changes). | |||
==5.0 STATE CONSULTATION== | |||
In accordance with the Commission's regulations, the Louisiana State official was notified of the proposed issuance of the amendment. The State official had no comments. | |||
==6.0 ENVIRONMENTAL CONSIDERATION== | |||
The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding | |||
published in the Federal Register on May 22, 2007 (72 FR 28720). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). | |||
Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments. | |||
==7.0 CONCLUSION== | ==7.0 CONCLUSION== | ||
The Commission has concluded, based on the considerations discussed above, that: | The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public. | ||
==8.0 REFERENCES== | ==8.0 REFERENCES== | ||
: 1. Letter from Entergy to U.S. Nuclear Regulatory Commission, ALicense Amendment Request to Allow the Use of Optimized ZIRLO | : 1. Letter from Entergy to U.S. Nuclear Regulatory Commission, ALicense Amendment Request to Allow the Use of Optimized ZIRLO' Fuel Rod Cladding,@ April 24, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML071160348). | ||
: 2. Westinghouse, WCAP-12610-P-A and CENPD-404-P-A, Addendum 1-A, AOptimized ZIRLO | : 2. Westinghouse, WCAP-12610-P-A and CENPD-404-P-A, Addendum 1-A, AOptimized ZIRLO',@ July 2006 (ADAMS Accession No. ML062080576, Proprietary, Non-Publicly Available). | ||
: 3. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, | : 3. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, SER [Safety Evaluation Report] Compliance with WCAP-12610-P-A and CENPD-404-P-A, Addendum 1-A >Optimized ZIRLO'=,@ January 4, 2007 (ADAMS Accession No. ML070100389, Proprietary, Non-Publicly Available). | ||
>Optimized ZIRLO | : 4. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, SER Compliance with WCAP-12610-P-A & CENPD-404-P-A Addendum 1-A >Optimized ZIRLO'=,@ | ||
=,@ January 4, 2007 (ADAMS Accession No. ML070100389, Proprietary, Non-Publicly Available). | November 6, 2007 (ADAMS Accession No. ML073130562, Proprietary, Non-Publicly Available). | ||
: 4. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, | : 5. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, ASER Compliance with WCAP-12610-P-A & CENPD-404-P-A Addendum 1-A Optimized ZIRLOTM, LTRNRC-07-58, Rev. 1, February 5, 2008 (ADAMS Accession No. ML080390452). | ||
>Optimized ZIRLO | : 6. Electronic Mail from R.L. Williams, Entergy Nuclear Operations, Inc., to N. Kalyanam, NRC/NRR/DORL/LPLIV, 2/12/2008 E-mail from Licensee Enclosing Markup of Technical Specification Page 5-5, Supplement to 4/24/2007 License Amendment Request Re: Use of Optimized ZIRLO-TM Fuel Rod Cladding, dated February 12, 2008 (ADAMS Accession No. ML080440127). | ||
=,@ November 6, 2007 (ADAMS Accession No. ML073130562, Proprietary, Non-Publicly Available). | Principal Contributor: P. Clifford Date: April 16, 2008}} | ||
: 5. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, ASER Compliance with WCAP-12610-P-A & CENPD-404-P-A Addendum 1-A | |||
: 6. Electronic Mail from R.L. Williams, Entergy Nuclear Operations, Inc., to N. Kalyanam, NRC/NRR/DORL/LPLIV, | |||
Principal Contributor: |
Latest revision as of 06:10, 13 March 2020
ML080380005 | |
Person / Time | |
---|---|
Site: | Waterford |
Issue date: | 04/16/2008 |
From: | Kalyanam N NRC/NRR/ADRO/DORL/LPLIV |
To: | Entergy Operations |
Kalyanam N, NRR/DORL/LPL4, 415-1480 | |
Shared Package | |
ML080380004 | List: |
References | |
TAC MD5370 | |
Download: ML080380005 (11) | |
Text
April 16, 2008 Vice President, Operations Entergy Operations, Inc.
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-3093
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - ISSUANCE OF AMENDMENT RE: USE OF OPTIMIZED ZIRLO' FUEL ROD CLADDING (TAC NO. MD5370)
Dear Sir or Madam:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Amendment No. 215 to Facility Operating License No. NPF-38 for the Waterford Steam Electric Station, Unit 3. This amendment consists of changes to the Technical Specifications (TSs) in response to your application dated April 24, 2007, as supplemented by electronic mail dated February 12, 2008.
The amendment changes TS 5.3.1, Fuel Assemblies, to add Optimized ZIRLO' as an acceptable fuel rod cladding material. In addition, you requested an exemption to the cladding material specified in pursuant to Part 50, Section 46 of Title 10 of the Code of Federal Regulations (10 CFR), AAcceptance criteria for emergency core cooling systems [ECCS] for light-water nuclear power reactors,@ and Appendix K to 10 CFR Part 50, AECCS Evaluation Models@ to allow the use of Optimized ZIRLO' fuel rod cladding material in future core reload applications.
The NRC staff authorized the exemption by letter dated March 11, 2008, and it was published in the Federal Register on March 18, 2008 (73 FR 14502).
A copy of our related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-382
Enclosures:
- 1. Amendment No. 215 to NPF-38
- 2. Safety Evaluation cc w/encls: See next page
Pkg ML080380004, Amendment ML080380005, License/TS Pg ML080380006
(*) SE input memo (**) See previous concurrence OFFICE DORL/LPL4/PM DORL/LPL4/LA DSS/SNPB/BC DIRS/ITSB/BC OGC - no legal objection DORL/LPL4/BC NAME NKalyanam (**) JBurkhardt (**) AMendiola: EThrom for AM GWaig (**) RHolmes (**) THiltz DATE 2/21/08 2/19/08 2/21/08 2/25/08 2/27/08 4/15/08 Waterford Steam Electric Station, Unit 3 (2/25/08) cc:
Senior Vice President Mr. Timothy Pflieger Entergy Nuclear Operations Environmental Scientist - Supervisor P.O. Box 31995 REP&R-CAP-SPOC Jackson, MS 39286-1995 Louisiana Department of Environmental Quality Vice President, Oversight P.O. Box 4312 Entergy Nuclear Operations Baton Rouge, LA 70821-4312 P.O. Box 31995 Jackson, MS 39286-1995 Parish President Council St. Charles Parish Senior Manager, Nuclear Safety P.O. Box 302
& Licensing Hahnville, LA 70057 Entergy Nuclear Operations P.O. Box 31995 Chairman Jackson, MS 39286-1995 Louisiana Public Services Commission P.O. Box 91154 Senior Vice President Baton Rouge, LA 70825-1697
& Chief Operating Officer Entergy Operations, Inc. Mr. Richard Penrod, Senior Environmental P.O. Box 31995 Scientist/State Liaison Officer Jackson, MS 39286-1995 Office of Environmental Services Northwestern State University Associate General Counsel Russell Hall, Room 201 Entergy Nuclear Operations Natchitoches, LA 71497 P.O. Box 31995 Jackson, MS 39286-1995 Resident Inspector Waterford NPS Manager, Licensing P.O. Box 822 Entergy Operations, Inc. Killona, LA 70057-0751 Waterford Steam Electric Station, Unit 3 17265 River Road Regional Administrator, Region IV Killona, LA 70057-3093 U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011
ENTERGY OPERATIONS, INC.
DOCKET NO. 50-382 WATERFORD STEAM ELECTRIC STATION, UNIT 3 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 215 License No. NPF-38
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Entergy Operations, Inc. (EOI), dated April 24, 2007, as supplemented by electronic mail dated February 12, 2008, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.2 of Facility Operating License No. NPF-38 is hereby amended to read as follows:
- 2. Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 215, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the license. EOI shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 60 days from the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Thomas G. Hiltz, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License No. NPF-38 and Technical Specifications Date of Issuance: April 16, 2008
ATTACHMENT TO LICENSE AMENDMENT NO. 215 TO FACILITY OPERATING LICENSE NO. NPF-38 DOCKET NO. 50-382 Replace the following pages of the Facility Operating License and Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Facility Operating License REMOVE INSERT Technical Specifications REMOVE INSERT 5-5 5-5
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 215 TO FACILITY OPERATING LICENSE NO. NPF-38 ENTERGY OPERATIONS, INC.
WATERFORD STEAM ELECTRIC STATION, UNIT 3 DOCKET NO. 50-382
1.0 INTRODUCTION
By letter dated April 24, 2007 (Reference 1), as supplemented by electronic mail dated February 12, 2008 (Reference 6), Entergy Operations, Inc. (Entergy), the licensee, submitted a request for an amendment for Waterford Steam Electric Station, Unit 3 (Waterford 3). The proposed change to Technical Specification (TS) 5.3.1, Fuel Assemblies, would add Optimized ZIRLO' as an acceptable fuel rod cladding material. Within the license amendment request (LAR), the licensee also requested an exemption to the cladding material specified in Part 50, Section 46 of Title 10 of the Code of Federal Regulations (10 CFR), AAcceptance criteria for emergency core cooling [ECCS] systems for light-water nuclear power reactors,@ and Appendix K to 10 CFR Part 50, AECCS Evaluation Models,@ to allow the use of Optimized ZIRLO' fuel rod cladding material in future core reload applications.
The U.S. Nuclear Regulatory Commission (NRC) staff authorized the exemption by letter dated March 11, 2008, and it was published in the Federal Register on March 18, 2008 (73 FR 14502).
The supplemental electronic mail dated February 12, 2008, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the NRC staff's original proposed no significant hazards consideration determination as published in the Federal Register on May 22, 2007 (72 FR 28720).
2.0 REGULATORY EVALUATION
Part 50 of 10 CFR includes the NRCs requirement that TS shall be included by applicants for a license authorizing operation of a production or utilization facility. Paragraph 10 CFR 50.36(d) requires that TS include items in five specific categories related to station operation. These categories are (1) safety limits, limiting safety system settings, and limiting control settings; (2) limiting conditions for operations; (3) surveillance requirements; (4) design features; and (5) administrative controls. The proposed change to TS 5.3.1 is within the safety limits category.
Regulatory guidance for the review of fuel rod cladding materials and fuel system designs and adherence to applicable General Design Criteria is provided in NUREG-0800, AStandard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants@ (SRP), Section 4.2, AFuel System Design.@ In accordance with SRP Section 4.2, the objectives of the fuel system safety review are to provide assurance that:
- The fuel system is not damaged as a result of normal operation and anticipated operational occurrences,
- Fuel system damage is never so severe as to prevent control rod insertion when it is required,
- The number of fuel rod failures is not underestimated for postulated accidents, and
- Coolability is always maintained.
In addition to licensed reload methodologies, an approved mechanical design methodology is utilized to demonstrate compliance with SRP 4.2 fuel design criteria. The NRC staff has previously reviewed and approved Optimized ZILRO' cladding material for application in Westinghouse and Combustion Engineering fuel assembly designs (Reference 2).
The LAR involves adding Optimized ZIRLO' as an acceptable fuel rod cladding material. The NRC staff=s review of TS 5.3.1 will verify that Optimized ZIRLO' fuel cladding material is applicable to the licensee and its implementation is done in accordance with established conditions and limitations.
Pursuant to 10 CFR 50.12, ASpecific Exemptions,@ Entergy has requested an exemption to 10 CFR 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors, and Appendix K to 10 CFR Part 50, ECCS Evaluation Models. The regulation in 10 CFR 50.46 contains acceptance criteria for ECCS for reactors fueled with zircaloy or ZIRLO' cladding. In addition, Appendix K to 10 CFR Part 50 requires that the Baker-Just equation be used to predict the rates of energy release, hydrogen concentration, and cladding oxidation from the metal-water reaction.
The exemption request relates solely to the specific types of cladding material specified in these regulations. As written, the regulations presume the use of zircaloy or ZIRLO' fuel rod cladding. Thus, an exemption from the requirements of 10 CFR 50.46 and Appendix K to 10 CFR Part 50 is needed to allow a cladding alloy other than zircaloy or ZIRLO'.
Note that a recent revision to 10 CFR 50.44 removed any specification of cladding material (e.g., zircaloy or ZIRLO'). This regulation specifies requirements for the control of hydrogen gas generated after a postulated loss-of-coolant accident for reactors fueled with zirconium cladding. As a result of this revision, an exemption to 10 CFR 50.44 is no longer required for different zirconium cladding alloys.
3.0 TECHNICAL EVALUATION
The proposed change to TS 5.3.1, AFuel Assemblies,@ was provided in Attachment 2 of Reference 1. The proposed change consists of adding the text Aor Optimized ZIRLO'@ within the sentence describing fuel rods. In Reference 2, the NRC staff had approved Optimized ZIRLO' fuel cladding based on (1) similarities with standard ZIRLO', (2) demonstrated material performance, and (3) a commitment to provide irradiated data and validate fuel performance models ahead of burnups achieved in batch application.
The NRC staff=s safety evaluation (SE) for Optimized ZIRLO' (contained within Reference 2) includes ten conditions and limitations. The licensee has documented compliance with these ten conditions and limitations in Attachment 1 of Reference 1 and has committed to ensuring compliance for future reloads in Attachment 4 of Reference 1. With the exception of Condition #6 and #7, the NRC staff has reviewed the licensee=s compliance with each of the ten SE conditions and limitations and finds each acceptable.
SE Condition #6 and #7 relate to validating in-reactor performance and fuel performance models based on Lead Test Assembly (LTA) data ahead of batch application. In Attachment 1 of Reference 1, the licensee refers to a Westinghouse letter (Reference 3) to demonstrate compliance with these two SE conditions up through the projected burnup of the first cycle.
Citing the availability of more recent data, the NRC staff requested that the Westinghouse compliance letter be updated. The revised SE compliance letter (Reference 4) contains LTA pool-side measurements from more recent fuel outages.
In response to a NRC staff request, the Westinghouse provided a revised LTA compliance letter (Reference 5) which added model predictions along with measured parameters. This information was necessary to confirm the adequacy of current fuel performance models. After reviewing the LTA data, the NRC staff finds that the licensee has demonstrated acceptable in-reactor performance and the adequacy of model predictions up through the first cycle burnup.
One of the main objectives of the ongoing Westinghouse creep program was to confirm the adequacy of the PAD creep models (same as FATES) for Optimized ZIRLOTM and verify that the steady state irradiation creep rate is the same in tension and compression. After review of the creep program measurements, the NRC staff is not convinced that these objectives were fulfilled. Based upon the profilometry data in Figures 3 through 6 of Reference 5, the NRC staff finds that the creep models are adequate for the first operating cycle where the fuel rod cladding is predominately in compressive creep. However, based upon the material in Section 3.3.2 of Reference 5, the NRC staff has concerns with respect to tensile creep predictions and potential impacts on cladding liftoff pressure. Cladding liftoff is a concern toward end-of-life, and therefore, is of little concern during the first operating cycle. The licensee has committed to provide further demonstration of model accuracy prior to subsequent cycles. For the next reload, the licensee should scrutinize the tensile creep model predictions with respect to the latest creep program data in order to ensure that the underlying objectives of the Westinghouse creep program are fulfilled.
Based upon information contained in the revised compliance letter (Reference 5), the NRC staff finds the licensee=s compliance with SE Condition #6 and #7 acceptable. The licensee has committed to confirm that Westinghouse has provided confirmatory LTA data and validated fuel
performance to the NRC prior to subsequent cycles. The licensee has proposed to add WCAP-12610-P-A and CENPD-404-P-A, Addendum 1-A, AOptimized ZIRLOTM,@ July 2006, which contain SE conditions #6 and #7 to TS 6.6.5, Core Operating Limits Report (COLR).@
The addition of the WCAP to TS 6.6.5 will require that the SE conditions will be met by the licensee for subsequent refueling cycles.
Based upon the NRC staff=s prior approval of Optimized ZIRLO' and the licensees current and future compliance with the SE conditions and limitations, the NRC staff finds the proposed change to TS 5.3.1 acceptable along with the future use of Optimized ZIRLO' fuel cladding material at Waterford 3.
The NRC staff recognizes that implementing a new cladding material (and/or assembly design) along with its supporting analytical methods may impact calculated results for many design-basis accidents. Based on the NRC staff=s prior review and approval (Reference 2), the licensee will continue to comply with regulatory criteria.
4.0 REGULATORY COMMITMENTS
- 1. The reload process for Waterford 3 will ensure the conditions and limitations of the NRC SER for Optimized ZIRLOTM as addressed in Attachment 1 of Reference 1 are met when a batch of Optimized ZIRLOTM is implemented.
- 2. Entergy will confirm that Westinghouse will provide additional confirmatory data associated with LTA programs at other facilities prior to subsequent cycles of operation with Optimized ZIRLOTM fuel rod cladding. Confirmation will continue until average burnup for the LTA programs at the other facilities reach the licensed average fuel rod burnup for Waterford 3 (60 gigawatt days per metric ton).
The NRC staff finds that reasonable controls for the implementation and for subsequent evaluation of proposed changes pertaining to the regulatory commitments are best provided by the licensee's administrative processes, including its commitment management program. The regulatory commitments do not warrant the creation of regulatory requirements (items requiring prior NRC approval of subsequent changes).
5.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Louisiana State official was notified of the proposed issuance of the amendment. The State official had no comments.
6.0 ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, and there has been no public comment on such finding
published in the Federal Register on May 22, 2007 (72 FR 28720). Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
7.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.
8.0 REFERENCES
- 1. Letter from Entergy to U.S. Nuclear Regulatory Commission, ALicense Amendment Request to Allow the Use of Optimized ZIRLO' Fuel Rod Cladding,@ April 24, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML071160348).
- 2. Westinghouse, WCAP-12610-P-A and CENPD-404-P-A, Addendum 1-A, AOptimized ZIRLO',@ July 2006 (ADAMS Accession No. ML062080576, Proprietary, Non-Publicly Available).
- 3. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, SER [Safety Evaluation Report] Compliance with WCAP-12610-P-A and CENPD-404-P-A, Addendum 1-A >Optimized ZIRLO'=,@ January 4, 2007 (ADAMS Accession No. ML070100389, Proprietary, Non-Publicly Available).
- 4. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, SER Compliance with WCAP-12610-P-A & CENPD-404-P-A Addendum 1-A >Optimized ZIRLO'=,@
November 6, 2007 (ADAMS Accession No. ML073130562, Proprietary, Non-Publicly Available).
- 5. Letter from Westinghouse to U.S. Nuclear Regulatory Commission, ASER Compliance with WCAP-12610-P-A & CENPD-404-P-A Addendum 1-A Optimized ZIRLOTM, LTRNRC-07-58, Rev. 1, February 5, 2008 (ADAMS Accession No. ML080390452).
- 6. Electronic Mail from R.L. Williams, Entergy Nuclear Operations, Inc., to N. Kalyanam, NRC/NRR/DORL/LPLIV, 2/12/2008 E-mail from Licensee Enclosing Markup of Technical Specification Page 5-5, Supplement to 4/24/2007 License Amendment Request Re: Use of Optimized ZIRLO-TM Fuel Rod Cladding, dated February 12, 2008 (ADAMS Accession No. ML080440127).
Principal Contributor: P. Clifford Date: April 16, 2008