{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL  60532-4352  December 20, 2016   Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL  60555  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL  60532
-4352  December 20, 2016 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road
 
Warrenville, IL  60555


==SUBJECT:==
==SUBJECT:==
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS - CLINTON POWER STATION, UNIT 1  
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS
- CLINTON POWER STATION, UNIT 1  


==Dear Mr. Hanson:==
==Dear Mr. Hanson:==
We have received your corporate letter RS-16-156, dated July 18, 2016, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2016-09, "Preparation and Scheduling of Operator Licensing Examinations."  In the letter, you requested no initial operator licensing examinations be scheduled through 2021 at the Clinton Power Station. Previously in station letter U-604281, dated May 23, 2016, you had requested initial license examination dates for January 2017, July 2018, and March 2019 at the Clinton Power Station. In response to your most recent letter, we have not scheduled these examination dates and have canceled the previously requested initial license examination dates of October 2018 and October 2020. In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/  Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 cc:  Distribution via LISTSERV Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555  
We have received your corporate letter RS-16-156, dated July 18, 2016, in response to U.S. Nuclear Regulatory Commission (
NRC) Regulatory Issue Summary 2016
-09, "Preparation and Scheduling of Operator Licensing Examinations."  In the letter, you requested no initial operator licensing examination s be scheduled through 2021 at the Clinton Power Station. Previously in station letter U-604281, dated May 23, 2016, you had requested initial license examination dates for January 2017, July 2018, and March 2019 at the Clinton Power Station.
In response to your most recent letter, we have not scheduled these examination dates and have canceled the previously requested initial license examination dates of October 2018 and October 2020.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room). Sincerely,
  /RA/  Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety
 
Docket No.
50-461 License No. NPF-62 cc:  Distribution via LISTSERV
 
Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555  


==SUBJECT:==
==SUBJECT:==
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS - CLINTON POWER STATION, UNIT 1  
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS
- CLINTON POWER STATION, UNIT 1


==Dear Mr. Hanson:==
==Dear Mr. Hanson:==
We have received your corporate letter RS-16-156, dated July 18, 2016, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2016-09, "Preparation and Scheduling of Operator Licensing Examinations."  In the letter, you requested no initial operator licensing examinations be scheduled through 2021 at the Clinton Power Station. Previously in station letter U-604281, dated May 23, 2016, you had requested initial license examination dates for January 2017, July 2018, and March 2019 at the Clinton Power Station. In response to your most recent letter, we have not scheduled these examination dates and have canceled the previously requested initial license examination dates of October 2018 and October 2020. In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Sincerely, /RA/  Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 cc:  Distribution via LISTSERV DISTRIBUTION: See next page ADAMS Accession Number:  ML16357A544 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII  RIII  RIII  RIII  NAME RKWalton:jw ROrlikowski   DATE 11/23/16 12/20/16  OFFICIAL RECORD COPY Letter to Mr. Bryan C. Hanson from Mr. Robert J. Orlikowski dated December 20, 2016  
 
We have received your corporate letter RS 156, dated July 18, 2016, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2016
-09, "Preparation and Scheduling of Operator Licensing Examinations."  In the letter, you requested no initial operator licensing examinations be scheduled through 2021 at the Clinton Power Station. Previously in station letter U
-604281, dated May 23, 2016, you had requested initial license examination dates for January 2017, July 2018, and March 2019 at the Clinton Power Station.
In response to your most recent letter, we have not scheduled these examination dates and have canceled the previously requested initial license examination dates of October 2018 and October 2020.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room). Sincerely,
  /RA/  Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety
 
Docket No.
50-461 License No. NPF-62 cc:  Distribution via LISTSERV DISTRIBUTION
: See next page ADAMS Accession Number:  ML16357A544 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII  RIII  RIII  RIII  NAME RKWalton:jw ROrlikowski DATE 11/23/16 12/20/16  OFFICIAL RECORD COPY Letter to Mr. Bryan C. Hanson from Mr. Robert J. Orlikowski dated December 20, 2016


==SUBJECT:==
==SUBJECT:==
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS - CLINTON POWER STATION, UNIT 1 DISTRIBUTION: Jeremy Bowen RidsNrrDorlLpl3-2 Resource RidsNrrPMClinton Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRSIII DRPIII Nancy Salgado Colleen Schmidt}}
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS
- CLINTON POWER STATION, UNIT 1 DISTRIBUTION
: Jeremy Bowen RidsNrrDorlLpl3
-2 Resource RidsNrrPMClinton Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRSIII DRPIII Nancy Salgado
 
Colleen Schmidt}}

Revision as of 00:29, 30 June 2018

Ltr 12/20/2016 Scheduling of Initial Operator License Examinations - Clinton Power Station, Unit 1 (Rkw)
ML16357A544
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/20/2016
From: Orlikowski R J
Operations Branch III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
Download: ML16357A544 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL 60532

-4352 December 20, 2016 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS

- CLINTON POWER STATION, UNIT 1

Dear Mr. Hanson:

We have received your corporate letter RS-16-156, dated July 18, 2016, in response to U.S. Nuclear Regulatory Commission (

NRC) Regulatory Issue Summary 2016

-09, "Preparation and Scheduling of Operator Licensing Examinations." In the letter, you requested no initial operator licensing examination s be scheduled through 2021 at the Clinton Power Station. Previously in station letter U-604281, dated May 23, 2016, you had requested initial license examination dates for January 2017, July 2018, and March 2019 at the Clinton Power Station.

In response to your most recent letter, we have not scheduled these examination dates and have canceled the previously requested initial license examination dates of October 2018 and October 2020.

In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room). Sincerely,

/RA/ Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety

Docket No.

50-461 License No. NPF-62 cc: Distribution via LISTSERV

Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS

- CLINTON POWER STATION, UNIT 1

Dear Mr. Hanson:

We have received your corporate letter RS 156, dated July 18, 2016, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2016

-09, "Preparation and Scheduling of Operator Licensing Examinations." In the letter, you requested no initial operator licensing examinations be scheduled through 2021 at the Clinton Power Station. Previously in station letter U

-604281, dated May 23, 2016, you had requested initial license examination dates for January 2017, July 2018, and March 2019 at the Clinton Power Station.

In response to your most recent letter, we have not scheduled these examination dates and have canceled the previously requested initial license examination dates of October 2018 and October 2020.

In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room). Sincerely,

/RA/ Robert J. Orlikowski, Chief Operations Branch Division of Reactor Safety

Docket No.

50-461 License No. NPF-62 cc: Distribution via LISTSERV DISTRIBUTION

See next page ADAMS Accession Number: ML16357A544 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME RKWalton:jw ROrlikowski DATE 11/23/16 12/20/16 OFFICIAL RECORD COPY Letter to Mr. Bryan C. Hanson from Mr. Robert J. Orlikowski dated December 20, 2016

SUBJECT:

SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS

- CLINTON POWER STATION, UNIT 1 DISTRIBUTION

Jeremy Bowen RidsNrrDorlLpl3

-2 Resource RidsNrrPMClinton Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRSIII DRPIII Nancy Salgado

Colleen Schmidt