ML20056A290: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:. - _ _  _ __ _. .          __      _ _ . . - . _ _      _        ._..      _ . _ _ _  _  _
{{#Wiki_filter:,
I T- HE                       Vice Pn,4 dent fu Academic         203 Bricker Hal' W                            Affales an i havont                 140 North Ovre Mall Columbus, O'd 432101358 Phone 61'e292 $881 UNIVERSITY   ._.
I T-HE Vice Pn,4 dent fu Academic 203 Bricker Hal' Affales an i havont 140 North Ovre Mall W
July 30, 1990 l
Columbus, O'd 432101358 Phone 61'e292 $881 UNIVERSITY July 30, 1990 l
i Document Control Desk U.S. Nuclear Regulatory Commission l       Washington, D. C.           20555 RE: Cecommissioning Funding Plan for The Ohio State University                             '
i Document Control Desk U.S. Nuclear Regulatory Commission l
Research Reactor, License R-75, Docket 5 -150 Gentlemen:
Washington, D.
As required by 10CFR50.33 (K),,this report is submitted to provide assurance that funds will be available to decommission The Ohio State University Research reactor, License R-75,                                           ,
C.
Docket 50-150.           These funds will be requested sufficiently in advance of decommissioning to prevent delay in the required activities.
20555 RE: Cecommissioning Funding Plan for The Ohio State University Research Reactor, License R-75, Docket 5 -150 Gentlemen:
As required by 10CFR50.33 (K),,this report is submitted to provide assurance that funds will be available to decommission The Ohio State University Research reactor, License R-75, Docket 50-150.
These funds will be requested sufficiently in advance of decommissioning to prevent delay in the required activities.
The cost estimate to decommission The OSU Research Reactor l
The cost estimate to decommission The OSU Research Reactor l
is $706,250 in 1990.             This estimate is based on the study
is $706,250 in 1990.
        " Technology, Safety and Costs of Decommissioning Reference Nuclear Research and Test Reactors", NUREG/CR 1756. Attached is the detail of methods and assumptions used to arrive at the figure.
This estimate is based on the study
" Technology, Safety and Costs of Decommissioning Reference Nuclear Research and Test Reactors", NUREG/CR 1756.
Attached is the detail of methods and assumptions used to arrive at the figure.
The Provost of The Ohio State University has been previously designated to the USNRC as the responsible University official under License R-75, Docket 50-150.
The Provost of The Ohio State University has been previously designated to the USNRC as the responsible University official under License R-75, Docket 50-150.
Sincerely, E. $
Sincerely, E. $
Frederick E. Hutchinson Vice President for Academic Affairs and Provost FEH/mab Attachment i
Frederick E. Hutchinson Vice President for Academic Affairs and Provost FEH/mab Attachment i
9008060306 900730 PDR     ADOCK 05000150 I
9008060306 900730 PDR ADOCK 05000150 I
PDC                                                               p
PDC p
                                                                                                        /// 1
///
1


    -    -      .                          -  ~     .. . - - - -        . -.      --    .. . .          _. - .      .
~
e    t(                                                                                                                     ,
t(
i Decommissioning Funding Plan for                                               :
e i
The Ohio State University Research Reactor License R-75 Docket 50-150 t
Decommissioning Funding Plan for The Ohio State University Research Reactor License R-75 Docket 50-150 t
In an effort to make a reasonable cost estimate for decommissioning one may                                   !
In an effort to make a reasonable cost estimate for decommissioning one may base this on the study " Technology, Safety and Costs of Decommissioning Reference Nuclear Research and Test Reactors" NURE0/CR1756. This study used 3
base this on the study " Technology, Safety and Costs of Decommissioning Reference Nuclear Research and Test Reactors" NURE0/CR1756. This study used                                   3 the Oregon State University TRIGA as its reference research reactor.
the Oregon State University TRIGA as its reference research reactor.
However, one must make adjustments due to the difference between the reactors and the time the study was completed.
However, one must make adjustments due to the difference between the reactors and the time the study was completed.
In order to estimate the cost of decommissioning the reactor by decontamination the following methods / assumptions were made.                                               l
In order to estimate the cost of decommissioning the reactor by decontamination the following methods / assumptions were made.
: 1. The cost of fuel shipment was not included since the NRC considers this an operational cost.                                                                 -
l
: 2. Inflation was estimated at 8%/ year based on OSUNRL labor                                           l costs since 2980/81.
: 1. The cost of fuel shipment was not included since the NRC considers this an operational cost.
: 2. Inflation was estimated at 8%/ year based on OSUNRL labor l
costs since 2980/81.
s
s
: 3. Staff labor requirements were based on Tables 10.1-2 and                                           .,
: 3. Staff labor requirements were based on Tables 10.1-2 and 10.1-3 from the above study with appropriate adjustments for
10.1-3 from the above study with appropriate adjustments for differences between the two eactors,
(
(
j                     4. Waste disposal was' estimated at $100/cu.ft. (based on the latest ~1U-ORS waste disposal bid) except for Co-60 which we estimated to cost more due to its high radiation level.
differences between the two eactors, j
: 4. Waste disposal was' estimated at $100/cu.ft. (based on the latest ~1U-ORS waste disposal bid) except for Co-60 which we estimated to cost more due to its high radiation level.
: 5. The minimum of structural material is removed and only radioactive material waste disposal is considered.
: 5. The minimum of structural material is removed and only radioactive material waste disposal is considered.
: 6. A qualified staff is on hand to plan and supervise the                                               ,
: 6. A qualified staff is on hand to plan and supervise the process.
process.
: 7. Labor and waste disposal comprise about 90% of the total as indicated in the above study.
: 7. Labor and waste disposal comprise about 90% of the total as indicated in the above study.
: 8. A 254 contingency is added as indicated in the above studr.
: 8. A 254 contingency is added as indicated in the above studr.
i
i


4 Staff Labor Estimate for DECON Using Table 10.1-3 " Staff Labor Requirements for DECON at the Reference             l Research Reactor" the total Jabor costs were reduced in the management and support staff area from 9.50 to 4.0 man-years. Decommissioning worker
4 Staff Labor Estimate for DECON Using Table 10.1-3 " Staff Labor Requirements for DECON at the Reference l
!              effort was reduced from 3.8 to 1.9 man-years based on the reduced requirements found in Table 10.1-2. Instead of 13.36 man-years it is estimated to require 5.9.       Therefore the staff labor cost should be reduced a
Research Reactor" the total Jabor costs were reduced in the management and support staff area from 9.50 to 4.0 man-years. Decommissioning worker effort was reduced from 3.8 to 1.9 man-years based on the reduced requirements found in Table 10.1-2.
from $530.570 to $234,300 in 1981 dollars. Eight percent inflation per year for nine years sakes this about $468,400 in 2990.
Instead of 13.36 man-years it is estimated to require 5.9.
Waste Disposal Cost for DECON 3.' Concrete          =    100 cuft.       6     $200/cuft.   $30,000
Therefore the staff labor cost should be reduced from $530.570 to $234,300 in 1981 dollars.
: 2. Oraphite            =     300 cuft.       6     $200/cuft.     20,000     e
Eight percent inflation per year a
: 3. Aluminum           =     100 cuft.       t     $100/cuft.     30,000
for nine years sakes this about $468,400 in 2990.
                                                                        $1000/cuft.       10,000
Waste Disposal Cost for DECON 100 cuft.
: 4. Stainlest Steel     =     au puft.        6
6
                                                                                        $40,000 This is based on 1990 waste disposal costs which are likely               -
$200/cuft.
to change significantly in the near future.       Remember that these are estimates only.
$30,000 3.' Concrete
There may be other costs but these two items will comprise about 90% of that         .
=
estimated for the reference reactor. Therefore, to determine the decommissioning estimate we used the following:
e
Staff Cost     +   Waste Disposal Cost
=
                        $468,400             $40.000             =   $565,000 + 254 contingency
300 cuft.
                                                                  =   $706,250 h
6
f}}
$200/cuft.
20,000
: 2. Oraphite
: 3. Aluminum
=
100 cuft.
t
$100/cuft.
30,000 au puft.
6
$1000/cuft.
10,000
: 4. Stainlest Steel
=
$40,000 This is based on 1990 waste disposal costs which are likely to change significantly in the near future.
Remember that these are estimates only.
There may be other costs but these two items will comprise about 90% of that estimated for the reference reactor. Therefore, to determine the decommissioning estimate we used the following:
Waste Disposal Cost Staff Cost
+
$468,400
$40.000
=
$565,000 + 254 contingency
=
$706,250 h
f
_ _}}

Latest revision as of 14:06, 17 December 2024

Forwards Decommissioning Funding Plan for Ohio State Univ Research Reactor
ML20056A290
Person / Time
Site: Ohio State University
Issue date: 07/30/1990
From: Hutchinson F
OHIO STATE UNIV., COLUMBUS, OH
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9008060306
Download: ML20056A290 (3)


Text

,

I T-HE Vice Pn,4 dent fu Academic 203 Bricker Hal' Affales an i havont 140 North Ovre Mall W

Columbus, O'd 432101358 Phone 61'e292 $881 UNIVERSITY July 30, 1990 l

i Document Control Desk U.S. Nuclear Regulatory Commission l

Washington, D.

C.

20555 RE: Cecommissioning Funding Plan for The Ohio State University Research Reactor, License R-75, Docket 5 -150 Gentlemen:

As required by 10CFR50.33 (K),,this report is submitted to provide assurance that funds will be available to decommission The Ohio State University Research reactor, License R-75, Docket 50-150.

These funds will be requested sufficiently in advance of decommissioning to prevent delay in the required activities.

The cost estimate to decommission The OSU Research Reactor l

is $706,250 in 1990.

This estimate is based on the study

" Technology, Safety and Costs of Decommissioning Reference Nuclear Research and Test Reactors", NUREG/CR 1756.

Attached is the detail of methods and assumptions used to arrive at the figure.

The Provost of The Ohio State University has been previously designated to the USNRC as the responsible University official under License R-75, Docket 50-150.

Sincerely, E. $

Frederick E. Hutchinson Vice President for Academic Affairs and Provost FEH/mab Attachment i

9008060306 900730 PDR ADOCK 05000150 I

PDC p

///

1

~

t(

e i

Decommissioning Funding Plan for The Ohio State University Research Reactor License R-75 Docket 50-150 t

In an effort to make a reasonable cost estimate for decommissioning one may base this on the study " Technology, Safety and Costs of Decommissioning Reference Nuclear Research and Test Reactors" NURE0/CR1756. This study used 3

the Oregon State University TRIGA as its reference research reactor.

However, one must make adjustments due to the difference between the reactors and the time the study was completed.

In order to estimate the cost of decommissioning the reactor by decontamination the following methods / assumptions were made.

l

1. The cost of fuel shipment was not included since the NRC considers this an operational cost.
2. Inflation was estimated at 8%/ year based on OSUNRL labor l

costs since 2980/81.

s

3. Staff labor requirements were based on Tables 10.1-2 and 10.1-3 from the above study with appropriate adjustments for

(

differences between the two eactors, j

4. Waste disposal was' estimated at $100/cu.ft. (based on the latest ~1U-ORS waste disposal bid) except for Co-60 which we estimated to cost more due to its high radiation level.
5. The minimum of structural material is removed and only radioactive material waste disposal is considered.
6. A qualified staff is on hand to plan and supervise the process.
7. Labor and waste disposal comprise about 90% of the total as indicated in the above study.
8. A 254 contingency is added as indicated in the above studr.

i

4 Staff Labor Estimate for DECON Using Table 10.1-3 " Staff Labor Requirements for DECON at the Reference l

Research Reactor" the total Jabor costs were reduced in the management and support staff area from 9.50 to 4.0 man-years. Decommissioning worker effort was reduced from 3.8 to 1.9 man-years based on the reduced requirements found in Table 10.1-2.

Instead of 13.36 man-years it is estimated to require 5.9.

Therefore the staff labor cost should be reduced from $530.570 to $234,300 in 1981 dollars.

Eight percent inflation per year a

for nine years sakes this about $468,400 in 2990.

Waste Disposal Cost for DECON 100 cuft.

6

$200/cuft.

$30,000 3.' Concrete

=

e

=

300 cuft.

6

$200/cuft.

20,000

2. Oraphite
3. Aluminum

=

100 cuft.

t

$100/cuft.

30,000 au puft.

6

$1000/cuft.

10,000

4. Stainlest Steel

=

$40,000 This is based on 1990 waste disposal costs which are likely to change significantly in the near future.

Remember that these are estimates only.

There may be other costs but these two items will comprise about 90% of that estimated for the reference reactor. Therefore, to determine the decommissioning estimate we used the following:

Waste Disposal Cost Staff Cost

+

$468,400

$40.000

=

$565,000 + 254 contingency

=

$706,250 h

f

_ _