On September 1, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at R.E. Ginna Nuclear Power Plant and discussed the results of this inspection with Daren Blankenship, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
On September 1, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at R.E. Ginna Nuclear Power Plant and discussed the results of this inspection with Daren Blankenship, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclos ed report.


No findings or violations of more than minor significance were identified during this inspection.
No findings or violations of more than minor significance were identified during this inspection.
Line 30: Line 30:
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.


Sincerely, Digitally signed by Daniel Daniel L. L. Schroeder Date: 2022.09.21 Schroeder 09:09:14 -04'00'
Sincerely, Daniel L. Schroeder, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security
Daniel L. Schroeder, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security Docket No. 05000244 License No. DPR-18
 
Docket No. 05000244 License No. DPR-18


===Enclosure:===
===Enclosure:===
Line 37: Line 38:


==Inspection Report==
==Inspection Report==
Docket Number: 05000244 License Number: DPR-18 Report Number: 05000244/2022501 Enterprise Identifier: I-2022-501-0006 Licensee: Constellation Energy Generation, LLC Facility: R.E. Ginna Nuclear Power Plant Location: Ontario, New York Inspection Dates: August 29, 2022 to September 1, 2022 Inspectors: J. Ambrosini, Senior Emergency Preparedness Inspector J. Lilliendahl, Senior Emergency Response Coordinator M. Patel, Senior Reactor Inspector C. Swisher, Resident Inspector Approved By: Daniel L. Schroeder, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security Enclosure
Docket Number: 05000244
 
License Number: DPR-18
 
Report Number: 05000244/2022501
 
Enterprise Identifier: I-2022-501- 0006
 
Licensee: Constellation Energy Generation, LLC
 
Facility: R.E. Ginna Nuclear Power Plant
 
Location: Ontario, New York
 
Inspection Dates: August 29, 2022 to September 1, 2022
 
Inspectors: J. Ambrosini, Senior Emergency Preparedness Inspector J. Lilliendahl, Senior Emergency Response Coordinator M. Patel, Senior Reactor Inspector C. Swisher, Resident Inspector
 
Approved By: Daniel L. Schroeder, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security
 
Enclosure


=SUMMARY=
=SUMMARY=
Line 45: Line 66:


===List of Findings and Violations===
===List of Findings and Violations===
No findings or violations of more than minor significance were identified.
No findings or violations of more than minor significance were identified.


Line 56: Line 76:


==REACTOR SAFETY==
==REACTOR SAFETY==
==71114.01 - Exercise Evaluation==
==71114.01 - Exercise Evaluation==
 
Inspection Review (IP Section 02.01 -02.11) (1 Sample)
===Inspection Review (IP Section 02.01-02.11) (1 Sample)===
: (1) The inspectors evaluated the biennial emergency plan exercise. The exercise scenario simulated a loss of offsite power with a concurrent loss of an emergency diesel generator, a reactor coolant system leak inside containment, the loss of the remaining emergency diesel generator, and a containment penetration failure resulting in minimal offsite dose consequences on August 30, 2022.
: (1) The inspectors evaluated the biennial emergency plan exercise. The exercise scenario simulated a loss of offsite power with a concurrent loss of an emergency diesel generator, a reactor coolant system leak inside containment, the loss of the remaining emergency diesel generator, and a containment penetration failure resulting in minimal offsite dose consequences on August 30, 2022.


==71114.04 - Emergency Action Level and Emergency Plan Changes==
==71114.04 - Emergency Action Level and Emergency Plan Changes==
===Inspection Review (IP Section 02.01-02.03) (1 Sample)===
===Inspection Review (IP Section 02.01-02.03) (1 Sample)===
: (1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
: (1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
* 21-62, EP-AA-1012, Addendum 3, Emergency Action Levels for Ginna Station, Revision 8
* 21-62, EP-AA-1012, Addendum 3, Emergency Action Levels for Ginna Station, Revision 8
* 22-22, EP-AA-120-1001, Addendum 3, Appendix 1, R.E. Ginna EAL Wallboard, Revision 2 This evaluation does not constitute NRC approval.
* 22-22, EP-AA-120- 1001, Addendum 3, Appendix 1, R.E. Ginna EAL Wallboard, Revision 2


==71114.08 - Exercise Evaluation - Scenario Review==
This evaluation does not constitute NRC approval.
 
==71114.08 - Exercise Evaluation -==
Scenario Review


===Inspection Review (IP Section 02.01 - 02.04) (1 Sample)===
===Inspection Review (IP Section 02.01 - 02.04) (1 Sample)===
: (1) The inspectors reviewed and evaluated the proposed scenario for biennial             emergency plan exercise on July 15,
: (1) The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on July 15,


==OTHER ACTIVITIES - BASELINE==
==OTHER ACTIVITIES - BASELINE==
===71151 - Performance Indicator Verification


===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
The inspectors verified licensee performance indicators submittals listed below:
EP01: Drill/Exercise Performance (DEP) (IP Section 02.12) ===
EP01: Drill/Exercise Performance (DEP) (IP Section 02.12)===
{{IP sample|IP=IP 71151|count=1}}
{{IP sample|IP=IP 71151|count=1}}
: (1) July 1, 2021 through June 30, 2022 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13)
(1 Sample)
: (1) July 1, 2021 through June 30, 2022
: (1) July 1, 2021 through June 30, 2022


===EP03: Alert and Notification System (ANS) Reliability (IP Section 02.14) (1 Sample)===
EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
: (1) July 1, 2021 through June 30, 2022
 
EP03: Alert and Notification System (ANS) Reliability (IP Section 02.14) (1 Sample)
: (1) July 1, 2021 through June 30,
: (1) July 1, 2021 through June 30,


Line 95: Line 117:
=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=


Inspection Type         Designation Description or Title                                   Revision or
Inspection Type Designation Description or Title Revision or
Procedure                                                                                   Date
Procedure Date
71114.01   Miscellaneous             R. E. Ginna Nuclear Power Station 2022 Emergency       06/30/2022
71114.01 Miscellaneous R. E. Ginna Nuclear Power Station 2022 Emergency 06/30/2022
Preparedness Biennial Exercise Scenario
Preparedness Biennial Exercise Scenario
EP-AA-1000 Exelon Nuclear Standardized Radiological Emergency Plan Revision 33
EP-AA-1000 Exelon Nuclear Standardized Radiological Emergency Plan Revision 33
EP-AA-1012 Exelon Nuclear Radiological Emergency Plan Annex for   Revision 8
EP-AA-1012 Exelon Nuclear Radiological Emergency Plan Annex for Revision 8
Ginna Station
Ginna Station
5
5
}}
}}

Latest revision as of 03:51, 16 November 2024

Emergency Preparedness Biennial Exercise Inspection Report 05000244/2022501
ML22264A034
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/21/2022
From: Daniel Schroeder
NRC/RGN-I/DORS
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
Schroeder D
References
IR 2022501
Download: ML22264A034 (7)


Text

September 21, 2022

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT - EMERGENCY PREPAREDNESS BIENNIAL EXERCISE INSPECTION REPORT 05000244/2022501

Dear David Rhoades:

On September 1, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at R.E. Ginna Nuclear Power Plant and discussed the results of this inspection with Daren Blankenship, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclos ed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Daniel L. Schroeder, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security

Docket No. 05000244 License No. DPR-18

Enclosure:

As stated

Inspection Report

Docket Number: 05000244

License Number: DPR-18

Report Number: 05000244/2022501

Enterprise Identifier: I-2022-501- 0006

Licensee: Constellation Energy Generation, LLC

Facility: R.E. Ginna Nuclear Power Plant

Location: Ontario, New York

Inspection Dates: August 29, 2022 to September 1, 2022

Inspectors: J. Ambrosini, Senior Emergency Preparedness Inspector J. Lilliendahl, Senior Emergency Response Coordinator M. Patel, Senior Reactor Inspector C. Swisher, Resident Inspector

Approved By: Daniel L. Schroeder, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety and Security

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an emergency preparedness biennial exercise inspection at R.E.

Ginna Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01 -02.11) (1 Sample)

(1) The inspectors evaluated the biennial emergency plan exercise. The exercise scenario simulated a loss of offsite power with a concurrent loss of an emergency diesel generator, a reactor coolant system leak inside containment, the loss of the remaining emergency diesel generator, and a containment penetration failure resulting in minimal offsite dose consequences on August 30, 2022.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • 21-62, EP-AA-1012, Addendum 3, Emergency Action Levels for Ginna Station, Revision 8
  • 22-22, EP-AA-120- 1001, Addendum 3, Appendix 1, R.E. Ginna EAL Wallboard, Revision 2

This evaluation does not constitute NRC approval.

71114.08 - Exercise Evaluation -

Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on July 15,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (DEP) (IP Section 02.12)===

(1) July 1, 2021 through June 30, 2022

EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)

(1) July 1, 2021 through June 30, 2022

EP03: Alert and Notification System (ANS) Reliability (IP Section 02.14) (1 Sample)

(1) July 1, 2021 through June 30,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 1, 2022, the inspectors presented the emergency preparedness biennial exercise inspection results to Daren Blankenship, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71114.01 Miscellaneous R. E. Ginna Nuclear Power Station 2022 Emergency 06/30/2022

Preparedness Biennial Exercise Scenario

EP-AA-1000 Exelon Nuclear Standardized Radiological Emergency Plan Revision 33

EP-AA-1012 Exelon Nuclear Radiological Emergency Plan Annex for Revision 8

Ginna Station

5