{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION
 
==REGION I==
475 ALLENDALE ROAD, SUITE 102 KING OF PRUSSIA, PA 19406 1415
 
August 29, 2024
 
Charles McFeaters President and Chief Nuclear Officer PSEG Nuclear, LLC P.O. Box 236 Hancocks Bridge, NJ 08038
 
SUBJECT: UPDATED INSPECTION PLAN FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (REPORT 05000272/20240 05 AND 05000311/2024 005)
 
==Dear Charles McFeaters:==
The enclosed inspection plan lists the inspections scheduled through June 30, 2026, for Salem Nuclear Generating Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
 
In addition to baseline inspections, the NRC plans to conduct Inspection Procedure 71003, Post -Approval Site Inspection for License Renewal, Phase 4 at your facility.
 
This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in C. McFeaters 2
 
accordance with Title 10 of the Code of Federal Regulations 2.390, Public Ins pections, Exemptions, Requests for Withholding.
 
Please contact me at (610) 337 -5312 with any questions yo u have r egarding this letter.
 
Sincerely, Brice A. Bickett, Chief Projects Branch 3 Division of Operating Reactor Safety
 
Docket Nos. 05000272 and 05000311 License Nos. DPR-70 and DPR-75
 
Enclosure:
As stated
 
cc w/encl: Distribution via ListServ C. McFeaters 3
 
SUBJECT: UPDATED INSPECTION PLAN FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (REPORTS 05000272/2024 005 AND 05000311/2024 005) DATED AUGUST 29, 2024
 
DISTRIBUTION:
RLorson, RA (R1ORAMAIL RESOURCE)
DCollins, DRA (R1ORAMAIL RESOURCE)
BWelling, DORS (R1DORSMAIL RESOURCE)
RMckinley DORS (R1DORSMAIL RESOURCE)
PKrohn, DRSS (R1DRSSMAIL RESOURCE)
JZimmerman, DRSS (R1DRSS MAIL RESOURCE)
BBickett, DORS RClagg, DORS SQuiroga, DORS JPatel, DORS, SRI EGarcia, DORS, RI CFragman, DORS, AA MSimmons, RI OEDO RidsNrrPMSalem Resource RidsNrrDorlLpl1 Resource DORS Specialist Branch Chiefs DRSS Reactor Branch Chiefs DTifft, RI, SLO DScrenci, RI, PAO NSheehan, RI, PAO ROPassessment Resource
 
DOCUMENT NAME: https://usnrc.sharepoint.com/teams/ROPAssessmentMeetings/Shared Documents/ROP -25 Second Quarter Process/Branch 3/2QAL_SL_ROP25.docx ADAMS Accession No. ML24240A202 SUNSI Review n -Sensitive Publvlle Sensitive n -Publiclyvlable
 
OFFICE RI/DORS RI/DORS ME RClagg BBickett TE 26/24 27/24 OFFIAL RERD CO Site Inspection Activity Plan Salem
 
07/01/2024 - 06/30/2026
 
Unit Start End Activity CAC Title Staff Count
 
RP - 71124.03 Airborne and 71124.04 Dose - Salem 1
 
1,2 7/22/2024 7/26/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation
 
1,2 7/22/2024 7/26/2024 IP 71124.04 000728 Occupational Dose Assessment
 
Cyber Security - Salem 4
 
1,2 8/5/2024 8/9/2024 IP 71130.10 000741 Cybersecurity
 
1,2 8/19/2024 8/23/2024 IP 71130.10 000741 Cybersecurity
 
Access Control, Equipment Testing and Maintenance, Training, SPR 3
 
1,2 8/26/2024 8/30/2024 IP 71130.02 000734 Access Control
 
1,2 8/26/2024 8/30/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance
 
1,2 8/26/2024 8/30/2024 IP 71130.07 000739 Security Training
 
1,2 8/26/2024 8/30/2024 IP 71130.09 001656 Security Plan Changes
 
1,2 8/26/2024 8/30/2024 IP 71151 001338 Performance Indicator Verification
 
Inservice Inspection - Salem Unit 2 1
 
2 10/7/2024 10/18/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
 
RP 71124.01 Rad Hazard Control - Salem 1
 
1,2 10/14/2024 10/18/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
 
2025 Salem Initial License Examination 4
 
1,2 12/1/2024 12/6/2024 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
 
1,2 1/12/2025 1/24/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
 
RP 71151 PI Verification - Salem 1
 
1,2 12/9/2024 12/13/2024 IP 71151 000746 Performance Indicator Verification
 
RP Radwaste 71124.08 SAL 1
 
1,2 2/3/2025 2/7/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation
 
EP Program Inspection - Salem 2
 
1,2 3/17/2025 3/21/2025 IP 71114.02 000717 Alert and Notification System Testing
 
1,2 3/17/2025 3/21/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
 
1,2 3/17/2025 3/21/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
 
1,2 3/17/2025 3/21/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness
 
1,2 3/17/2025 3/21/2025 IP 71151 001397 Performance Indicator Verification
 
RP RETS 71124.06 SAL 1
 
1,2 3/31/2025 4/4/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment
 
Inservice Inspection - Salem Unit 1 1
 
Prepared on 8/20/2024 3:11:08 PM 1 of 3 Site Inspection Activity Plan
 
1 4/14/2025 4/25/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
 
RP Rad Hazard 71124.01 SAL 1
 
1,2 4/21/2025 4/25/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
 
Access Control, Protective Strategy, TSR, SPR, PIs - Salem 4
 
1,2 6/9/2025 6/13/2025 IP 71130.02 000734 Access Control
 
1,2 6/9/2025 6/13/2025 IP 71130.05 000737 Protective Strategy Evaluation
 
1,2 6/9/2025 6/13/2025 IP 71130.09 001656 Security Plan Changes
 
1,2 6/9/2025 6/13/2025 IP 71130.14 000743 Review of Power Reactor Target Sets
 
1,2 6/9/2025 6/13/2025 IP 71151 001338 Performance Indicator Verification
 
PI&R BIENNIAL TEAM INSPECTION - SALEM 4
 
1,2 6/9/2025 6/13/2025 IP 71152B 000747 Problem Identification and Resolution
 
1,2 6/23/2025 6/27/2025 IP 71152B 000747 Problem Identification and Resolution
 
RP REMP 71124.07 SAL 1
 
1,2 7/14/2025 7/18/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program
 
License Renewal Phase 4 - Salem Units 1 & 2 4
 
1,2 8/11/2025 8/15/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal
 
Salem Requal Inspection with P/F Results 2
 
1,2 9/15/2025 9/19/2025 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 1,2 9/15/2025 9/19/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance
 
RP Instrumentation 71124.05 SAL 1
 
1,2 11/10/2025 11/20/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation
 
Age Related Degradation Inspection - Salem 3
 
1,2 11/17/2025 11/21/2025 IP 71111.21N.04 001832 Age-Related Degradation
 
1,2 12/1/2025 12/5/2025 IP 71111.21N.04 001832 Age-Related Degradation
 
RP PI Verification 71151 SAL 1
 
1,2 11/17/2025 11/21/2025 IP 71151 000746 Performance Indicator Verification
 
Commercial Grade Dedication - Salem 3
 
1,2 1/12/2026 1/16/2026 IP 71111.21N.03 001808 Commercial Grade Dedication
 
1,2 1/26/2026 1/30/2026 IP 71111.21N.03 001808 Commercial Grade Dedication
 
RP In Plant Airborne 71124.03 and Occupational Dose Assessment 71124.04 - Salem 1
 
1,2 3/9/2026 3/13/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation
 
1,2 3/9/2026 3/13/2026 IP 71124.04 000728 Occupational Dose Assessment
 
Sec - Access Control, Equipment Testing and Maintenance, Training, SPR, PI Verification - Salem 3
 
1,2 3/9/2026 3/13/2026 IP 71130.02 000734 Access Control
 
1,2 3/9/2026 3/13/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance
 
Prepared on 8/20/2024 3:11:08 PM 2 of 3 Site Inspection Activity Plan
 
1,2 3/9/2026 3/13/2026 IP 71130.07 000739 Security Training
 
1,2 3/9/2026 3/13/2026 IP 71130.09 001656 Security Plan Changes
 
1,2 3/9/2026 3/13/2026 IP 71151 001338 Performance Indicator Verification
 
Inservice Inspection - Salem Unit 2 1
 
2 4/13/2026 4/24/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
 
RP Rad Hazard Assessment and Exposure Control 71124.01 - Salem 1
 
2 4/13/2026 4/17/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
 
2026 Salem Initial Operator Licensing Exam 4
 
1,2 5/11/2026 5/15/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
 
EP Exercise Inspection - Salem 5
 
1,2 5/18/2026 5/22/2026 IP 71114.01 000716 Exercise Evaluation
 
1,2 5/18/2026 5/22/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
 
1,2 5/18/2026 5/22/2026 IP 71151 001397 Performance Indicator Verification
 
Cyber Security - Salem 2
 
1,2 6/8/2026 6/12/2026 IP 71130.10 000741 Cybersecurity
 
1,2 6/22/2026 6/26/2026 IP 71130.10 000741 Cybersecurity
 
Prepared on 8/20/2024 3:11:08 PM 3 of 3
}}
}}

Latest revision as of 23:05, 3 October 2024

Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005)
ML24240A202
Person / Time
Site: Salem  PSEG icon.png
Issue date: 08/29/2024
From: Brice Bickett
NRC/RGN-I/DORS
To: Mcfeaters C
Public Service Enterprise Group
References
IR 2024005
Download: ML24240A202 (1)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION I

475 ALLENDALE ROAD, SUITE 102 KING OF PRUSSIA, PA 19406 1415

August 29, 2024

Charles McFeaters President and Chief Nuclear Officer PSEG Nuclear, LLC P.O. Box 236 Hancocks Bridge, NJ 08038

SUBJECT: UPDATED INSPECTION PLAN FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (REPORT 05000272/20240 05 AND 05000311/2024 005)

Dear Charles McFeaters:

The enclosed inspection plan lists the inspections scheduled through June 30, 2026, for Salem Nuclear Generating Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In addition to baseline inspections, the NRC plans to conduct Inspection Procedure 71003, Post -Approval Site Inspection for License Renewal, Phase 4 at your facility.

This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in C. McFeaters 2

accordance with Title 10 of the Code of Federal Regulations 2.390, Public Ins pections, Exemptions, Requests for Withholding.

Please contact me at (610) 337 -5312 with any questions yo u have r egarding this letter.

Sincerely, Brice A. Bickett, Chief Projects Branch 3 Division of Operating Reactor Safety

Docket Nos. 05000272 and 05000311 License Nos. DPR-70 and DPR-75

Enclosure:

As stated

cc w/encl: Distribution via ListServ C. McFeaters 3

SUBJECT: UPDATED INSPECTION PLAN FOR SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 (REPORTS 05000272/2024 005 AND 05000311/2024 005) DATED AUGUST 29, 2024

DISTRIBUTION:

RLorson, RA (R1ORAMAIL RESOURCE)

DCollins, DRA (R1ORAMAIL RESOURCE)

BWelling, DORS (R1DORSMAIL RESOURCE)

RMckinley DORS (R1DORSMAIL RESOURCE)

PKrohn, DRSS (R1DRSSMAIL RESOURCE)

JZimmerman, DRSS (R1DRSS MAIL RESOURCE)

BBickett, DORS RClagg, DORS SQuiroga, DORS JPatel, DORS, SRI EGarcia, DORS, RI CFragman, DORS, AA MSimmons, RI OEDO RidsNrrPMSalem Resource RidsNrrDorlLpl1 Resource DORS Specialist Branch Chiefs DRSS Reactor Branch Chiefs DTifft, RI, SLO DScrenci, RI, PAO NSheehan, RI, PAO ROPassessment Resource

DOCUMENT NAME: https://usnrc.sharepoint.com/teams/ROPAssessmentMeetings/Shared Documents/ROP -25 Second Quarter Process/Branch 3/2QAL_SL_ROP25.docx ADAMS Accession No. ML24240A202 SUNSI Review n -Sensitive Publvlle Sensitive n -Publiclyvlable

OFFICE RI/DORS RI/DORS ME RClagg BBickett TE 26/24 27/24 OFFIAL RERD CO Site Inspection Activity Plan Salem

07/01/2024 - 06/30/2026

Unit Start End Activity CAC Title Staff Count

RP - 71124.03 Airborne and 71124.04 Dose - Salem 1

1,2 7/22/2024 7/26/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

1,2 7/22/2024 7/26/2024 IP 71124.04 000728 Occupational Dose Assessment

Cyber Security - Salem 4

1,2 8/5/2024 8/9/2024 IP 71130.10 000741 Cybersecurity

1,2 8/19/2024 8/23/2024 IP 71130.10 000741 Cybersecurity

Access Control, Equipment Testing and Maintenance, Training, SPR 3

1,2 8/26/2024 8/30/2024 IP 71130.02 000734 Access Control

1,2 8/26/2024 8/30/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance

1,2 8/26/2024 8/30/2024 IP 71130.07 000739 Security Training

1,2 8/26/2024 8/30/2024 IP 71130.09 001656 Security Plan Changes

1,2 8/26/2024 8/30/2024 IP 71151 001338 Performance Indicator Verification

Inservice Inspection - Salem Unit 2 1

2 10/7/2024 10/18/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 71124.01 Rad Hazard Control - Salem 1

1,2 10/14/2024 10/18/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

2025 Salem Initial License Examination 4

1,2 12/1/2024 12/6/2024 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 1/12/2025 1/24/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

RP 71151 PI Verification - Salem 1

1,2 12/9/2024 12/13/2024 IP 71151 000746 Performance Indicator Verification

RP Radwaste 71124.08 SAL 1

1,2 2/3/2025 2/7/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation

EP Program Inspection - Salem 2

1,2 3/17/2025 3/21/2025 IP 71114.02 000717 Alert and Notification System Testing

1,2 3/17/2025 3/21/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

1,2 3/17/2025 3/21/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

1,2 3/17/2025 3/21/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness

1,2 3/17/2025 3/21/2025 IP 71151 001397 Performance Indicator Verification

RP RETS 71124.06 SAL 1

1,2 3/31/2025 4/4/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment

Inservice Inspection - Salem Unit 1 1

Prepared on 8/20/2024 3:11:08 PM 1 of 3 Site Inspection Activity Plan

1 4/14/2025 4/25/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP Rad Hazard 71124.01 SAL 1

1,2 4/21/2025 4/25/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

Access Control, Protective Strategy, TSR, SPR, PIs - Salem 4

1,2 6/9/2025 6/13/2025 IP 71130.02 000734 Access Control

1,2 6/9/2025 6/13/2025 IP 71130.05 000737 Protective Strategy Evaluation

1,2 6/9/2025 6/13/2025 IP 71130.09 001656 Security Plan Changes

1,2 6/9/2025 6/13/2025 IP 71130.14 000743 Review of Power Reactor Target Sets

1,2 6/9/2025 6/13/2025 IP 71151 001338 Performance Indicator Verification

PI&R BIENNIAL TEAM INSPECTION - SALEM 4

1,2 6/9/2025 6/13/2025 IP 71152B 000747 Problem Identification and Resolution

1,2 6/23/2025 6/27/2025 IP 71152B 000747 Problem Identification and Resolution

RP REMP 71124.07 SAL 1

1,2 7/14/2025 7/18/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program

License Renewal Phase 4 - Salem Units 1 & 2 4

1,2 8/11/2025 8/15/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal

Salem Requal Inspection with P/F Results 2

1,2 9/15/2025 9/19/2025 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 1,2 9/15/2025 9/19/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance

RP Instrumentation 71124.05 SAL 1

1,2 11/10/2025 11/20/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation

Age Related Degradation Inspection - Salem 3

1,2 11/17/2025 11/21/2025 IP 71111.21N.04 001832 Age-Related Degradation

1,2 12/1/2025 12/5/2025 IP 71111.21N.04 001832 Age-Related Degradation

RP PI Verification 71151 SAL 1

1,2 11/17/2025 11/21/2025 IP 71151 000746 Performance Indicator Verification

Commercial Grade Dedication - Salem 3

1,2 1/12/2026 1/16/2026 IP 71111.21N.03 001808 Commercial Grade Dedication

1,2 1/26/2026 1/30/2026 IP 71111.21N.03 001808 Commercial Grade Dedication

RP In Plant Airborne 71124.03 and Occupational Dose Assessment 71124.04 - Salem 1

1,2 3/9/2026 3/13/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

1,2 3/9/2026 3/13/2026 IP 71124.04 000728 Occupational Dose Assessment

Sec - Access Control, Equipment Testing and Maintenance, Training, SPR, PI Verification - Salem 3

1,2 3/9/2026 3/13/2026 IP 71130.02 000734 Access Control

1,2 3/9/2026 3/13/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance

Prepared on 8/20/2024 3:11:08 PM 2 of 3 Site Inspection Activity Plan

1,2 3/9/2026 3/13/2026 IP 71130.07 000739 Security Training

1,2 3/9/2026 3/13/2026 IP 71130.09 001656 Security Plan Changes

1,2 3/9/2026 3/13/2026 IP 71151 001338 Performance Indicator Verification

Inservice Inspection - Salem Unit 2 1

2 4/13/2026 4/24/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP Rad Hazard Assessment and Exposure Control 71124.01 - Salem 1

2 4/13/2026 4/17/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

2026 Salem Initial Operator Licensing Exam 4

1,2 5/11/2026 5/15/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

EP Exercise Inspection - Salem 5

1,2 5/18/2026 5/22/2026 IP 71114.01 000716 Exercise Evaluation

1,2 5/18/2026 5/22/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes

1,2 5/18/2026 5/22/2026 IP 71151 001397 Performance Indicator Verification

Cyber Security - Salem 2

1,2 6/8/2026 6/12/2026 IP 71130.10 000741 Cybersecurity

1,2 6/22/2026 6/26/2026 IP 71130.10 000741 Cybersecurity

Prepared on 8/20/2024 3:11:08 PM 3 of 3