IR 05000272/2023011
| ML23066A013 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 03/07/2023 |
| From: | Mel Gray Division of Operating Reactors |
| To: | Carr E Public Service Enterprise Group |
| References | |
| IR 2023011 | |
| Download: ML23066A013 (1) | |
Text
March 7, 2023
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 -
COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000272/2023011 AND 05000311/2023011
Dear Eric Carr:
On February 9, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Salem Nuclear Generating Station, Units 1 and 2 and discussed the results of this inspection with R.J. DeSanctis, Jr., and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety
Docket Nos. 05000272 and 05000311 License Nos. DPR-70 and DPR-75
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000272 and 05000311
License Numbers:
Report Numbers:
05000272/2023011 and 05000311/2023011
Enterprise Identifier: I-2023-011-0009
Licensee:
Facility:
Salem Nuclear Generating Station
Location:
Hancocks Bridge, NJ
Inspection Dates:
January 23, 2023 to February 9, 2023
Inspectors:
J. Brand, Reactor Inspector
J. Kulp, Senior Reactor Inspector
N. Mentzer, Resident Inspector
E. Miller, Reactor Inspector
J. Rady, Senior Reactor Inspector
J. Schoppy, Senior Reactor Inspector
A. Turilin, Reactor Inspector
Approved By:
Mel Gray, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Comprehensive Engineering Team Inspection Report at Salem Nuclear Generating Station, Units 1 and 2, in accordance with the Reactor Oversight Process.
The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Comprehensive Engineering Team Inspection
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Structures, Systems, and Components (IP section 03.01)===
For each component or operator action sample listed below, the team reviewed licensing and design basis documents and a sampling of applicable operator actions, periodic testing results, corrective action program documents, internal and external operating experience, preventive and corrective maintenance work orders, modifications, and aging management programs. Additionally, the team performed walkdowns of the component or procedure and conducted interviews with licensee personnel.
The team used the attributes contained in IP 71111.21M, Appendix A, Component Review Attributes, such as those listed below as guidance. Specifically, the team evaluated these attributes in the course of applying 71111.21M, Appendix B, Component Design Review Considerations and 71111.21M, Appendix C, Component Walkdown Considerations.
(1)12 Service Water Pump
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (2) Risk Significant Operator Action: Bleed and Feed (Response to Loss of Secondary Heat Sink) and Associated Structures, Systems, and Components
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (3) Non-Safety-Related Auxiliary Feedwater (AFW) Pump and Diesel
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (4) Unit 1 1A Emergency Diesel Generator (1DAE4)
- Energy sources (fuel, air and electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, Electrical Loads and As-Built System.
- (5) Unit 1 1A 4kV Switchgear (S14KV-1SWGR1AD)
- Energy sources (electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, Electrical Loads and As-Built System.
- (6) S128D-1BTRY1ADE - Unit 1 28VDC Battery, Charger, and Switchgear
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Heat will be adequately removed from major components.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, Electrical Loads and As-Built System.
- (7) Time sensitive operator action - DC Load Shedding (EOP-LOPA-1) and Associated Structures, Systems, and Components
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, Electrical Loads and As-Built System.
(8)23 Turbine Driven Auxiliary Feedwater Pump
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Heat will be adequately removed from major components.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
(9)22MS10 Main Steam Atmospheric Relief Valve
- Energy sources (air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
Modifications (IP section 03.02) (5 Samples)
- (1) ECP 80119413, Emergency Diesel Generator Field Flash Relay, Revision 1
- (3) ECP 80122162, Remove Automatic Rod Control, Revision 0
Revision 0
- (5) ECP 80123050, Salem 1&2 MS10 Valves Positioner Upgrade, Revision 1
10 CFR 50.59 Evaluations/Screening (IP section 03.03) (13 Samples)
- (1) S2022-089, 50.59 review for procedure Revision S1(2).OP-AB.CN-0001(Q),
Revision 0
- (2) S2021-101, DCP 80126494 Salem Unit 2 Up-flow Conversion and eLBB Implementation, Revision 0
- (3) S2021-109, Containment Ventilation Operation 50.59 Screen, Revision 0
- (4) S2019-222, Salem 1 & 2 MS10 Valves Positioner Upgrade, Revision 1
- (5) S2022-118, Procedure Revisions S1(2).OP-AB.LOOP-0001 R35(R33), Revision 0
- (6) S2022-111, Procedure Revisions - 125VDC Battery Operations, Revision 0
- (7) S2018-063, Remove Auto Rod Withdrawal, Revision 0
- (8) S2022-003, Generic Rosemount Transmitter Equivalent Change, Revision 0
- (9) S2021-122, Procedure Revision - S2.OP-AB.SF-0001, Spent Fuel Pool Peak Temperature at Various In-Vessel Decay Times and Temperatures, Revision 0
- (10) S2022-012, Reactor Coolant Pump Abnormality 50.59 Screen, Revision 0
- (11) S2022-072, 1(2)RH21 Leakby (RWST Back-Leakage) 50.59 Evaluation, Revision 0
- (12) S2022-065, Receipt of Bulk Chemical Trucks - SC.CH-GP.ZZ-2470 (Z), Revision 0
- (13) S2021-117, Salem Unit 3 Gas Turbine (Jet) Interim Abandonment, Revision 0
Operating Experience Samples (IP section 03.04) (2 Samples)
- (1) NRC Information Notice 2021-03, Operating Experience Related to the Duane Arnold Energy Center Derecho Event on August 10, 2020, dated August 11, 2021
- (2) NRC Information Notice 2020-02, Flex EDG Operational Challenges, dated September 15,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On February 9, 2023, the inspectors presented the Comprehensive Engineering Team Inspection results to R.J. DeSanctis, Jr., and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
Study to Increase the 125V DC Battery Margin
Revision 15
ES-3.002(Q)
Volt DC Battery and Battery Charger Sizing Calculation
Revision 5
S-C-AF-MDC-
0432
Auxiliary Feedwater Pump NPSH
Revision 1
S-C-SW-MDC-
1350
Service Water System MODE OPS Analysis
Revision 9
S-C-SW-MDC-
1967
Service Water System Thermal Hydraulic Model
Revision 11
Corrective Action
Documents
20777337
20861944
20867126
20884341
Corrective Action
Documents
Resulting from
Inspection
20925886
20925899
20925918
20925919
20925920
20926157
20926165
20926173
20926182
20926183
20926184
20926185
20926186
20926191
20926203
20926277
20926279
20926280
20926291
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
20926294
20926296
20926428
20926429
20926430
20926443
20926457
20926458
20926459
20926460
20926461
20926486
20926523
20926552
20926572
20926599
20926605
20926606
20926610
20926611
20926625
20926626
20926627
20926635
20926772
20926775
20926792
20926874
20927031
20927042
20927044
20927051
20927053
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
20927070
20927071
20927072
20927139
20927146
20927147
20927154
20927171
20927175
20927222
20927236
20927324
Engineering
Evaluations
VTD 314204
Station Blackout Analysis for Salem Units 1 and 2, Volume 1
Revision 5
Reactor Internals Up-flow Conversion Program Engineering
Report for Salem Nuclear Generating Station Unit 2
Revision 0
Miscellaneous
S1.OP-ST.SW-
0002
Inservice Testing - 12 Service Water Pump
2/17/2022
S2.OP-ST.AF-
0003(Q)
Inservice Testing - 23 Auxiliary Feedwater Pump
11/23/2022
Procedures
1-EOP-FRHS-1
Response to Loss of Secondary Heat Sink
Revision 42
1-EOP-LOPA-1
Loss of All AC Power
Revision 41
S1.OP-AB.LOOP-
0001
Revision 35
S1.OP-SO.SW-
0001
Service Water Pump Operation
Revision 31
S1.OP-SO.SW-
0005
Service Water System Operation
Revision 53
S2.OP-AB.LOOP-
0001
Revision 34
S2.OP-SO.MS-
0002
Steam Dump System Operation
Revision 14
S2.RA-ST.MS-
0002
Inservice Testing Main Steam and Main Feedwater Valves
Acceptance Criteria
Revision 22
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
SC.OP-AR.AF-
0001(Z)
MSPI emergency diesel generator Pump Diesel Alarm
Response
Revision 0
SC.OP-PT.AF-
0001(Z)
Testing the MSPI Pump and Diesel
Revision 1
SC.OP-SO.AF-
0001(Q)
Feed Steam Generators with MSPI AFW Pump
Revision 1
Work Orders
30344911
50171438
60149379