MONTHYEARIR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) ML22318A1062022-11-14014 November 2022 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 IR 05000272/20220052022-08-31031 August 2022 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022005 and 05000311/2022005) ML22234A0362022-08-22022 August 2022 Request for Information to Support Triennial Baseline Design - Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000272/2022011 and 05000311/2022011 IR 05000272/20224022022-04-14014 April 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000272/2022402 and 05000311/2022402 IR 05000272/20210062022-03-0202 March 2022 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2021006 and 05000311/2021006) IR 05000272/20210052021-09-0101 September 2021 Updated Inspection Plan for the Salem Nuclear Generating Station (Report 05000272/2021005 and 05000311/2021005) IR 05000272/20200062021-03-0303 March 2021 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2020006 and 05000311/2020006) LR-N21-0014, Snubber Program Plan, Fifth Ten-Year Inspection Interval, Effective from January 1, 2021 Through December 31, 20302021-02-16016 February 2021 Snubber Program Plan, Fifth Ten-Year Inspection Interval, Effective from January 1, 2021 Through December 31, 2030 ML20281A5172020-10-13013 October 2020 Notification of Conduct of a Fire Protection Team Inspection IR 05000272/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000272/2020005 and 05000311/2020005) ML20077L3492020-03-20020 March 2020 Ti 2515/194 Inspection Documentation Request IR 05000272/20190062020-03-0303 March 2020 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2019006 and 05000311/2019006) IR 05000272/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000272/2019005 and 05000311/2019005) IR 05000272/20180062019-03-0404 March 2019 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2018006 and 05000311/2018006) IR 05000272/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Reports 05000272/2018005 and 05000311/2018005) IR 05000272/20170062018-02-28028 February 2018 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2017006, 05000311/2017006, 05000272/2017402, 05000311/2017402, 05000272/2017501, and 05000311/2017501 IR 05000272/20170052017-08-28028 August 2017 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2017005 and 05000311/2017005) IR 05000272/20160062017-03-0101 March 2017 Annual Assessment Letter for Salem Nuclear Generating Station (Salem), Units 1 and 2 (Reports 05000272/2016006 and 05000311/2016006) IR 05000272/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Salem Nuclear Generating Station - Unit Nos. 1 and 2 (Report 05000272/2016005 and 05000311/2016005) IR 05000272/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 & 2 (Inspection Report 05000272/2015006 and 05000311/2015006) IR 05000272/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2015005 and 05000311/2015005) IR 05000272/20140012015-03-0404 March 2015 ROP-15 Annual Assessment Letter for Salem Nuclear Generating Station Units 1 and 2 (Report 05000272/2014001 and 05000311/2014001) IR 05000272/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000272/2014006 and 05000311/2014006 IR 05000272/20130012014-03-0404 March 2014 ROP-14 2013 Salem Nuclear Generating Station Units 1 and 2, Annual Assessment Letter, Report 05000272-13-001 and 05000311-13-001),and Inspection Plan IR 05000272/20130062013-09-0303 September 2013 ROP-14 Mid-Cycle Performance Review and Inspection Plan Report 05000272/2013006 and 05000311/2013006 IR 05000272/20120012013-03-0404 March 2013 Annual Assessment Letter for Salem Nuclear Generating Station, Unit 1 and 2 (Report 05000272/2012001 and 05000311/2012001) ML12248A0402012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Salem Nuclear Generating Station, Units 1 and 2 IR 05000272/20110012012-03-0505 March 2012 Annual Assessment Letter for Salem Nuclear Generating Station, Unit Nos. 1 and 2 (Report 05000272/2011001 and 05000311/2011001) ML1124112942011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Salem Nuclear Generating Station, Units 1 and 2 IR 05000272/20100012011-03-0404 March 2011 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2, EOC-11 (Report 05000272/2010001 and 05000311/2010001) ML1024403642010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Salem Nuclear Generating Station, Units 1 and 2 ML1029505872010-03-12012 March 2010 Email from Ohara, Timothy to Conte, Richard, FW: Salem U1 Inspection Plan. ML1006208082010-03-0303 March 2010 EOC Letter and Report 22 ML0924403092009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Salem Nuclear Generating Station, Unit Nos. 1 and 2 (September 1, 2009) IR 05000272/20090012009-03-0404 March 2009 Annual Assessment Letter - Salem Nuclear Generating Station, Units 1 and 2 (05000272-09-001 and 05000311-09-001) IR 05000272/20080012008-03-0303 March 2008 Annual Assessment Letter EOC 2007 ROP8 - Salem Station (05000272-08-001, 05000311-08-001) ML0734706552007-12-13013 December 2007 ROP 8 - Salem - Change to Inspection Plan, 12/13/07 ML0724309472007-08-31031 August 2007 Mid-Cycle Review and Inspection Plan IR 05000272/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Salem Generating Station (Report 05000272-07-001, 05000311-07-001) ML0624306512006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Salem Nuclear Generating Station IR 07200200/19600012006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Salem Nuclear Generating Station (Report 05-272/2006001 and 05-311/2006001) ML0406307982004-03-0303 March 2004 2003-04 Annual Assessment Letter - Salem ML0323905112003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Salem Units 1 and 2 ML0306206932003-03-0303 March 2003 2003 Annual Assessment Letter - Salem Nuclear Generating Station 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000272/20240032024-10-30030 October 2024 Integrated Inspection Report 05000272/2024003 and 05000311/2024003 ML24296B1932024-10-23023 October 2024 Project Manager Assignment LR-N24-0068, Core Operating Limits Report - Cycle 282024-10-21021 October 2024 Core Operating Limits Report - Cycle 28 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 05000272/LER-2024-001, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report – Cycle 302023-11-0101 November 2023 Core Operating Limits Report – Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, And Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 And Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location 2024-09-23
[Table view] |
Text
December 13, 2007 William Levis President and Chief Nuclear Officer PSEG Nuclear LLC 80 Park Plaza, T4B Newark, NJ 07102
SUBJECT:
CHANGE TO THE INSPECTION PLAN FOR THE SALEM NUCLEAR GENERATING STATION
Dear Mr. Levis:
As part of a periodic self-assessment, the Nuclear Regulatory Commission (NRC) thoroughly reviewed the inspection procedures to ensure the continued effective application of inspection resources. The main objective of the review was to determine the appropriate inspection scope for the majority of the inspection procedures in the reactor oversight process (ROP). The result of this effort (designated ROP realignment) created changes to both inspection scope and/or inspection frequency for selected inspection procedures in the ROP. The purpose of this letter is to update the schedule of future inspection activities at your facility that was provided with the mid-cycle assessment letter in August 2007. Please note that there were no changes made to inspection procedures in the security, emergency preparedness, and health physics areas.
The enclosed inspection plan details the inspections (less those related to physical protection) scheduled for calendar year 2008. The inspection plan is provided to resolve any scheduling and/or personnel availability issues well in advance of the inspector(s) arrival onsite. Routine resident inspections are not listed due to their continuous nature.
In accordance with 10 CFR 2.390 of the NRCs Rules and Practices a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS).
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).
W. Levis 2 Please contact me at 610-337-5069 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mr. Arthur Burritt, Chief Projects Branch 3 Division of Reactor Projects Docket No. 50-272 and 50-311 License No. DPR-70 and DPR-75
Enclosures:
Salem Nuclear Generating Station Inspection/Activity Plans cc w/encl:
T. Joyce, Senior Vice President, Operations R. Braun, Site Vice President K. Chambliss, Vice President, Nuclear Oversight B. Clark, Director of Finance G. Gellrich, Salem Plant Manager J. Keenan, General Solicitor, PSEG M. Wetterhahn, Esquire, Winston and Strawn, LLP L. Peterson, Chief of Police and Emergency Management Coordinator P. Baldauf, Assistant Director, NJ Radiation Protection Programs P. Mulligan, Acting-Manager, NJ Bureau of Nuclear Engineering H. Otto, Ph.D., Admin, DE Interagency Progs, DNREC Div of Water Resources Consumer Advocate, Office of Consumer Advocate, Commonwealth of Pennsylvania N. Cohen, Coordinator - Unplug Salem Campaign E. Zobian, Coordinator - Jersey Shore Anti Nuclear Alliance
W. Levis 2 Please contact me at 610-337-5069 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/ra/
Mr. Arthur Burritt, Chief Projects Branch 3 Division of Reactor Projects Docket No. 50-272 and 50-311 License No. DPR-70 and DPR-75
Enclosures:
Salem Nuclear Generating Station Inspection/Activity Plans Distribution w/encl:
S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP A. Burritt, DRP C. Khan, DRP L. Cline, DRP D. Schroeder, DRP, Sr Resident Inspector H. Balian, DRP, Resident Inspector K. Venuto, DRP, Resident OA G. West, RI OEDO J. Lubinski, NRR H. Chernoff, NRR R. Ennis, NRR, PM J. Shea, NRR, Backup D. Collins, NRR J. Thompson, NRR (JWT1@nrc.gov)
D. Screnci, PAO R. Barkley, ORA D. Holody, ORA SUNSI Review Complete: LC (Reviewer=s Initials)
DOCUMENT NAME: T:\DRP\BRANCH3\ROP 8 Letters\HCGSROPrealignment.doc After declaring this document AAn Official Agency Record@ it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E"
= Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME LCline/LC ABurritt/ALB DATE 12/07/07 12/13/07 OFFICIAL RECORD COPY
Page 1 of 2 Salem 12/11/2007 14:32:17 Inspection / Activity Plan Report 22 01/01/2008 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 7112201 - PUB RAD SAFETY - RETS 1 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 01/07/2008 01/11/2008 Baseline Inspections S/G - U2 S/G REPLACEMENT 2 2 IP 50001 Steam Generator Replacement Inspection 01/07/2008 04/25/2008 Other Routine 7111108P - U2 INSERVICE INSPECTION 1 2 IP 7111108P Inservice Inspection Activities - PWR 03/17/2008 03/28/2008 Baseline Inspections 71121 - OCC RAD SAFETY 1 2 IP 50001 Steam Generator Replacement Inspection 04/07/2008 04/11/2008 Other Routine 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 04/07/2008 04/11/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 04/07/2008 04/11/2008 Baseline Inspections 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 04/07/2008 04/11/2008 Baseline Inspections 2 IP 50001 Steam Generator Replacement Inspection 04/21/2008 04/25/2008 Other Routine 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 04/21/2008 04/25/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 04/21/2008 04/25/2008 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 04/21/2008 04/25/2008 Baseline Inspections 08/25EXM - INITIAL OPERATOR LICENSING EXAM 4 1 U01686 FY08 - SALEM 1 & 2 INITIAL OPERATOR EXAM 07/21/2008 07/25/2008 Not Applicable 1 U01686 FY08 - SALEM 1 & 2 INITIAL OPERATOR EXAM 08/25/2008 08/29/2008 Not Applicable S/G - U2 S/G REPLACEMENT CONTINUED 2 2 IP 50001 Steam Generator Replacement Inspection 04/26/2008 05/09/2008 Other Routine EP - EP EXERCISE EVALUATION 4 1, 2 IP 7111401 Exercise Evaluation 05/19/2008 05/23/2008 EP Baseline Inspectio 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 05/19/2008 05/23/2008 EP Baseline Inspectio 1, 2 IP 71151-EP01 Drill/Exercise Performance 05/19/2008 05/23/2008 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 05/19/2008 05/23/2008 Baseline Inspections 1, 2 IP 71151-EP03 Alert & Notification System 05/19/2008 05/23/2008 Baseline Inspections 7111121 - CDBI 10 1, 2 IP 7111121 Component Design Bases Inspection 07/14/2008 07/18/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 07/28/2008 08/01/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 08/04/2008 08/08/2008 Baseline Inspections 71121 - OCC RAD SAFETY 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 09/15/2008 09/19/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Salem 12/11/2007 14:32:17 Inspection / Activity Plan Report 22 01/01/2008 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121 - OCC RAD SAFETY 1 1, 2 IP 71151-PR01 RETS/ODCM Radiological Effluent 09/15/2008 09/19/2008 Baseline Inspections 71121 - OCC RDA SAFETY 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 10/20/2008 10/24/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 10/20/2008 10/24/2008 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 10/20/2008 10/24/2008 Baseline Inspections 7111108 - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 10/20/2008 10/31/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.