Similar Documents at Salem |
---|
Category:Inspection Plan
MONTHYEARIR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) ML22318A1062022-11-14014 November 2022 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 IR 05000272/20220052022-08-31031 August 2022 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022005 and 05000311/2022005) ML22234A0362022-08-22022 August 2022 Request for Information to Support Triennial Baseline Design - Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000272/2022011 and 05000311/2022011 ML22104A1762022-04-14014 April 2022 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000272/2022402 and 05000311/2022402 IR 05000272/20210062022-03-0202 March 2022 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2021006 and 05000311/2021006) IR 05000272/20210052021-09-0101 September 2021 Updated Inspection Plan for the Salem Nuclear Generating Station (Report 05000272/2021005 and 05000311/2021005) IR 05000272/20200062021-03-0303 March 2021 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2020006 and 05000311/2020006) LR-N21-0014, Snubber Program Plan, Fifth Ten-Year Inspection Interval, Effective from January 1, 2021 Through December 31, 20302021-02-16016 February 2021 Snubber Program Plan, Fifth Ten-Year Inspection Interval, Effective from January 1, 2021 Through December 31, 2030 ML20281A5172020-10-13013 October 2020 Notification of Conduct of a Fire Protection Team Inspection IR 05000272/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000272/2020005 and 05000311/2020005) ML20077L3492020-03-20020 March 2020 Ti 2515/194 Inspection Documentation Request IR 05000272/20190062020-03-0303 March 2020 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2019006 and 05000311/2019006) IR 05000272/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000272/2019005 and 05000311/2019005) IR 05000272/20180062019-03-0404 March 2019 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2018006 and 05000311/2018006) IR 05000272/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Reports 05000272/2018005 and 05000311/2018005) IR 05000272/20170062018-02-28028 February 2018 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2017006, 05000311/2017006, 05000272/2017402, 05000311/2017402, 05000272/2017501, and 05000311/2017501 IR 05000272/20170052017-08-28028 August 2017 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2017005 and 05000311/2017005) IR 05000272/20160062017-03-0101 March 2017 Annual Assessment Letter for Salem Nuclear Generating Station (Salem), Units 1 and 2 (Reports 05000272/2016006 and 05000311/2016006) IR 05000272/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Salem Nuclear Generating Station - Unit Nos. 1 and 2 (Report 05000272/2016005 and 05000311/2016005) IR 05000272/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 & 2 (Inspection Report 05000272/2015006 and 05000311/2015006) IR 05000272/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2015005 and 05000311/2015005) IR 05000272/20140012015-03-0404 March 2015 ROP-15 Annual Assessment Letter for Salem Nuclear Generating Station Units 1 and 2 (Report 05000272/2014001 and 05000311/2014001) IR 05000272/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000272/2014006 and 05000311/2014006 IR 05000272/20130012014-03-0404 March 2014 ROP-14 2013 Salem Nuclear Generating Station Units 1 and 2, Annual Assessment Letter, Report 05000272-13-001 and 05000311-13-001),and Inspection Plan IR 05000272/20130062013-09-0303 September 2013 ROP-14 Mid-Cycle Performance Review and Inspection Plan Report 05000272/2013006 and 05000311/2013006 IR 05000272/20120012013-03-0404 March 2013 Annual Assessment Letter for Salem Nuclear Generating Station, Unit 1 and 2 (Report 05000272/2012001 and 05000311/2012001) ML12248A0402012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Salem Nuclear Generating Station, Units 1 and 2 IR 05000272/20110012012-03-0505 March 2012 Annual Assessment Letter for Salem Nuclear Generating Station, Unit Nos. 1 and 2 (Report 05000272/2011001 and 05000311/2011001) ML1124112942011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Salem Nuclear Generating Station, Units 1 and 2 IR 05000272/20100012011-03-0404 March 2011 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2, EOC-11 (Report 05000272/2010001 and 05000311/2010001) ML1024403642010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Salem Nuclear Generating Station, Units 1 and 2 ML1029505872010-03-12012 March 2010 Email from Ohara, Timothy to Conte, Richard, FW: Salem U1 Inspection Plan. ML1006208082010-03-0303 March 2010 EOC Letter and Report 22 ML0924403092009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Salem Nuclear Generating Station, Unit Nos. 1 and 2 (September 1, 2009) IR 05000272/20090012009-03-0404 March 2009 Annual Assessment Letter - Salem Nuclear Generating Station, Units 1 and 2 (05000272-09-001 and 05000311-09-001) IR 05000272/20080012008-03-0303 March 2008 Annual Assessment Letter EOC 2007 ROP8 - Salem Station (05000272-08-001, 05000311-08-001) ML0734706552007-12-13013 December 2007 ROP 8 - Salem - Change to Inspection Plan, 12/13/07 ML0724309472007-08-31031 August 2007 Mid-Cycle Review and Inspection Plan IR 05000272/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Salem Generating Station (Report 05000272-07-001, 05000311-07-001) ML0624306512006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Salem Nuclear Generating Station IR 07200200/19600012006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Salem Nuclear Generating Station (Report 05-272/2006001 and 05-311/2006001) ML0406307982004-03-0303 March 2004 2003-04 Annual Assessment Letter - Salem ML0323905112003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Salem Units 1 and 2 ML0306206932003-03-0303 March 2003 2003 Annual Assessment Letter - Salem Nuclear Generating Station 2024-08-29
[Table view] Category:Inspection Report
MONTHYEARIR 05000272/20240032024-10-30030 October 2024 Integrated Inspection Report 05000272/2024003 and 05000311/2024003 IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 IR 05000272/20230112023-03-0707 March 2023 Comprehensive Engineering Team Inspection Report 05000272/2023011 and 05000311/2023011 IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) IR 05000272/20220042023-01-31031 January 2023 Integrated Inspection Report 05000272/2022004 and 05000311/2022004 IR 05000272/20220112023-01-0606 January 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000272/2022011 and 05000311/2022011 IR 05000272/20220032022-11-0909 November 2022 Integrated Inspection Report 05000272/2022003 and 05000311/2022003 IR 05000272/20224022022-10-14014 October 2022 Cyber Security Report 05000272/2022402 and 05000311/2022402 - Cover Letter Only IR 05000272/20220052022-08-31031 August 2022 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022005 and 05000311/2022005) IR 05000272/20220022022-08-0808 August 2022 Integrated Inspection Report 05000272/2022002 and 05000311/2022002 IR 05000272/20224012022-07-21021 July 2022 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2022401, 05000272/2022401, and 05000311/2022401 (Cover Letter Only) IR 05000272/20225012022-06-14014 June 2022 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2022501, 05000272/2022501, and 05000311/2022501 IR 05000272/20220012022-05-0404 May 2022 Integrated Inspection Report 05000272/2022001 and 05000311/2022001 IR 05000272/20223012022-04-27027 April 2022 Initial Operator Licensing Examination Report 05000272/2022301 and 05000311/2022301 IR 05000272/20210132022-03-10010 March 2022 Evaluation of Changes, Tests, and Experiments Baseline IR 05000354/2021013, 05000272/2021013 and 05000311/2021013 & ISFSI IR 07200048/2021001 Related to PSEG Evals of Stations & Planned Wind Port Manufacturing Facility IR 05000272/20210062022-03-0202 March 2022 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2021006 and 05000311/2021006) IR 05000272/20210042022-02-10010 February 2022 Integrated Inspection Report 05000272/2021004 and 05000311/2021004 IR 05000272/20215012021-11-30030 November 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2021501, 05000272/2021501 and 05000311/2021501 IR 05000272/20214022021-11-19019 November 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2021402, 05000272/2021402 and 05000311/2021402 IR 05000272/20210032021-11-0202 November 2021 Integrated Inspection Report 05000272/2021003 and 05000311/2021003 IR 05000272/20214032021-10-28028 October 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Biennial Problem Identification and Resolution Inspection Report (Security-Related Information) 05000354/2021403, 05000272/2021403 and 05000311/2021403 (Cover Letter Only IR 05000272/20210122021-10-28028 October 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Biennial Problem Identification and Resolution Inspection Report 05000354/2021012, 05000272/2021012 and 05000311/2021012 IR 05000272/20210112021-09-30030 September 2021 Temporary Instruction 2515/194 Inspection Report 05000272/2021011 and 05000311/2021011 IR 05000272/20210052021-09-0101 September 2021 Updated Inspection Plan for the Salem Nuclear Generating Station (Report 05000272/2021005 and 05000311/2021005) IR 05000272/20210022021-08-18018 August 2021 Reissued Integrated Inspection Report 05000272/2021002 and 05000311/2021002 ML21222A1402021-08-11011 August 2021 Integrated Inspection Report 05000272/2021002 and 05000311/2021002 IR 05000272/20210012021-05-0505 May 2021 Integrated Inspection Report 05000272/2021001 and 05000311/2021001 IR 05000272/20210102021-03-0909 March 2021 Triennial Fire Protection Inspection Report 05000272/2021010 and 05000311/2021010 IR 05000272/20200062021-03-0303 March 2021 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2020006 and 05000311/2020006) IR 05000272/20214012021-02-23023 February 2021 and Salem Nuclear Generating Station, Units 1 and 2: Security Baseline Inspection Report 05000354/2021401, 05000272/2021401 and 05000311/2021401 (Letter Only) IR 05000272/20200042021-02-0909 February 2021 Generating Station, Units 1 and 2: Integrated Inspection Report 05000272/2020004 and 05000311/2020004 2024-09-23
[Table view] Category:Letter
MONTHYEARIR 05000272/20240032024-10-30030 October 2024 Integrated Inspection Report 05000272/2024003 and 05000311/2024003 ML24296B1932024-10-23023 October 2024 Project Manager Assignment LR-N24-0068, Core Operating Limits Report - Cycle 282024-10-21021 October 2024 Core Operating Limits Report - Cycle 28 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 05000272/LER-2024-001, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location 2024-09-23
[Table view] |
Inspection Report - Salem - 2016005 |
---|
|
|
Text
ust 31, 2016
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2 (REPORT 05000272/2016005 AND 05000311/2016005)
Dear Mr. Sena:
On August 9, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Salem Nuclear Generating Station, Unit Nos. 1 and 2 (Salem). The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Salem Unit 1 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Salem Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections for Salem Unit 1.
The NRC determined that overall, Salem Unit 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Salem Unit 2 during the most recent quarter was within the Regulatory Response Column of the NRCs ROP Action Matrix due to a White PI for Unplanned Scrams per 7,000 Hours Critical.
This PI changed to White in the second quarter of 2016 due to a reactor trip on June 28, 2016, preceded by three other unplanned reactor trips (August 5, 2015, February 4, 2016, and February 14, 2016) within the assessment period.
Therefore, in addition to ROP baseline inspections, the NRC plans to conduct a supplemental inspection at Unit 2 in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, upon notification of your readiness. The inspection will be focused on ensuring that root causes and contributing causes of the unplanned scrams are understood, the extent of condition and causes are identified, and the corrective actions implemented are sufficient to prevent recurrence. The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last half of the inspection period in the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues.
The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Final Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the Salem site, the Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections, the full implementation of the orders mentioned above by performing Temporary Instruction 2515-191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
In Staff Requirements Memorandum - SECY 16-0009, Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities, (ADAMS Accession No. ML16104A158) the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct assessment reviews and communicate changes in the assessment of licensee performance quarterly, and will also issue end-of-cycle assessment letters.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact Fred Bower at (610) 337-5200 with any questions you have regarding this letter.
Sincerely,
/RA/
Michael L. Scott, Director Division of Reactor Projects Docket Nos. 50-272 and 50-311 License Nos. DPR 70 and DPR 75 Enclosure: Salem Inspection/Activity Plan Cc w/encl: Distribution via ListServ
ML16242A099 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE R1/DRP R1/DRP R1/DRP R1/DRP R1/DRP NAME RVadella/RB for MDraxton PFinney FBower MScott DATE 08/22/16 08/18/16 08/22/16 08/28/16 08/31/16
Page 1 of 3 Salem 08/12/2016 09:10:06 Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111117T - MODS INSPECTION 4 1, 2 07/18/2016 07/22/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 08/01/2016 08/05/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications ISFSI - ISFSI FOLLOWUP INSPECTION 2 1, 2 07/26/2016 07/26/2016 IP 60855 Operation Of An ISFSI 71124 - RADIATION PROTECTION 1 1, 2 07/25/2016 07/29/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 07/25/2016 07/29/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 07/25/2016 07/29/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 07/25/2016 07/29/2016 IP 71124.04 Occupational Dose Assessment 1, 2 07/25/2016 07/29/2016 IP 71124.05 Radiation Monitoring Instrumentation EXM12/12 - SALEM INITIAL OL EXAMINATION 4 1 11/14/2016 11/18/2016 U01930 FY17-SALEM INITIAL OPERATOR LICENSING EXAM 1 12/12/2016 12/23/2016 U01930 FY17-SALEM INITIAL OPERATOR LICENSING EXAM 71124 - RADIATION PROTECTION 1 1, 2 08/22/2016 08/26/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 08/22/2016 08/26/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 08/22/2016 08/26/2016 IP 71124.04 Occupational Dose Assessment 1, 2 08/22/2016 08/26/2016 IP 71124.05 Radiation Monitoring Instrumentation 711107T - TRIENNIAL HEAT SINK 1 1, 2 11/14/2016 11/18/2016 IP 7111107T Heat Sink Performance 71124 - RADIATION PROTECTION 1 1, 2 12/12/2016 12/16/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/12/2016 12/16/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/12/2016 12/16/2016 IP 71124.04 Occupational Dose Assessment 1, 2 12/12/2016 12/16/2016 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 12/12/2016 12/16/2016 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71124 - RADIATION PROTECTION 1 1, 2 04/03/2017 04/07/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/03/2017 04/07/2017 IP 71124.02 Occupational ALARA Planning and Controls 2 04/03/2017 04/07/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 2 04/03/2017 04/07/2017 IP 71124.04 Occupational Dose Assessment 1, 2 04/03/2017 04/07/2017 IP 71124.05 Radiation Monitoring Instrumentation This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 3 Salem 08/12/2016 09:10:06 Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP - EP PROGRAM INSPECTION 1 1, 2 05/15/2017 05/19/2017 IP 7111402 Alert and Notification System Testing 1, 2 05/15/2017 05/19/2017 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 05/15/2017 05/19/2017 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 05/15/2017 05/19/2017 IP 71151 Performance Indicator Verification 7111108P - U2 INSERVICE INSPECTION 1 2 04/24/2017 05/05/2017 IP 7111108P Inservice Inspection Activities - PWR 71124 - RADIATION PROTECTION 1 1, 2 05/01/2017 05/05/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 05/01/2017 05/05/2017 IP 71124.02 Occupational ALARA Planning and Controls 2 05/01/2017 05/05/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 05/01/2017 05/05/2017 IP 71124.04 Occupational Dose Assessment 1, 2 05/01/2017 05/05/2017 IP 71124.05 Radiation Monitoring Instrumentation 71152B - PI&R BIENNIAL 2 1, 2 05/22/2017 05/26/2017 IP 71152B Problem Identification and Resolution 1, 2 06/05/2017 06/09/2017 IP 71152B Problem Identification and Resolution 71124 - RADIOACTIVE EFFLUENTS 1 1, 2 06/12/2017 06/16/2017 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 06/12/2017 06/16/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment CDBI - COMPONENT DESIGN BASIS INSPECTION 6 1, 2 06/12/2017 06/16/2017 IP 7111121 Component Design Bases Inspection 1, 2 06/26/2017 06/30/2017 IP 7111121 Component Design Bases Inspection 1, 2 07/10/2017 07/14/2017 IP 7111121 Component Design Bases Inspection 7111111B - SALEM REQUAL INSP WITH P/F RESULTS 2 1, 2 09/12/2017 09/16/2017 IP 7111111B Licensed Operator Requalification Program 1/22EXM - SALEM INITIAL EXAM 4 1 12/11/2017 12/15/2018 U01949 FY18-SALEM INITIAL OPERATOAR LICENSING EXAM 1 01/22/2018 02/02/2018 U01949 FY18-SALEM INITIAL OPERATOAR LICENSING EXAM 71124 - RADIATION PROTECTION 1 1, 2 08/21/2017 08/25/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 08/21/2017 08/25/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 08/21/2017 08/25/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 08/21/2017 08/25/2017 IP 71124.04 Occupational Dose Assessment This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 3 of 3 Salem 08/12/2016 09:10:06 Inspection / Activity Plan Report 22 07/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RADIATION PROTECTION 1 1, 2 08/21/2017 08/25/2017 IP 71124.05 Radiation Monitoring Instrumentation 71124.08 - RADWASTE 1 1, 2 10/16/2017 10/20/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 7111108P - U1 INSERVICE INSPECTION 1 1 10/23/2017 11/03/2017 IP 7111108P Inservice Inspection Activities - PWR 71124 - RADIATION PROTECTION 1 1 10/23/2017 10/27/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/23/2017 10/27/2017 IP 71124.02 Occupational ALARA Planning and Controls 1 10/23/2017 10/27/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/23/2017 10/27/2017 IP 71124.04 Occupational Dose Assessment 1 10/23/2017 10/27/2017 IP 71124.05 Radiation Monitoring Instrumentation 71124 - RADIATION PROTECTION AND PI 1 1, 2 12/04/2017 12/08/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/04/2017 12/08/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/04/2017 12/08/2017 IP 71124.04 Occupational Dose Assessment 1, 2 12/04/2017 12/08/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 12/04/2017 12/08/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 7111105T - TRIENNIAL FIRE PROTECTION 4 1, 2 02/12/2018 02/16/2018 IP 7111105T Fire Protection [Triennial]
1, 2 02/26/2018 03/02/2018 IP 7111105T Fire Protection [Triennial]
EP - EP EXERCISE INSPECTION 4 1, 2 05/21/2018 05/25/2018 IP 7111401 Exercise Evaluation This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.