ML21138A013: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot change)
(StriderTol Bot change)
 
(2 intermediate revisions by the same user not shown)
(No difference)

Latest revision as of 15:12, 20 January 2022

NRC Response to Request for Additional Time to Respond to James A. Fitzpatrick Nuclear Power Plant: Final Significance Determination of a White Finding with Assessment Follow Up and Notice of Violation-Inspection No. 05000333/2021090
ML21138A013
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/18/2021
From: Dan Collins
NRC Region 1
To: Rhoades D
Exelon Generation Co
References
EA-20-138 IR 2021090
Download: ML21138A013 (2)


See also: IR 05000333/2021090

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BLVD.

KING OF PRUSSIA, PA 19406-2713

May 18, 2021

EA-20-138

Mr. David P. Rhoades

Senior Vice President

Exelon Generation Company, LLC

President and Chief Nuclear Officer, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: U.S. NUCLEAR REGULATORY COMMISSION RESPONSE TO REQUEST

FOR ADDITIONAL TIME TO RESPOND TO JAMES A. FITZPATRICK

NUCLEAR POWER PLANT - FINAL SIGNIFICANCE

DETERMINATION OF A WHITE FINDING WITH ASSESSMENT

FOLLOW-UP AND NOTICE OF VIOLATION - NRC INSPECTION

REPORT 05000333/2021090

Dear Mr. Rhoades:

The U.S. Nuclear Regulatory Commission (NRC) acknowledges receipt of Exelon Generations

verbal request on May 17, 2021, for additional time to respond to the Final Notice of Violation

(ML21105A543) issued on April 20, 2021. The basis for the extension was due to additional

time needed for clarification regarding the backfit appeal and violation dispute processes.

Based on this discussion, I approve the request for a 14-day extension of time from May 20,

2021, to June 3, 2021, to formally respond to the violation.

Should you have any questions regarding this matter, please contact Ms. Erin E. Carfang, Chief,

Projects Branch 1, Division of Operating Reactor Safety in Region I, at 610-337-5120.

Sincerely,

Digitally signed by Daniel S.

Daniel S. Collins Collins

Date: 2021.05.18 13:27:26

-04'00'

Daniel S. Collins, Director

Division of Operating Reactor Safety

Docket No. 50-333

License No. DPR-59

cc: Distribution via ListServ

D. Rhoades 2

SUBJECT: U.S. NUCLEAR REGULATORY COMMISSION RESPONSE TO REQUEST

FOR ADDITIONAL TIME TO RESPOND TO JAMES A. FITZPATRICK

NUCLEAR POWER PLANT - FINAL SIGNIFICANCE

DETERMINATION OF A WHITE FINDING WITH ASSESSMENT

FOLLOW-UP AND NOTICE OF VIOLATION - NRC INSPECTION

REPORT 05000333/2021090 DATED MAY 18, 2021

DISTRIBUTION

ECarfang, DORS

JDeBoer, DORS

SHaney, DORS

CSwisher, DORS

EMiller, DORS, SRI

JEngland, DORS, RI

ATrudell, DORS, AA

MHaire, RI, OEDO

AVegel, OE

JPeralta, OE

RFretz, OE

BHughes, NRR

RidsNrrPMFitzPatrick Resource

RidsNrrDorlLpl1 Resource

ROPReports Resource

DORS Branch Chiefs

DScrenci, PAO,

NSheehan, PAO

DTifft, SLO

DGarvin, ORA

ROPAssessment Resource

RidsNrrDrolrabResource

OE, Region I

DOCUMENT NAME: https://usnrc.sharepoint.com/teams/region-i-branch-1/shared documents/fitzpatrick acknowledgement letter extension.docx

ADAMS ACCESSION NO. ML21138A013

Non-Sensitive Publicly Available

SUNSI Review/

Sensitive Non-Publicly Available

OFFICE RI/DORS RI/DORS RI/EAGL RI/DORS

NAME JDeBoer MYoung MMcLaughlin DCollins

DATE 5/18/2021 5/18/2021 5/18/2021 5/18/2021

OFFICIAL RECORD COPY