JAFP-16-0130, License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition - Supplement 2

From kanterella
Jump to navigation Jump to search

License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition - Supplement 2
ML16223A717
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/10/2016
From: Brian Sullivan
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CAC MF7347, JAFP-16-0130
Download: ML16223A717 (8)


Text

Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

James A. FitzPatrick NPP P.O. Box 110 Lycoming, NY 13093 Tel 315-342-3840 Brian R. Sullivan Site Vice President - JAF JAFP-16-0130 August 10, 2016 10 CFR 50.90 10 CFR 50.54(q)(4)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852

Subject:

License Amendment Request to Revise the James A. FitzPatrick Emergency Plan to Address the Permanently Defueled Condition - Supplement 2 (CAC No.

MF7347)

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-59

References:

1. ENOI letter, License Amendment Request to Revise the James A.

FitzPatrick Emergency Plan to Address the Permanently Defueled Condition, JAFP-16-0012, dated February 4, 2016

2. ENOI letter, License Amendment Request to Revise the James A.

FitzPatrick Emergency Plan to Address the Permanently Defueled Condition - Supplement 1 (CAC No. MF7347), JAFP-16-0113, dated July 6, 2016

3. NRC memo, Supplemental Request for Additional Information Regarding Proposed Emergency Plan Change Amendment for the Permanently Defueled Condition, dated August 3, 2016

Dear Sir or Madam:

By letter dated February 4, 2016 [Reference 1], Entergy Nuclear Operations, Inc. (ENOI) proposed an amendment to Renewed Facility Operating License DPR-59 for the James A.

FitzPatrick Nuclear Power Plant (JAF). The proposed amendment would revise the JAF Emergency Plan for the permanently defueled condition. Specifically, the proposed changes would revise the on-shift staffing and Emergency Response Organization (ERO) staffing levels.

By letter dated July 6, 2016 [Reference 2], ENOI provided responses to Requests for Additional Information (RAI). On August 3, 2016, [Reference 3] the NRC requested additional RAI. of this letter provides the responses to the supplemental RAI.

The conclusions of the no significant hazards consideration and the environmental considerations contained in Reference 1 are not affected by, and remain applicable to, this supplement.

JAFP-16-0130 Page 2 of 2 contains a list of new regulatory commitments. If you should have any questions regarding this transmittal, please contact Mr. James D. Jones, Emergency Planning Manager, at 315-349-6030.

I declare under penalty of perjury that the foregoing is true and correct. Executed on August 10, 2016.

Sincerely, Brian R. Sullivan Site Vice President BRS/JDJ/pc Attachments: 1. Response to Request for Additional Information

2. List of Regulatory Commitments cc: Director, Office of Nuclear Reactor Regulation NRG Region I Administrator NRG Resident Inspector NRG Project Manager NYSPSC NYSERDA

JAFP-16-0130 Attachment 1 Response to Request for Additional Information (3 Pages)

JAFP-16-0130 Attachment 1 Response to Supplemental Request for Additional Information RESPONSE TO SUPPLEMENTAL REQUEST FOR ADDITIONAL INFORMATION REGARDING PROPOSED EMERGENCY PLAN CHANGE AMENDMENT FOR THE PERMANENTLY DEFUELED CONDITION ENTERGY NUCLEAR OPERATIONS. INC.

JAMES A. FITZPATRICK NUCLEAR POWER PLANT DOCKET NO. 50-333 RENEWED FACILITY OPERATING LICENSE NO. DPR-59 By letter dated February 4, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16043A427), as supplemented by letter dated July 6, 2016 (ADAMS Accession No. ML16188A388), Entergy Nuclear Operations, Inc. (ENOI or the licensee) submitted a request for U. S. Nuclear Regulatory Commission (NRC) approval of a license amendment request for the James A. FitzPatrick (JAF) Nuclear Power Plant concerning proposed changes to the Emergency Plan for the permanently defueled condition. On March 16, 2016, pursuant to 10 CFR 50.82(a)(1)(i), ENOI provided a formal notification to the NRC of its intention to permanently cease power operations of JAF on January 27, 2017 (ADAMS Accession No. ML16076A391). The proposed changes would revise the on-shift staffing and Emergency Response Organization staffing levels.

On August 3, 2016, the NRC staff conducted a clarification call with ENOI to clarify the licensees July 6, 2016, RAI responses.

As discussed in the clarification call, supplemental information is needed by the NRC staff to complete its evaluation.

1. Attachment 1 (Description and Evaluation of Proposed Changes) of ENOs February 4, 2016, submittal letter (page 11 of 36) under Section 3.2.1, Analysis of Proposed Changes / ERO Staffing, states:

To validate the results of the analysis, drills will be developed and conducted prior to implementation of the changes described within. The drills will be conducted to confirm the ability of the post-shutdown ERO to perform the necessary functions of each emergency response facility and will utilize the post-shutdown procedures that will be developed depicting the revised assignment of duties. The drills will be used to train and qualify post-shutdown ERO members, evaluate and validate the ability to accomplish the stated mission of each emergency response facility, and ensure that the planning standard functions are preserved with no degradation in time sensitive activities or in the ability to communicate with offsite response organizations. The drills will also validate that the post-shutdown ERO continues to address the risks to public health and safety and comply with the JAF Emergency Plan, site commitments, and applicable regulations.

Page 1 of 3

JAFP-16-0130 Page 2 of 2 To support NRC and FEMAs evaluation that proposed ERO staffing changes on the ability of the licensee to effectively implement the emergency plan, as revised, and to verify that changes pose no impact to offsite REP plans as currently approved by FEMA:

a. Discuss whether a drill will be conducted involving a spent fuel pool event that tests the major elements of the licensees emergency plan and communications/

coordination with offsite response organizations, including at the Joint Information Center, prior to implementation, and

Response

JAF will conduct one or more drills to demonstrate the ability to implement the major elements of the Post Shutdown Emergency Plan (PSEP), and communications/coordination with offsite response organizations, including at the Joint Information Center (JIC). Implementing procedures are currently being updated to address the permanently shut down and defueled condition and will be used to support training of ERO staff and conduct of drills.

In the permanently shut down and defueled condition, the primary events of concern in the immediate post-shutdown and defueled condition will involve loss of spent fuel pool (SFP) cooling and/or water inventory. Therefore, the drill scenario(s) will necessarily involve the SFP.

This action is included as a new regulatory commitment in Attachment 2.

b. Discuss whether State and local response organizations will be offered the opportunity to participate, and the NRC and FEMA be provided advance notice and the opportunity to observe drill activities.

Response

New York State and Oswego County emergency response organizations will be offered the opportunity to participate in the drill(s) described in response to Part a of this RAI. JAF has not yet finalized a schedule of drills that will be conducted. As described in Reference 1, when the dates are finalized, the NRC and FEMA will be notified through the Office of Nuclear Reactor Regulation Project Manager and provided with a schedule. These actions are included as new regulatory commitment in Attachment 2.

2. Attachment 1 of ENOs February 4, 2016, submittal letter (page 16 of 36) under Section 3.2.1.2, Analysis of Proposed Changes / ERO Staffing / Operations Support Center, states in part:

The primary events of concern in the immediate post-shut-down and defueled condition will be a fuel handling accident and a loss of SFP cooling and/or water inventory. During fuel handling activities there will be extra personnel on site that will, were a fuel handling accident to occur, be able to respond to the event. Events involving a loss of SFP cooling and/or water inventory can be addressed by implementation of SFP inventory makeup strategies required under 10 CFR 50.54(hh)(2). These strategies also continue to be required as a license condition.

The JAF analysis of proposed post-shutdown on-shift staffing only appears to address a fuel handling accident, which the licensee appears to define as mechanical Page 2 of 3

JAFP-16-0130 Attachment 1 Response to Supplemental Request for Additional Information damage to the spent fuel during handling or by impact with a heavy object as the only credible scenario for a gaseous release. Has an analysis been performed to verify that sufficient on-shift staffing would be available to promptly implement SFP inventory makeup strategies required under 10 CFR 50.54(hh)(2) if required without impacting the performance of designated EP functions?

Response

A specific analysis was not performed to determine if sufficient on-shift staffing would be available to promptly implement SFP inventory makeup strategies. The JAF 5-person Fire Brigade is currently responsible for implementing the SFP inventory makeup strategies required under 10 CFR 50.54(hh)(2). In the permanently shut down and defueled condition, JAF will continue to maintain a trained and qualified 5-person Fire Brigade responsible for implementation of the SFP inventory makeup strategies. The Fire Brigade personnel identified in the PSEP are separate and distinct from those responsible for implementing the major elements of the emergency plan including emergency classification (Shift Manager), offsite notifications (Control Room Supervisor), and dose assessment/protective action recommendation development (Radiological Specialist). Therefore, sufficient staffing is available to promptly implement SFP inventory makeup strategies required under 10 CFR 50.54(hh)(2) without impacting the performance of designated emergency plan functions.

As described in Section 3.2.1.2 of Reference 2, events involving a loss of SFP cooling and/or water inventory can be addressed by implementation of SFP inventory makeup strategies required under 10 CFR 50.54(hh)(2). These strategies will continue to be maintained to satisfy Condition 2.R of the JAF Renewed Facility Operating License.

References

1. Letter, License Amendment Request to Revise the James A. FitzPatrick Emergency Plan to Address the Permanently Defueled Condition - Supplement 1 (CAC No.

MF7347), JAFP 16-0113, dated July 6, 2016 (ML16188A388)

2. Letter, Entergy Nuclear Operations, Inc. to USNRC, License Amendment Request to Revise the James A. FitzPatrick Emergency Plan to Address the Permanently Defueled Condition, JAFP-16-0012, dated February 4, 2016 (ML16035A309)

Page 3 of 3

JAFP-16-0130 Attachment 2 List of Regulatory Commitments (1 Page)

JAFP-16-0130 Attachment 2 List of Regulatory Commitments This table identifies actions discussed in this letter for which Entergy commits to perform. Any other actions discussed in this submittal are described for the NRCs information and are not commitments.

TYPE (Check one) SCHEDULED ONE-TIME CONTINUING COMPLETION DATE COMMITMENT ACTION COMPLIANCE (If Required)

JAF will conduct one or more drills involving Prior to the loss of spent fuel pool (SFP) cooling implementation of and/or inventory to demonstrate the ability the PSEP.

to implement the major elements of the X

Post Shutdown Emergency Plan (PSEP),

and communications/coordination with offsite response organizations, including at the Joint Information Center (JIC).

JAF will provide the NRC and FEMA with Within 21 days of advanced notice and an opportunity to development of a observe PSEP implementation drill activities schedule with which by providing a schedule of drill(s) to be PSEP conducted to the NRC through the Office of implementation X

Nuclear Reactor Regulation Project drills will be Manager. JAF will offer New York State and conducted.

Oswego County emergency response organizations the opportunity to participate in the drill(s).

Page 1 of 1