Letter Sequence Response to RAI |
---|
CAC:MF8293, Control Room Habitability (Approved, Closed) |
Results
Other: JAFP-15-0027, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), JAFP-15-0105, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), JAFP-16-0028, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), JAFP-16-0140, Seventh Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, JAFP-17-0018, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), ML16243A055, ML16243A056, ML17041A196, ML17041A274, ML17086A205, ML17090A188
|
MONTHYEARJAFP-15-0027, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other JAFP-15-0105, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other JAFP-16-0028, Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other CNRO-2016-00010, Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2016-03-30030 March 2016 Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) Project stage: Request JAFP-16-0096, Supporting Information for Request for Relaxation of March 12, 2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool..2016-06-16016 June 2016 Supporting Information for Request for Relaxation of March 12, 2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool.. Project stage: Request ML16235A0812016-08-18018 August 2016 Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment Project stage: Request JAFP-16-0140, Seventh Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2016-08-25025 August 2016 Seventh Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other JAFP-16-0147, Request for Extension to Comply with 03/12/2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Reliable Spent Fuel Pool Instrumentation2016-09-0808 September 2016 Request for Extension to Comply with 03/12/2012 Commission Orders Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Reliable Spent Fuel Pool Instrumentation Project stage: Request ML16243A0552016-09-0909 September 2016 Notice of Consideration of Approval of Transfer of Renewed Facility Operating License and Conforming Amendment, and Opportunity for a Hearing - James A. Fitzpatrick Nuclear Power Plant Project stage: Other ML16243A0562016-09-0909 September 2016 FRN for License Transfer for FitzPatrick NPP: from ENO to Exelon Project stage: Other ML16250A4612016-09-19019 September 2016 Request for Withholding Information from Public Disclosure for James A. FitzPatrick Nuclear Power Plant Project stage: Withholding Request Acceptance ML16266A4832016-10-0303 October 2016 Plan: Acceptance of Requested Licensing Action Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment Project stage: Acceptance Review ML16299A0192016-11-0202 November 2016 Request for Additional Information Regarding Direct License Transfer from Entergy to Exelon Project stage: RAI ML16335A1042016-11-29029 November 2016 Independent Spent Fuel Storage Installation, Response to Request for Additional Information Regarding Application for Order Approving Transfer F Renewed Facility Operating License and Proposed Conforming License Amendment Project stage: Response to RAI ML17012A2802017-01-0404 January 2017 Withdrawal of Certification of Permanent Cessation of Power Operations Project stage: Request JAFP-17-0018, Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2017-02-28028 February 2017 Eighth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML17041A2742017-03-0101 March 2017 Federal Register Notice - Order Approving Direct License Transfer of FitzPatrick Power Plant from Entergy Nuclear FitzPatrick, LLC and Entergy Nuclear Operations, Inc. to Exelon Generation Company, LLC Project stage: Other ML17041A1962017-03-0101 March 2017 LTR with Order Approving Direct Transfer of Renewed Facility Operating License and Independent Spent Fuel Storage Installation General License and Conforming Amendment Project stage: Other ML17086A2052017-03-27027 March 2017 Notification of Expected Date of Transfer of Nuclear Unit to Exelon Generation Company, LLC, Notification of Satisfactory Documentary Evidence of Insurance, and Notification of Receipt of All Required Regulatory Approvals Project stage: Other ML17090A1882017-03-31031 March 2017 ISFSI - Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Entergy Project stage: Other ML17082A2832017-03-31031 March 2017 Issuance of Amendment Application for Order to Transfer Renewed Facility Operating License, Independent Spent Fuel Storage Installation General License, and Conforming Amendment from Entergy Nuclear to Exelon Generation CAC No. MF8293) Project stage: Approval ML17206A3952017-07-24024 July 2017 ISFSI - Application for Order Approving Transfer of Direct Ownership Under Renewed Facility Operating License and Proposed Conforming License Amendment Project stage: Request 2016-08-25
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000333/20240902024-10-29029 October 2024 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000333/2024090 JAFP-24-0055, Response to Request for Additional Information for License Amendment Request to Add Temporary Change to TS 3.3.2.1, Condition C, Control Rod Block Instrumentation2024-10-29029 October 2024 Response to Request for Additional Information for License Amendment Request to Add Temporary Change to TS 3.3.2.1, Condition C, Control Rod Block Instrumentation IR 05000333/20244022024-10-28028 October 2024 Material Control and Accounting Program Inspection Report 05000333/2024402 (Cover Letter Only) ML24276A1332024-10-17017 October 2024 Issuance of Amendment No. 357 Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision-4, and Administrative Changes ML24282B0302024-10-11011 October 2024 Project Manager Assignment RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24207A0192024-10-0909 October 2024 SE Addendum Related to the License Amendment No. 338 for Implementation of the Alternative Source Term (DPO-2021-001) JAFP-24-0051, Reply to Preliminary White Finding and Apparent Violation in NRC Inspection Report 05000333/2024011; EA-24-0882024-10-0303 October 2024 Reply to Preliminary White Finding and Apparent Violation in NRC Inspection Report 05000333/2024011; EA-24-088 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24270A0742024-09-30030 September 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0134) - LTR ML24270A1452024-09-26026 September 2024 Notice of Enforcement Discretion for James A. Fitzpatrick Nuclear Power Plant JAFP-24-0046, Request for Enforcement Discretion for Technical Specification (TS) 3.3.2.1 Control Rod Block Instrumentation2024-09-25025 September 2024 Request for Enforcement Discretion for Technical Specification (TS) 3.3.2.1 Control Rod Block Instrumentation JAFP-24-0047, License Amendment Request – Temporary Addition to TS 3.3.2.1 Condition C, Control Rod Block Instrumentation to Support Upgrade to Rod Worth Minimizer Software2024-09-25025 September 2024 License Amendment Request – Temporary Addition to TS 3.3.2.1 Condition C, Control Rod Block Instrumentation to Support Upgrade to Rod Worth Minimizer Software JAFP-24-0045, Supplemental Information for License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2024-09-20020 September 2024 Supplemental Information for License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20240112024-09-19019 September 2024 Follow-up to Inspection Procedure 71153 Report 05000333/2024011 and Preliminary White Finding and Apparent Violation JAFP-24-0044, Core Operating Limits Report Cycle 272024-09-16016 September 2024 Core Operating Limits Report Cycle 27 JAFP-24-0043, Revision to Commitment Relating to Resolution of Anchor Darling Double Disc Gate Valve Part 21 Issues2024-09-12012 September 2024 Revision to Commitment Relating to Resolution of Anchor Darling Double Disc Gate Valve Part 21 Issues 05000333/LER-2024-002, Reactor Protection System Electric Power Monitoring System Trip Caused Primary Containment Isolation2024-09-0404 September 2024 Reactor Protection System Electric Power Monitoring System Trip Caused Primary Containment Isolation ML24165A0382024-09-0404 September 2024 Issuance of Amendment No. 356 Update Fuel Handling Accident Analysis IR 05000333/20240052024-08-29029 August 2024 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2024005) 05000333/LER-2024-001-01, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-08-21021 August 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000333/20240022024-08-0707 August 2024 Integrated Inspection Report 05000333/2024002 JAFP-24-0034, 10 CFR 50.46 Annual Report2024-07-31031 July 2024 10 CFR 50.46 Annual Report ML24208A0492024-07-30030 July 2024 Notice of Consideration of Issuance of Amendments to Facility Operating Licenses and Proposed No Significant Hazards Consideration Determination (Letter) JAFP-24-0036, Supplement to License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2024-07-29029 July 2024 Supplement to License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-24-0033, Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test2024-07-23023 July 2024 Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20244032024-07-18018 July 2024 Biennial Problem Identification and Resolution Inspection Report 05000333/2024403 (Cover Letter Only) IR 05000333/20244012024-07-15015 July 2024 Security Baseline Inspection 05000333/2024401 RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24190A1932024-07-0909 July 2024 Correction Letter of Amendment No. 355 Revise Technical Specifications Section 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance IR 05000333/20240102024-07-0808 July 2024 Commercial Grade Dedication Inspection Report 05000333/2024010 ML24184A1662024-07-0303 July 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24136A1162024-06-26026 June 2024 Issuance of Amendment No. 355 Revise Technical Specifications Section 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance 05000333/LER-2024-001, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-06-24024 June 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket ML24176A2412024-06-24024 June 2024 Licensed Operator Positive Fitness-for-Duty Test JAFP-24-0027, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-06-24024 June 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations JAFP-24-0026, Supplement to License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (Srvs) Setpoint Lower Tolerance2024-06-12012 June 2024 Supplement to License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (Srvs) Setpoint Lower Tolerance ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 JAFP-24-0023, 2023 Annual Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000333/20240012024-05-0909 May 2024 Integrated Inspection Report 05000333/2024001 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests JAFP-24-0020, 2023 Annual Radioactive Effluent Release Report2024-04-25025 April 2024 2023 Annual Radioactive Effluent Release Report JAFP-24-0019, 2023 REIRS Transmittal of NRC Form 52024-04-18018 April 2024 2023 REIRS Transmittal of NRC Form 5 ML24106A0152024-04-15015 April 2024 Request for Withholding Information from Public Disclosure Response to Request for Additional Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24107A6972024-04-12012 April 2024 Engine Systems, Inc Part 21 Report Re EMD Cylinder Liner Water Leak RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24068A0532024-03-28028 March 2024 Issuance of Amendment No. 354 Revise Technical Specifications Section 3.3.1.2, Source Range Monitors Instrumentation 2024-09-04
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARJAFP-24-0055, Response to Request for Additional Information for License Amendment Request to Add Temporary Change to TS 3.3.2.1, Condition C, Control Rod Block Instrumentation2024-10-29029 October 2024 Response to Request for Additional Information for License Amendment Request to Add Temporary Change to TS 3.3.2.1, Condition C, Control Rod Block Instrumentation RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24085A2362024-03-25025 March 2024 Response to Request for Additional Information JAFP-24-0010, Response to Request for Additional Information for License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance2024-02-29029 February 2024 Response to Request for Additional Information for License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance JAFP-24-0009, Response to Request for Additional Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2024-02-28028 February 2024 Response to Request for Additional Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-22-0032, Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b..2022-06-16016 June 2022 Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.. RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P NMP1L3447, Constellation Energy Generation, LLC - Response to Request for Additional Information - Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs2022-02-0202 February 2022 Constellation Energy Generation, LLC - Response to Request for Additional Information - Proposed Relief Request Associated with Reactor Pressure Vessel Water Level Instrumentation Partial Penetration Nozzle Repairs JAFP-22-0008, Response to Request for Supplemental Information by the Office of Nuclear Reactor Regulation to Support Review of a License Amendment Request to Eliminate Selected Response Time Testing for Reactor Protection System and Primary2022-01-14014 January 2022 Response to Request for Supplemental Information by the Office of Nuclear Reactor Regulation to Support Review of a License Amendment Request to Eliminate Selected Response Time Testing for Reactor Protection System and Primary JAFP-21-0087, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-09-16016 September 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments JAFP-21-0073, Response to Request for Additional Information Regarding Application to Revise the James A. FitzPatrick Nuclear Power Plant Limiting Condition for Operation (LCO) 3.5.1, ECCS - Operating Surveillance.2021-08-0909 August 2021 Response to Request for Additional Information Regarding Application to Revise the James A. FitzPatrick Nuclear Power Plant Limiting Condition for Operation (LCO) 3.5.1, ECCS - Operating Surveillance. JAFP-21-0044, Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments2021-06-11011 June 2021 Response to Request for Additional Information Regarding Request for Approval of Transfer of Licenses and Conforming Amendments ML21138A0132021-05-18018 May 2021 NRC Response to Request for Additional Time to Respond to James A. Fitzpatrick Nuclear Power Plant: Final Significance Determination of a White Finding with Assessment Follow Up and Notice of Violation-Inspection No. 05000333/2021090 JAFP-21-0032, Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting2021-04-20020 April 2021 Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting JAFP-21-0008, Supplement to Application to Revise Surveillance Requirement (SR) 3.5.1.62021-02-18018 February 2021 Supplement to Application to Revise Surveillance Requirement (SR) 3.5.1.6 JAFP-21-0005, Response to Request for Additional Information to Support Review of License Amendment Request - Application to Modify Technical Specifications 3.6.1.3 Primary Containment Isolation Valves2021-01-26026 January 2021 Response to Request for Additional Information to Support Review of License Amendment Request - Application to Modify Technical Specifications 3.6.1.3 Primary Containment Isolation Valves ML20315A2452020-11-10010 November 2020 Response to Request for Additional Information to Support Review of License Amendment Request - Application to Modify Technical Specifications 3.6.1.3 Primary Containment Isolation Valves JAFP-20-0030, Response to Request for Additional Information in Support of License Amendment Request - Proposed Changes to the Technical Specifications to Primary Containment Hydrodynamic Loads2020-04-0606 April 2020 Response to Request for Additional Information in Support of License Amendment Request - Proposed Changes to the Technical Specifications to Primary Containment Hydrodynamic Loads JAFP-20-0026, Response to Request for Additional Information to Support Review of a License Amendment Request to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment Isolation2020-03-31031 March 2020 Response to Request for Additional Information to Support Review of a License Amendment Request to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment Isolation JAFP-20-0020, Response to Request for Additional Information to Support Review of a License Amendment Request to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment Isolation2020-02-21021 February 2020 Response to Request for Additional Information to Support Review of a License Amendment Request to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment Isolation JAFP-20-0008, Response to Request for Additional Information Associated with the License Amendment Request for Application of the Alternative Source Term for Calculating Loss-of-Coolant Accident Dose Consequences2020-01-16016 January 2020 Response to Request for Additional Information Associated with the License Amendment Request for Application of the Alternative Source Term for Calculating Loss-of-Coolant Accident Dose Consequences JAFP-19-0105, Response to Request for Supplemental Information by the Office of Nuclear Reactor Regulation to Support Review of a License Amendment Request to Revise the Allowable Value for Reactor Water Cleanup (Rwcu)...2019-11-0606 November 2019 Response to Request for Supplemental Information by the Office of Nuclear Reactor Regulation to Support Review of a License Amendment Request to Revise the Allowable Value for Reactor Water Cleanup (Rwcu)... ML19279A0012019-10-0606 October 2019 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of an Emergency License Amendment Request for One Time Extension to the TS 3.8.1 Action ... JAFP-19-0057, Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-8802019-06-0404 June 2019 Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-880 NMP1L3279, Response to Request for Additional Information - Proposed Alternatives to Utilize Code Cases N-878 and N-880 for Plants2019-05-0101 May 2019 Response to Request for Additional Information - Proposed Alternatives to Utilize Code Cases N-878 and N-880 for Plants JAFP-19-0009, End of Interval Relief Request Associated with the Fourth Ten-Year Inservice Inspection (ISI) Interval2019-01-15015 January 2019 End of Interval Relief Request Associated with the Fourth Ten-Year Inservice Inspection (ISI) Interval JAFP-19-0006, Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-8802019-01-0808 January 2019 Response to Request for Additional Information - Proposed Alternative to Utilize Code Cases N-878 and N-880 JAFP-18-0068, Response to Request for Additional Information: License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors2018-07-12012 July 2018 Response to Request for Additional Information: License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors RS-18-067, Response to Request for Additional Information Regarding Generic Letter 2016-012018-05-29029 May 2018 Response to Request for Additional Information Regarding Generic Letter 2016-01 JAFP-18-0038, Response to Request for Additional Information Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22018-04-19019 April 2018 Response to Request for Additional Information Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 JAFP-18-0029, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of James A. FitzPatrick Nuclear Power Plant to Address Secondary Containment Personnel Access Door Openings2018-03-15015 March 2018 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation to Support Review of James A. FitzPatrick Nuclear Power Plant to Address Secondary Containment Personnel Access Door Openings JAFP-18-0014, Response to Request for Additional Information on Submittal of Relief Request JAF-15R-05 Concerning Nozzle-to-Vessel Weld and Inner Radii Examinations (Use of Code Case N-702)2018-03-0202 March 2018 Response to Request for Additional Information on Submittal of Relief Request JAF-15R-05 Concerning Nozzle-to-Vessel Weld and Inner Radii Examinations (Use of Code Case N-702) ML18025A7992018-01-25025 January 2018 Response to Request for Additional Information Regarding Generic Letter 2016-01 JAFP-18-0012, Supplemental Response Concerning License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22018-01-22022 January 2018 Supplemental Response Concerning License Amendment Request to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 ML17346A1532017-12-11011 December 2017 Submittal of Response to Request for Additional Information on Relief Requests Associated with the Fifth Inservice Inspection (ISI) Interval JAFP-17-0029, Revision to Entergy'S Expedited Seismic Evaluation Process Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of Near-Term Task Force Review of Insights...2017-04-27027 April 2017 Revision to Entergy'S Expedited Seismic Evaluation Process Report (CEUS Sites) Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of Near-Term Task Force Review of Insights... JAFP-17-0005, Response to 03/12/2012 Request for Information Regarding Recommendations of the Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident, Recommendation 9.3 for Emergency Preparedness2017-01-23023 January 2017 Response to 03/12/2012 Request for Information Regarding Recommendations of the Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident, Recommendation 9.3 for Emergency Preparedness JAFP-16-0182, Spent Fuel Pool Evaluation, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2016-12-22022 December 2016 Spent Fuel Pool Evaluation, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident ML16335A1042016-11-29029 November 2016 Independent Spent Fuel Storage Installation, Response to Request for Additional Information Regarding Application for Order Approving Transfer F Renewed Facility Operating License and Proposed Conforming License Amendment JAFP-16-0170, Response to Request for Additional Information (RAI) Regarding License Amendment Request to Revise Technical Specifications Section 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies - Supplement 12016-11-21021 November 2016 Response to Request for Additional Information (RAI) Regarding License Amendment Request to Revise Technical Specifications Section 5.5.6 for Extension of Type a and Type C Leak Rate Test Frequencies - Supplement 1 JAFP-16-0165, Response to Generic Letter 2016-01 - Monitoring of Neutron Absorbing Materials in Spent Fuel Pools2016-11-0303 November 2016 Response to Generic Letter 2016-01 - Monitoring of Neutron Absorbing Materials in Spent Fuel Pools JAFP-16-0142, Revision to Technical Specification (TS) Administrative Controls for Staffing and Training Upon Permanent Cessation of Operation (CAC No. MF7280) - Supplement 22016-09-19019 September 2016 Revision to Technical Specification (TS) Administrative Controls for Staffing and Training Upon Permanent Cessation of Operation (CAC No. MF7280) - Supplement 2 JAFP-16-0131, Response to Request for Additional Information Regarding Request for Approval of a Certified Fuel Handler Training and Retraining Program2016-08-18018 August 2016 Response to Request for Additional Information Regarding Request for Approval of a Certified Fuel Handler Training and Retraining Program JAFP-16-0130, License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition - Supplement 22016-08-10010 August 2016 License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition - Supplement 2 JAFP-16-0113, License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition - Supplement 12016-07-0606 July 2016 License Amendment Request to Revise the Emergency Plan to Address the Permanently Defueled Condition - Supplement 1 JAFP-16-0114, Response to Request for Additional Information for Proposed Inservice Inspection Program Alternative in Accordance with 10 CFR 50.55a(z)(2), RR-202016-06-27027 June 2016 Response to Request for Additional Information for Proposed Inservice Inspection Program Alternative in Accordance with 10 CFR 50.55a(z)(2), RR-20 JAFP-16-0077, Response to Request for Additional Information (RAI) Regarding Revision to Technical Specification (TS) Administrative Controls for Staffing and Training Upon Permanent Cessation of Operation (CAC No. MF7280) - Supplement 12016-06-0303 June 2016 Response to Request for Additional Information (RAI) Regarding Revision to Technical Specification (TS) Administrative Controls for Staffing and Training Upon Permanent Cessation of Operation (CAC No. MF7280) - Supplement 1 JAFP-16-0078, Response to Request for Additional Information (RAI) Regarding Request for Approval of Certified Fuel Handler Training and Retaining Program2016-06-0303 June 2016 Response to Request for Additional Information (RAI) Regarding Request for Approval of Certified Fuel Handler Training and Retaining Program CNRO-2016-00016, Entergy - Response to RAI Questions and Submittal of Relief Request EN-ISI-15-1 (Updated)2016-06-0202 June 2016 Entergy - Response to RAI Questions and Submittal of Relief Request EN-ISI-15-1 (Updated) 2024-08-09
[Table view] |
Text
Exelon Generation . *- Entergy 10 CFR 50.80 10 CFR 50.90 10 CFR 72.50 November 29, 2016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 James A. FitzPatrick Nuclear Power Plant Renewed Facility Operating License No. DPR-59 Docket No. 50-333 James A. FitzPatrick Nuclear Power Plant Independent Spent Fuel Storage Installation General License SFGL-12 Docket No.72-012
References:
- 1. Entergy Nuclear Operations, Inc. and Exelon Generation Company, LLC Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment, dated August 18, 2016
- 2. Letter from U.S. Nuclear Regulatory Commission to Entergy Nuclear Operations, Inc., James A. FitzPatrick Nuclear Power Plant - Request for Additional Information Regarding Direct License Transfer from Entergy to Exelon (CAC No. MF8293), dated November 2, 2016
- 3. Letter from Patrick Simpson, Manager Licensing, Exelon Generation Company, LLC to U.S. Nuclear Regulatory Commission Document Control Desk, regarding Executed Trust Fund Agreement Amendments and Subordinate Trust Agreement, dated October 29, 2013
Subject:
Response to Request For Additional Information Regarding Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment In accordance with Section 184 of the Atomic Energy Act of 1954, as amended (the "Act"), 10 CFR 50.80, 10 CFR 72.50, and 10 CFR 50.90, Entergy Nuclear FitzPatrick, LLC and Entergy Nuclear Operations, Inc. (collectively referred to as "Entergy") and Exelon Generation Company, LLC ("Exelon Generation") requested written consent approving the transfer of the James A. FitzPatrick Nuclear Power Plant Renewed Facility Operating License No. DPR-59 and the transfer of the generally licensed FitzPatrick Independent Spent Fuel Storage Installation, from Entergy to Exelon Generation (Reference 1).
U.S. Nuclear Regulatory Commission Response to Request for Additional Information Regarding Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment Docket Nos. 50-333 and 72-012 November 29, 2016 Page2 In the Reference 2 letter, the NRC requested additional information regarding the Reference 1 application.
The attachment to this letter contains the response of the parties.
In addition, Entergy and Exelon Generation would like to provide an update to certain technical details regarding the transfer of the FitzPatrick nuclear decommissioning trust ("JAF NDT") to Exelon Generation. The license transfer application (Reference 1, Enclosure 1) on pages 11-12 indicated that the JAF NDT established by Entergy Nuclear FitzPatrick would be transferred to Exelon Generation. However, Entergy Nuclear FitzPatrick will instead transfer the assets of the JAF NDT at closing into a trust established by Exelon Generation, at which time Exelon Generation will assume all liabilities for decommissioning of FitzPatrick. Exelon Generation will take action to update the ( 1)
Second Amended and Restated Qualified Nuclear Decommissioning Master Trust Agreement dated as of July 1, 2013 between Exelon Generation Consolidation, LLC and The Northern Trust Company, as trustee (Reference 3, Attachment 1), to add a qualified decommissioning trust for FitzPatrick and (2)
Second Amended and Restated Non-Qualified Nuclear Decommissioning Master Trust Agreement dated as of July 1, 2013 among NQF Companies Referred to Herein and The Northern Trust Company, as trustee (Reference 3, Attachment 2), to add a non-qualified fund and non-qualified fund limited liability company for FitzPatrick (collectively referred to as the "Trust Agreements"). Exelon Generation's management of the trusts through its wholly owned subsidiaries, including all investments and disbursements, will continue to be consistent with the regulatory requirements in 10 CFR 50.75 and the requirements of the Trust Agreements and Master Terms for Trust Agreements (Reference 3, Attachment 3). Exelon Generation will maintain the decommissioning trust funds segregated from its assets and outside its administrative control in accordance with the requirements of 10 CFR 50.75(e)(l). In accordance with 10 CFR 50.75, with this change, there continues to be reasonable assurance that Exelon Generation will have the funds necessary to cover the estimated decommissioning costs of FitzPatrick at the end of licensed operations.
There are no regulatory commitments contained in this response.
Please contact David P. Helker (Exelon Generation) at 610-765-5525 (David.Helker@exeloncorp.com) or Bryan Ford (Entergy) at 601-368-5516 (bford@entergy.com) if you have any questions or require any additional information regarding this response.
U.S. Nuclear Regulatory Commission Response to Request for Additional Information Regarding Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment Docket Nos. 50-333 and 72-012 Page 3
. Bradley ewell Senior Vice President Regulatory Affairs and General Counsel Exelon Generation Company, LLC STATE OF ILLINOIS Q.{)tJurY o~ DUPA-bs To wit:
CITY OF WARRENVILLE I, J. Bradley Fewell, state that I am the Senior Vice President Regulatory Affairs and General Counsel of Exelon Generation Company, LLC and that I am duly authorized to execute and file this response on behalf of Exelon Generation Company, LLC. To the best of my knowledge and belief, the statements contained in this document with respect to these companies are true and correct. To the extent that these statements are not based on my personal knowledge, they are based upon information provided by employees and/or consultants of the companies. Such information has been reviewed in accordance with company practice, and I believe it to be reliable.
Subscrib9d and sworn before ~e, a Notary Public in and for the State of Illinois and City of Warrenville this;lq-+:bday of f\l rnJt:tnr:;}-f!( , 2016.
WITNESS my Hand and Notarial Seal:
~--- \ Notary Public "OFFICIAL SEAL 11
~ CAROLYN V POLOS Notary Public, State of Illinois My Commission Expires 1/26/2018 My Commission Expires:
Date
U.S. Nuclear Regulatory Commission Response to Request for Additional Information Regarding Application for Order Approving Transferof Renewed Facility Operating License and Proposed Conforming License Amendment Docket Nos. 50-333 and 72-012 Page4 Respectfully, Brian Vice President - FitzPatrick Entergy Nuclear Operations, Inc.
STATE OF NEW YORK To wit:
COUNTY OF OSWEGO I, Brian Sullivan, state that I am Vice President - FitzPatrick of Entergy Nuclear Operations, Inc. and that I am duly authorized to execute and file this response on behalf of Entergy Nuclear Operations, Inc. To the best of my knowledge and belief, the statements contained in this document with respect to these companies are true and correct. To the extent that these statements are not based on my personal knowledge, they are based upon information provided by employees and/or consultants of the companies.
Such information has been reviewed in accordance with company practice, and I believe it to be reliable.
Subscribed and sworn before me, a Notary Public in and for the State of New York and County of Oswego this d'9'th day of '()oY~r , 2016.
WITNESS my Hand and Notarial Seal:
~*A1 a~ . 6CNJ1JJM£L Notary Publk My Commission Expires:
Date
U.S. Nuclear Regulatory Commission Response to Request for Additional Information Regarding Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment Docket Nos. 50-333 and 72-012 November 29, 2016 Page 5
Attachment:
Response to Request for Additional Information Regarding Application for Order Approving Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment cc: w/Attachment Regional Administrator - NRC Region I NRC Senior Resident Inspector - FitzPatrick Nuclear Power Plant NRC Project Manager, NRR- FitzPatrick Nuclear Power Plant A. L. Peterson, NYSERDA
ATTACHMENT RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING APPLICATION FOR ORDER APPROVING TRANSFER OF RENEWED FACILITY OPERATING LICENSE AND PROPOSED CONFORMING LICENSE AMENDMENT
Attachment Response to Request for Additional Information Regarding Application for Order Approving Transferof Renewed Facility Operating License and Proposed Conforming License Amendment Page 1of3 Question - DRA/APHB RAI-1:
The licensee stated on Page 3 of the LAR that:
The proposed transaction will not require any significant change in the staffing and qualifications of personnel who currently operate FitzPatrick. Prior to closing the transaction, Exelon Generation will offer employment to substantially all of the Entergy employees at FitzPatrick such that at the time of the closing of the transaction and transfer of the License, the Entergy employees who accept offers of employment will become employees of Exelon Generation.
Please provide additional information regarding what arrangements have been and will be made to secure adequate resources (i.e., sufficient staffing levels), to ensure that Exelon will continue to comply with 10 CFR 50.54(m)(2) at FitzPatrick Nuclear Power Plant, after Entergy employees are offered employment with Exelon.
Response
Exelon Generation and Entergy are committed to active engagement in the safe operation of the plant and ensuring the appropriate qualified resources are available throughout the license transfer and integration process. Early in the due diligence process, the parties identified the need for contingency planning to ensure appropriate staffing levels and technical expertise are maintained. The parties took a number of actions to secure staffing. Given the breadth of the Exelon Generation fleet, the decreased staffing needs at other facilities in the industry, and the vendor relationships Exelon Generation maintains in New York, the parties are confident that the appropriate level of technical expertise will continue to ensure safe operations during the period Entergy remains the licensed operator and after the transfer of the operating license to Exelon Generation. The parties have focused on ( 1) directly securing expertise throughout the transition process; (2) communicating openly with FitzPatrick employees to ensure transparency and build trust; and (3) providing corporate oversight to ensure continued compliance with high standards during the transition. These actions are described in more detail below.
Directly Securing Expertise Throughout Transition The parties have engaged in a number of strategies to ensure consistent and adequate staffing throughout the transition, including the following measures:
- The Exelon Senior Vice President, Operations for the Northeast Region met directly with Entergy Operations personnel to understand the potential staffing needs, including changes caused by retirements and transfers, on each Operations Crew.
- An Operations staffing plan was developed that identified the need for a new license class to support continued safe operations. Entergy began a new license class at FitzPatrick in October 2016 and another license class is scheduled to start in July 2017, after the anticipated closing.
Also, Entergy is starting an Equipment Operator class in November 2016.
- In anticipation of a potential need for additional Operators, Exelon Generation reached out to former Entergy FitzPatrick employees who now work in Operations at Exelon Generation's Nine
Attachment Response to Request for Additional Information Regarding Application for TransferofRenewed Facility Operating License and Proposed Conforming License Amendment Page 2of3 Mile Point Station to assess the interest of those employees in returning to Operations positions at FitzPatrick, if the need arises. Those discussions are ongoing.
- Exelon Generation instituted an Operations Observation team led by the Ginna Site Vice President to ensure continued focus on Operator Fundamentals throughout the transition.
- Although Security was not identified as a potential area for attention, Exelon Generation maintains a relationship with G4S Secure Solutions in New Yark to support its Ginna facility and could extend that relationship to cover FitzPatrick if concerns arose related to Security staffing.
- Exelon Generation will extend individual job offers to personnel across FitzPatrick Station in early January 201 7, in advance of the refueling outage. Candidates will have five days to respond in writing to the offer, with exceptions made for employees scheduled to take the week for vacation. Exelon Generation will then be able to assess any additional staffing needs that may be required post-closing.
- As a bridge between the refueling outage and closing of the transaction, Entergy has offered its employees at FitzPatrick a retention package to encourage them to stay through the closing.
Communicating Openly to Ensure Transparency and Build Trust Exelon Generation and Entergy maintain an open dialogue with FitzPatrick employees to ensure transparency, answer questions, build trust, and familiarize the FitzPatrick employees with Exelon Generation so they know what to expect if they are offered and accept employment with Exelon Generation. The below examples show how we are facilitating open dialogue:
- Employees at FitzPatrick receive two communications from Exelon Generation each month, in the form of an All Hands Meeting presentation and a newsletter.
- Employees have a direct line of communication to Exelon Generation, via a standard e-mail address that is designated and monitored for employee questions.
- Common questions are routinely answered in Q&A documents distributed by Entergy and Exelon Human Resources, in All Hands Meetings and in the newsletter.
- Benefits Open Houses have been conducted by Exelon to ensure that employees have a strong understanding of the differences between the benefits programs offered by Entergy and Exelon Generation. This ensures that employees understand the benefits they would receive if they accepted employment with Exelon Generation in positions that are not covered by a collective bargaining agreement.
- Separate benefits meetings will be scheduled for unionized Entergy employees at FitzPatrick, after a contract between the union and Exelon Generation has been signed.
- Nine Mile Point and Ginna Station employees are in contact with Entergy FitzPatrick employees to share best practices, answer procedural questions, and provide insight into what it is like to be an Exelon Generation employee.
- Multiple networking events between Exelon Generation's stations and Entergy's FitzPatrick Station have occurred and will continue to occur to further assist with open dialogue.
Attachment Response to Request for Additional Information Regarding Application for Transfer of Renewed Facility Operating License and Proposed Conforming License Amendment Page 3of3 Ensuring Industry Best Practice and High Standards Exelon Generation and Entergy have a corporate oversight team in place to ensure continued compliance with high standards during the transition.
- A joint Entergy and Exelon Generation Integration Team ensures that the actions required to complete the transfer are in place and that a smooth transition of ownership occurs.
- Entergy is committed to the success of the plant and continues to work cooperatively with Exelon Generation to ensure appropriate staffing and a smooth transition of ownership at the time of closing.
- The Exelon Generation Integration Team is led by an Exelon Generation executive and reports to a six-person Steering Committee, which includes the Chief Nuclear Officer and the Chief Operating Officer. Site staffing is a regular topic reviewed at Steering Committee meetings.
- The status of integration efforts, including site staffing, is also monitored in other oversight forums (e.g., Generation Staff Meeting, Quarterly Management Meeting).
- Exelon Generation has a presence onsite at FitzPatrick, including through a Ginna employee who was instrumental in the Exelon/Constellation integration, and twice weekly visits from the Ginna Site Vice President.
The parties continue to engage in additional efforts and develop their integration and staffing support activities as the transition proceeds forward.