ML12248A117: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 4, 2012 Mr. Thomas D. Gatlin Vice President - Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station P.O. Box 88 Jenkinsville, SC 29065 | ||
==SUBJECT:== | ==SUBJECT:== | ||
MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 - | MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 - | ||
NRC ASSESSMENT REPORT 05000395/2012006 | NRC ASSESSMENT REPORT 05000395/2012006 | ||
==Dear Mr. Gatlin:== | ==Dear Mr. Gatlin:== | ||
On August 16, 2011, the NRC completed its mid-cycle performance review of VC Summer Nuclear Station Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the | On August 16, 2011, the NRC completed its mid-cycle performance review of VC Summer Nuclear Station Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This assessment reflects the integration of the Security Cornerstone into the ROP performance assessment program governed by IMC 0305, Operating Reactor Assessment Program. | ||
The NRC determined the performance at VC Summer Nuclear Station Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. | |||
governed by IMC 0305, | |||
The NRC determined the performance at VC Summer Nuclear Station Unit 1 during the most recent quarter was within the Licensee Response Column of the | |||
facility. | |||
The enclosed inspection plan lists the inspections scheduled through December 31, 2013. | The enclosed inspection plan lists the inspections scheduled through December 31, 2013. | ||
Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, we will conduct an Operating License Initial Exam, Temporary Instruction (TI) 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks, and consistent with the | Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, we will conduct an Operating License Initial Exam, Temporary Instruction (TI) 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks, and consistent with the Agencys actions related to Fukushima, TI-2515/187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns and TI-2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. | ||
The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. | |||
T. Gatlin 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Please contact me at 404-997-4551 with any questions you may have regarding this letter. | Please contact me at 404-997-4551 with any questions you may have regarding this letter. | ||
Sincerely, | Sincerely, | ||
/RA/ | |||
Gerald J. McCoy, Chief Reactor Projects Branch 5 | Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No.: 50-395 License No.: NPF-12 | ||
Division of Reactor Projects Docket No.: | |||
==Enclosure:== | ==Enclosure:== | ||
V.C. Summer Inspection / Activity Plan (09/01/2012 - 12/31/2013) cc w/Encl: | V.C. Summer Inspection / Activity Plan (09/01/2012 - 12/31/2013) cc w/Encl: (See page 3) | ||
Bruce L. Thompson Manager Nuclear Licensing (Mail Code 830) | _________________________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE SON /RA/ GJM /RA/ | ||
South Carolina Electric & Gas Company Electronic Mail Distribution | NAME SNinh GMcCoy DATE 08/23/2012 08/28/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO T. Gatlin 3 cc w/encl: Bruce L. Thompson J. B. Archie Manager Senior Vice President Nuclear Licensing (Mail Code 830) | ||
Nuclear Operations and Chief Nuclear South Carolina Electric & Gas Company Officer Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Donna W. Railey Licensing Technician George A. Lippard, III Nuclear Licensing General Manager South Carolina Electric & Gas Company Nuclear Plant Operations Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Robin J. White Nuclear Coordinator Andy T. Barbee S.C. Public Service Authority Mail Code 802 Director Electronic Mail Distribution Nuclear Training South Carolina Electric & Gas Company Susan E. Jenkins Electronic Mail Distribution SC Department of Health & Environmental Control Wayne D. Stuart Bureau of Land and Waste Management (Acting) General Manager Electronic Mail Distribution Engineering Services South Carolina Electric & Gas Company Sandra Threatt, Manager Electronic Mail Distribution Nuclear Response and Emergency Environmental Surveillance Robin R. Haselden Bureau of Land and Waste Management General Manager Department of Health and Environmental Organizational Development & Control Effectiveness Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Division of Radiological Health TN Dept. of Environment & Conservation Shaun M. Zarandi 401 Church Street General Manager Nashville, TN 37243-1532 Nuclear Support Services South Carolina Electric & Gas Company Electronic Mail Distribution Robert L. Justice Manager Nuclear Operations South Carolina Electric & Gas Company Electronic Mail Distribution Kathryn M. Sutton, Esq. | |||
Morgan, Lewis & Bockius LLP Electronic Mail Distribution | |||
T. Gatlin 4 Letter to Thomas D. Gatlin from Gerald J. McCoy dated September 4, 2012 | |||
T. Gatlin 4 | |||
Letter to Thomas D. Gatlin from Gerald J. McCoy dated September 4, 2012 | |||
==SUBJECT:== | ==SUBJECT:== | ||
MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 - | MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 - | ||
NRC ASSESSMENT REPORT 05000395/2012006 | NRC ASSESSMENT REPORT 05000395/2012006 Distribution w/encl: | ||
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMSummer Resource INPO ROP Reports | |||
Distribution w/encl | |||
Page 1 of 2 Summer 09/04/2012 08:22:14 Inspection / Activity Plan Report 22 09/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1EP - EMERGENCY PREPAREDNESS INSPECTION 2 1 09/17/2012 09/21/2012 IP 7111402 Alert and Notification System Testing 1 09/17/2012 09/21/2012 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 09/17/2012 09/21/2012 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 09/17/2012 09/21/2012 IP 71151 Performance Indicator Verification PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 9 1 09/10/2012 09/14/2012 IP 71152B Problem Identification and Resolution 1 09/24/2012 09/28/2012 IP 71152B Problem Identification and Resolution PSB1-RP - RADIOLOGICAL HAZARD ASSESSMENT 2 1 10/15/2012 10/19/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls TI-188 - TI-188 P2 - NTTF 2.3 - SEISMIC WALKDOWNS 1 1 10/17/2012 10/19/2012 IP 2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns EB3 ISI - SUM ISI AND RPVH EXAMS 2 1 10/22/2012 10/26/2012 IP 7111108P Inservice Inspection Activities - PWR TI-182 - TI-182 BURIED PIPING/TANK - PHASE 1 1 1 03/11/2013 03/15/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping MODS - PERM MODS 50.59 INSPECTION 3 1 04/01/2013 04/05/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 1 04/15/2013 04/19/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications HS - TRIENNIAL HEAT SINK PERFORMANCE 1 1 06/17/2013 06/21/2013 IP 7111107T Heat Sink Performance EP - EMERGENCY PREPAREDNESS EXERCISE 1 1 07/22/2013 07/26/2013 IP 7111401 Exercise Evaluation 1 07/22/2013 07/26/2013 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM PREP 3 1 07/29/2013 08/02/2013 V23400 SUMMER U1/AUGUST 2013 INITIAL EXAM AT POWER FACILITIES OL RQ - REQUAL INSPECTION 2 1 08/05/2013 08/09/2013 IP 7111111B Licensed Operator Requalification Program OL EXAM - INITIAL EXAM WEEK 1 3 1 08/19/2013 08/23/2013 V23400 SUMMER U1/AUGUST 2013 INITIAL EXAM AT POWER FACILITIES PSB1-RP - RP OCCUPATIONAL BASELINE 5 1 08/19/2013 08/23/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 08/19/2013 08/23/2013 IP 71124.02 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures. | |||
Page 2 of 2 Summer 09/04/2012 08:22:14 Inspection / Activity Plan Report 22 09/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1-RP - RP OCCUPATIONAL BASELINE 5 1 08/19/2013 08/23/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 08/19/2013 08/23/2013 IP 71124.04 Occupational Dose Assessment 1 08/19/2013 08/23/2013 IP 71124.05 Radiation Monitoring Instrumentation 1 08/19/2013 08/23/2013 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM WEEK 2 3 1 08/26/2013 08/30/2013 V23400 SUMMER U1/AUGUST 2013 INITIAL EXAM AT POWER FACILITIES PSB1-RP - RP OCCUPATIONAL BASELINE WEEK2 3 1 09/09/2013 09/13/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 09/09/2013 09/13/2013 IP 71124.02 Occupational ALARA Planning and Controls 1 09/09/2013 09/13/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 09/09/2013 09/13/2013 IP 71124.04 Occupational Dose Assessment 1 09/09/2013 09/13/2013 IP 71124.05 Radiation Monitoring Instrumentation 1 09/09/2013 09/13/2013 IP 71151 Performance Indicator Verification Comments: | |||
This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.}} | |||
-12/31/2013 Unit | |||
This report shows only on-site and announced inspection procedures.}} |
Latest revision as of 12:23, 6 February 2020
ML12248A117 | |
Person / Time | |
---|---|
Site: | Summer |
Issue date: | 09/04/2012 |
From: | Gerald Mccoy NRC/RGN-II/DRP/RPB5 |
To: | Gatlin T South Carolina Electric & Gas Co |
References | |
IR-12-006 | |
Download: ML12248A117 (7) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 4, 2012 Mr. Thomas D. Gatlin Vice President - Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station P.O. Box 88 Jenkinsville, SC 29065
SUBJECT:
MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 -
NRC ASSESSMENT REPORT 05000395/2012006
Dear Mr. Gatlin:
On August 16, 2011, the NRC completed its mid-cycle performance review of VC Summer Nuclear Station Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This assessment reflects the integration of the Security Cornerstone into the ROP performance assessment program governed by IMC 0305, Operating Reactor Assessment Program.
The NRC determined the performance at VC Summer Nuclear Station Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2013.
Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, we will conduct an Operating License Initial Exam, Temporary Instruction (TI) 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks, and consistent with the Agencys actions related to Fukushima, TI-2515/187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns and TI-2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
T. Gatlin 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4551 with any questions you may have regarding this letter.
Sincerely,
/RA/
Gerald J. McCoy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No.: 50-395 License No.: NPF-12
Enclosure:
V.C. Summer Inspection / Activity Plan (09/01/2012 - 12/31/2013) cc w/Encl: (See page 3)
_________________________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE SON /RA/ GJM /RA/
NAME SNinh GMcCoy DATE 08/23/2012 08/28/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO T. Gatlin 3 cc w/encl: Bruce L. Thompson J. B. Archie Manager Senior Vice President Nuclear Licensing (Mail Code 830)
Nuclear Operations and Chief Nuclear South Carolina Electric & Gas Company Officer Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Donna W. Railey Licensing Technician George A. Lippard, III Nuclear Licensing General Manager South Carolina Electric & Gas Company Nuclear Plant Operations Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Robin J. White Nuclear Coordinator Andy T. Barbee S.C. Public Service Authority Mail Code 802 Director Electronic Mail Distribution Nuclear Training South Carolina Electric & Gas Company Susan E. Jenkins Electronic Mail Distribution SC Department of Health & Environmental Control Wayne D. Stuart Bureau of Land and Waste Management (Acting) General Manager Electronic Mail Distribution Engineering Services South Carolina Electric & Gas Company Sandra Threatt, Manager Electronic Mail Distribution Nuclear Response and Emergency Environmental Surveillance Robin R. Haselden Bureau of Land and Waste Management General Manager Department of Health and Environmental Organizational Development & Control Effectiveness Electronic Mail Distribution South Carolina Electric & Gas Company Electronic Mail Distribution Division of Radiological Health TN Dept. of Environment & Conservation Shaun M. Zarandi 401 Church Street General Manager Nashville, TN 37243-1532 Nuclear Support Services South Carolina Electric & Gas Company Electronic Mail Distribution Robert L. Justice Manager Nuclear Operations South Carolina Electric & Gas Company Electronic Mail Distribution Kathryn M. Sutton, Esq.
Morgan, Lewis & Bockius LLP Electronic Mail Distribution
T. Gatlin 4 Letter to Thomas D. Gatlin from Gerald J. McCoy dated September 4, 2012
SUBJECT:
MID-CYCLE LETTER FOR VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 -
NRC ASSESSMENT REPORT 05000395/2012006 Distribution w/encl:
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMSummer Resource INPO ROP Reports
Page 1 of 2 Summer 09/04/2012 08:22:14 Inspection / Activity Plan Report 22 09/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1EP - EMERGENCY PREPAREDNESS INSPECTION 2 1 09/17/2012 09/21/2012 IP 7111402 Alert and Notification System Testing 1 09/17/2012 09/21/2012 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 09/17/2012 09/21/2012 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1 09/17/2012 09/21/2012 IP 71151 Performance Indicator Verification PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 9 1 09/10/2012 09/14/2012 IP 71152B Problem Identification and Resolution 1 09/24/2012 09/28/2012 IP 71152B Problem Identification and Resolution PSB1-RP - RADIOLOGICAL HAZARD ASSESSMENT 2 1 10/15/2012 10/19/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls TI-188 - TI-188 P2 - NTTF 2.3 - SEISMIC WALKDOWNS 1 1 10/17/2012 10/19/2012 IP 2515/188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns EB3 ISI - SUM ISI AND RPVH EXAMS 2 1 10/22/2012 10/26/2012 IP 7111108P Inservice Inspection Activities - PWR TI-182 - TI-182 BURIED PIPING/TANK - PHASE 1 1 1 03/11/2013 03/15/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping MODS - PERM MODS 50.59 INSPECTION 3 1 04/01/2013 04/05/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 1 04/15/2013 04/19/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications HS - TRIENNIAL HEAT SINK PERFORMANCE 1 1 06/17/2013 06/21/2013 IP 7111107T Heat Sink Performance EP - EMERGENCY PREPAREDNESS EXERCISE 1 1 07/22/2013 07/26/2013 IP 7111401 Exercise Evaluation 1 07/22/2013 07/26/2013 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM PREP 3 1 07/29/2013 08/02/2013 V23400 SUMMER U1/AUGUST 2013 INITIAL EXAM AT POWER FACILITIES OL RQ - REQUAL INSPECTION 2 1 08/05/2013 08/09/2013 IP 7111111B Licensed Operator Requalification Program OL EXAM - INITIAL EXAM WEEK 1 3 1 08/19/2013 08/23/2013 V23400 SUMMER U1/AUGUST 2013 INITIAL EXAM AT POWER FACILITIES PSB1-RP - RP OCCUPATIONAL BASELINE 5 1 08/19/2013 08/23/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 08/19/2013 08/23/2013 IP 71124.02 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.
Page 2 of 2 Summer 09/04/2012 08:22:14 Inspection / Activity Plan Report 22 09/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1-RP - RP OCCUPATIONAL BASELINE 5 1 08/19/2013 08/23/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 08/19/2013 08/23/2013 IP 71124.04 Occupational Dose Assessment 1 08/19/2013 08/23/2013 IP 71124.05 Radiation Monitoring Instrumentation 1 08/19/2013 08/23/2013 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM WEEK 2 3 1 08/26/2013 08/30/2013 V23400 SUMMER U1/AUGUST 2013 INITIAL EXAM AT POWER FACILITIES PSB1-RP - RP OCCUPATIONAL BASELINE WEEK2 3 1 09/09/2013 09/13/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 09/09/2013 09/13/2013 IP 71124.02 Occupational ALARA Planning and Controls 1 09/09/2013 09/13/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 09/09/2013 09/13/2013 IP 71124.04 Occupational Dose Assessment 1 09/09/2013 09/13/2013 IP 71124.05 Radiation Monitoring Instrumentation 1 09/09/2013 09/13/2013 IP 71151 Performance Indicator Verification Comments:
This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.