ML13079A150: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML13079A150
| number = ML13079A150
| issue date = 03/20/2013
| issue date = 03/20/2013
| title = 03/11/2013 Summary of Public Meeting with Joseph M. Farley
| title = Summary of Public Meeting with Joseph M. Farley
| author name = Ehrhardt F
| author name = Ehrhardt F
| author affiliation = NRC/RGN-II/DRP/RPB2
| author affiliation = NRC/RGN-II/DRP/RPB2
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 20, 2013 Mr. T. A. Lynch Vice President  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 20, 2013 Mr. T. A. Lynch Vice President Southern Nuclear Operating Company, Inc.
 
Joseph M. Farley Nuclear Plant P.O. Drawer 470, BIN B500 Ashford, AL 36312
Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant P.O. Drawer 470, BIN B500  
 
Ashford, AL 36312  


==SUBJECT:==
==SUBJECT:==
Line 26: Line 22:


==SUMMARY==
==SUMMARY==
  - JOSEPH M. FARLEY NUCLEAR PLANT DOCKET NOS. 50-348 AND 50-364  
  - JOSEPH M. FARLEY NUCLEAR PLANT DOCKET NOS. 50-348 AND 50-364


==Dear Mr. Lynch:==
==Dear Mr. Lynch:==


This refers to the meeting conducted on March 11, 2013, in Ashford, Alabama. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Joseph M. Farley Nuclear Plant with the public for the period of January 1, 2012, - December 31, 2012. Enclosed are a list of attendees, copies of the poster boards displayed at the meeting, and the meeting handout.
This refers to the meeting conducted on March 11, 2013, in Ashford, Alabama. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Joseph M. Farley Nuclear Plant with the public for the period of January 1, 2012, - December 31, 2012. Enclosed are a list of attendees, copies of the poster boards displayed at the meeting, and the meeting handout.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).
 
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
available electronically for public in spection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
 
Should you have any questions concerning this meeting, please contact me at (404) 997-4611.
Should you have any questions concerning this meeting, please contact me at (404) 997-4611.
Sincerely,
Sincerely,
/RA/  
                                                /RA/
 
Frank Ehrhardt, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-348 and 50-364 License Nos.: NPF-2 and NPF-8
Frank Ehrhardt, Chief       Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-348 and 50-364 License Nos.: NPF-2 and NPF-8  


==Enclosures:==
==Enclosures:==
: 1. List of Attendees
: 1. List of Attendees
: 2. Poster Boards
: 2. Poster Boards
: 3. Meeting Handout
: 3. Meeting Handout cc w/encls: (See page 2)


cc w/encls: (See page 2)  
_________________________        X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE            RII:DRP          RII:DRP SIGNATURE        Via email        FJE /RA/
NAME              TLighty          FEhrhardt DATE                03/20/2013      03/19/2013 E-MAIL COPY?        YES    NO      YES      NO    YES    NO      YES  NO      YES    NO    YES    NO    YES    NO T. Lynch                                2 cc w/encls:                               B. D. McKinney, Jr.
C. Russ Dedrickson                        Regulatory Response Manager Fleet Support Supervisor                  Southern Nuclear Operating Company, Inc.
Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution D. W. Daughhetee Cheryl A. Gayheart                        Licensing Engineer Plant Manager                              Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant            Electronic Mail Distribution Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              T. D. Honeycutt Regulatory Response Supervisor S. Kuczynski                              Southern Nuclear Operating Company, Inc.
Chairman, President and CEO                Electronic Mail Distribution Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              Bradley J. Adams Vice President Leigh Perry                                Fleet Operations Support SVP & General Counsel-Ops & SNC            Southern Nuclear Operating Company, Inc.
Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution N. J. Stringfellow D. G. Bost                                Licensing Manager Chief Nuclear Officer                      Southern Nuclear Operating Company, Inc.
Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution L. P. Hill Dennis R. Madison                          Licensing Supervisor Vice President                            Southern Nuclear Operating Company, Inc.
Edwin I. Hatch Nuclear Plant              Electronic Mail Distribution Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              L. L. Crumpton Administrative Assistant, Sr.
Paula Marino                              Southern Nuclear Operating Company, Inc.
Vice President                            Electronic Mail Distribution Engineering Southern Nuclear Operating Company, Inc. William D. Oldfield Electronic Mail Distribution              Principal Licensing Engineer Joseph M. Farley Nuclear Plant T. E. Tynan                                Electronic Mail Distribution Site Vice President Vogtle Electric Generating Plant          Todd L. Youngblood Southern Nuclear Operating Company, Inc. Vice President Electronic Mail Distribution              Fleet Oversight Southern Nuclear Operating Company, Inc.
Mark Williams                              Electronic Mail Distribution Commissioner Georgia Department of Natural Resources    (cc w/encls continued next page)
Electronic Mail Distribution


_________________________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRP      SIGNATURE Via email FJE /RA/      NAME TLighty FEhrhardt      DATE 03/20/2013 03/19/2013      E-MAIL COPY?    YES NO      YES NO      YES NO      YES NO      YES NO      YES NO      YES NO T. Lynch 2 cc w/encls: C. Russ Dedrickson Fleet Support Supervisor
T. Lynch                                 3 (cc w/encls continued)
John G. Horn Site Support Manager Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Mark Culver Chairman Houston County Commission P. O. Box 6406 Dothan, AL 36302 James L. McNees, CHP Director Office of Radiation Control Alabama Dept. of Public Health P. O. Box 303017 Montgomery, AL 36130-3017 State Health Officer Alabama Dept. of Public Health P.O. Box 303017 Montgomery, AL 36130-3017 Chuck Mueller Manager Policy and Radiation Program Georgia Department of Natural Resources Electronic Mail Distribution


Southern Nuclear Operating Company, Inc.
T. Lynch                                4 Letter to Thomas A. Lynch from Frank Ehrhardt dated March 20, 2013
Electronic Mail Distribution


Cheryl A. Gayheart Plant Manager Joseph M. Farley Nuclear Plant
==SUBJECT:==
PUBLIC MEETING


Southern Nuclear Operating Company, Inc.
==SUMMARY==
Electronic Mail Distribution
- JOSEPH M. FARLEY NUCLEAR PLANT -
 
DOCKET NOS. 50-348 AND 50-364 Distribution w/encls:
S. Kuczynski Chairman, President and CEO
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMFarley Resource NRC Annual Assessment Summary JOSEPH M. FARLEY NUCLEAR PLANT Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.
 
Joseph M. Farley Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.
Southern Nuclear Operating Company, Inc.
Enclosure 2
Electronic Mail Distribution
 
Leigh Perry SVP & General Counsel-Ops & SNC
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
D. G. Bost Chief Nuclear Officer Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution  
 
Dennis R. Madison Vice President Edwin I. Hatch Nuclear Plant
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
Paula Marino Vice President Engineering
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
T. E. Tynan Site Vice President Vogtle Electric Generating Plant
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
Mark Williams Commissioner
 
Georgia Department of Natural Resources Electronic Mail Distribution B. D. McKinney, Jr. Regulatory Response Manager Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
D. W. Daughhetee Licensing Engineer Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
 
T. D. Honeycutt
 
Regulatory Response Supervisor Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
 
Bradley J. Adams Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution


N. J. Stringfellow Licensing Manager Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
2 NRC Inspection Activities JOSEPH M. FARLEY NUCLEAR PLANT for 2012 2 Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports 3 Major Team Inspections Emergency Preparedness Exercise 95001 Supplemental Inspection Initial License Examination Enclosure 2


L. P. Hill Licensing Supervisor Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
3 NRC Plans for 2013 NRC plans baseline inspections at Joseph M. Farley Nuclear Plant for the remainder of 2013 Additional Major Inspections Include:
Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Enclosure 2


L. L. Crumpton Administrative Assistant, Sr.
4 Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection                    Performance Indicator Results                                Results Significance                    Significance Significance Threshold                      Threshold Threshold Action Matrix Regulatory Response Enclosure 2


Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
5 Reactor Oversight Process Regulatory Framework PUBLIC HEALTH AND NRCs Overall                                            SAFETY AS A RESULT OF CIVILIAN Safety Mission                                    NUCLEAR REACTOR OPERATION Strategic Performance                      REACTOR            RADIATION                  PLANT SAFETY              SAFETY              SECURITY Areas INITIATING MITIGATING  BARRIER    EMERGENCY    PUBLIC    OCCUPATIONAL    PHYSICAL Cornerstones  EVENTS    SYSTEMS  INTEGRITY  PREPAREDNESS RADIATION    RADIATION    PROTECTION SAFETY        SAFETY Human Performance          Safety Conscious Work          Problem Identification Environment                  and Resolution Cross-Cutting Areas                                    Enclosure 2


William D. Oldfield Principal Licensing Engineer
Joseph M. Farley Nuclear Plant Annual Assessment Meeting 2012 Reactor Oversight Process Nuclear Regulatory Commission - Region II Enclosure 3


Joseph M. Farley Nuclear Plant Electronic Mail Distribution
2 Enclosure 3


Todd L. Youngblood Vice President
3 Significance Threshold Performance Indicators Green    Baseline Inspection White    Requires additional NRC oversight Yellow  Requires more NRC oversight Red      Requires most NRC oversight Inspection Findings Green    Very low safety issue White    Low to moderate safety issue Yellow  Substantial safety issue Red      High safety issue Enclosure 3


Fleet Oversight
4 NRC Annual Assessment Summary JOSEPH M. FARLEY NUCLEAR PLANT Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.
Joseph M. Farley Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.
Enclosure 3


Southern Nuclear Operating Company, Inc. Electronic Mail Distribution
5 NRC Inspection Activities JOSEPH M. FARLEY NUCLEAR PLANT for 2012 2 Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports 3 Major Team Inspections Emergency Preparedness Exercise 95001 Supplemental Inspection Initial License Examination Enclosure 3


(cc w/encls continued next page)
6 Joseph M. Farley Nuclear Plant PIs and Findings January 1 through December 31, 2012 All Green Performance Indicators 9 Green / Severity Level IV inspection findings Enclosure 3


T. Lynch  3 (cc w/encls continued)
7 NRC Inspection Findings Joseph M. Farley Nuclear Plant Loss of shutdown cooling due to loss of Train A 4160v safety related switchgear Failure to perform ISI general visual examinations of containment moisture barrier Inadvertent transfer of approximately 5000 gallons of borated water from the RWST to the RCS refueling cavity and spent fuel pool Enclosure 3
John G. Horn


Site Support Manager
8 NRC Plans for 2013 NRC plans baseline inspections at Joseph M. Farley Nuclear Plant for the remainder of 2013 Additional Major Inspections Include:
Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Enclosure 3


Joseph M. Farley Nuclear Plant
9 Enclosure 3
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division
 
Georgia Department of Natural Resources Electronic Mail Distribution
 
James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution
 
Mr. Mark Culver Chairman Houston County Commission P. O. Box 6406 Dothan, AL  36302
 
James L. McNees, CHP
 
Director Office of Radiation Control Alabama Dept. of Public Health P. O. Box 303017
 
Montgomery, AL  36130-3017
 
State Health Officer Alabama Dept. of Public Health P.O. Box 303017
 
Montgomery, AL  36130-3017
 
Chuck Mueller Manager Policy and Radiation Program
 
Georgia Department of Natural Resources Electronic Mail Distribution
 
T. Lynch  4 Letter to Thomas A. Lynch from Frank Ehrhardt dated March 20, 2013
 
==SUBJECT:==
PUBLIC MEETING
 
==SUMMARY==
- JOSEPH M. FARLEY NUCLEAR PLANT - DOCKET NOS. 50-348 AND 50-364 Distribution w/encls
: C. Evans, RII L. Douglas, RII  OE Mail  RIDSNRRDIRS PUBLIC RidsNrrPMFarley Resource


Enclosure 1
10 Enclosure 3


Enclosure 2 NRC Annual Assessment SummarySouthern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.Joseph M. Farley Nuclear Plant was in the Licensee Response Column of the NRC's ROP Action Matrix for the last quarter of 2012.JOSEPH M. FARLEY NUCLEAR PLANT 2  Enclosure 2 NRC Inspection Activities2 Resident Inspectors on SiteImplemented baseline inspection programInspected in-plant evolutions and activitiesCompiled and submitted quarterly inspection reports3 Major Team InspectionsEmergency Preparedness Exercise95001 Supplemental InspectionInitial License ExaminationJOSEPH M. FARLEY NUCLEAR PLANTfor 2012 3  Enclosure 2 NRC Plans for 2013NRC plans baseline inspections at Joseph M. Farley Nuclear Plant for the remainder of 2013 Additional Major Inspections Include:Problem Identification and ResolutionInitial License ExaminationPlant Modifications Inspection 4  Enclosure 2 Reactor Oversight ProcessSafetyCornerstonesBaseline Inspection ResultsSignificance ThresholdAction MatrixSignificance ThresholdPerformance IndicatorResultsStrategicPerformance AreasSafetyCornerstonesBaseline Inspection ResultsSignificance ThresholdAction MatrixSignificance ThresholdPerformance IndicatorResultsRegulatory ResponseStrategicPerformance Areas 5  Enclosure 2 Reactor Oversight Process Regulatory FrameworkNRC's OverallSafety MissionPUBLIC HEALTH AND SAFETY AS A RESULT OF CIVILIAN NUCLEAR REACTOR OPERATIONREACTOR SAFETY Strategic Performance AreasRADIATION SAFETYPLANT SECURITYCornerstonesINITIATING EVENTSMITIGATING SYSTEMSBARRIER INTEGRITYEMERGENCY PREPAREDNESSPUBLIC RADIATION SAFETYOCCUPATIONAL RADIATION SAFETYPHYSICAL PROTECTIONHuman PerformanceSafety Conscious Work EnvironmentProblem Identification and ResolutionCross-Cutting Areas Enclosure 3 Joseph M. Farley Nuclear Plant Annual Assessment Meeting2012 Reactor Oversight ProcessNuclear Regulatory Commission -Region II 2  Enclosure 3 3  Enclosure 3 Significance ThresholdGreenBaseline InspectionWhiteRequires additional NRC oversightYellowRequires more NRC oversightRedRequires most NRC oversightPerformance Indicators Inspection FindingsGreenVery low safety issueWhiteLow to moderate safety issueYellowSubstantial safety issueRedHigh safety issue 4  Enclosure 3 NRC Annual Assessment SummarySouthern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.Joseph M. Farley Nuclear Plant was in the Licensee Response Column of the NRC's ROP Action Matrix for the last quarter of 2012.JOSEPH M. FARLEY NUCLEAR PLANT 5  Enclosure 3 NRC Inspection Activities2 Resident Inspectors on SiteImplemented baseline inspection programInspected in-plant evolutions and activitiesCompiled and submitted quarterly inspection reports3 Major Team InspectionsEmergency Preparedness Exercise95001 Supplemental InspectionInitial License ExaminationJOSEPH M. FARLEY NUCLEAR PLANTfor 2012 6  Enclosure 3 Joseph M. Farley Nuclear Plant PIs and FindingsAll Green Performance Indicators9 Green / Severity Level IV inspection findingsJanuary 1 through December 31, 2012 7  Enclosure 3 NRC Inspection FindingsLoss of shutdown cooling due to loss of Train A 4160v safety related switchgearFailure to perform ISI general visual examinations of containment moisture barrierInadvertent transfer of approximately 5000 gallons of borated water from the RWST to the RCS refueling cavity and spent fuel poolJoseph M. Farley Nuclear Plant 8  Enclosure 3 NRC Plans for 2013NRC plans baseline inspections at Joseph M. Farley Nuclear Plant for the remainder of 2013Additional Major Inspections Include:Problem Identification and ResolutionInitial License ExaminationPlant Modifications Inspection 9  Enclosure 3 10  Enclosure 3 11 Enclosure 3 Nuclear Regulatory CommissionRegion IIAtlanta, GeorgiaMarch 11, 2013}}
11 Nuclear Regulatory Commission Region II Atlanta, Georgia March 11, 2013 Enclosure 3}}

Latest revision as of 06:17, 6 February 2020

Summary of Public Meeting with Joseph M. Farley
ML13079A150
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 03/20/2013
From: Frank Ehrhardt
NRC/RGN-II/DRP/RPB2
To: Lynch T
Southern Nuclear Operating Co
References
Download: ML13079A150 (22)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 20, 2013 Mr. T. A. Lynch Vice President Southern Nuclear Operating Company, Inc.

Joseph M. Farley Nuclear Plant P.O. Drawer 470, BIN B500 Ashford, AL 36312

SUBJECT:

PUBLIC MEETING

SUMMARY

- JOSEPH M. FARLEY NUCLEAR PLANT DOCKET NOS. 50-348 AND 50-364

Dear Mr. Lynch:

This refers to the meeting conducted on March 11, 2013, in Ashford, Alabama. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Joseph M. Farley Nuclear Plant with the public for the period of January 1, 2012, - December 31, 2012. Enclosed are a list of attendees, copies of the poster boards displayed at the meeting, and the meeting handout.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 997-4611.

Sincerely,

/RA/

Frank Ehrhardt, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-348 and 50-364 License Nos.: NPF-2 and NPF-8

Enclosures:

1. List of Attendees
2. Poster Boards
3. Meeting Handout cc w/encls: (See page 2)

_________________________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE Via email FJE /RA/

NAME TLighty FEhrhardt DATE 03/20/2013 03/19/2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO T. Lynch 2 cc w/encls: B. D. McKinney, Jr.

C. Russ Dedrickson Regulatory Response Manager Fleet Support Supervisor Southern Nuclear Operating Company, Inc.

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution D. W. Daughhetee Cheryl A. Gayheart Licensing Engineer Plant Manager Southern Nuclear Operating Company, Inc.

Joseph M. Farley Nuclear Plant Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor S. Kuczynski Southern Nuclear Operating Company, Inc.

Chairman, President and CEO Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Bradley J. Adams Vice President Leigh Perry Fleet Operations Support SVP & General Counsel-Ops & SNC Southern Nuclear Operating Company, Inc.

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution N. J. Stringfellow D. G. Bost Licensing Manager Chief Nuclear Officer Southern Nuclear Operating Company, Inc.

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution L. P. Hill Dennis R. Madison Licensing Supervisor Vice President Southern Nuclear Operating Company, Inc.

Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution L. L. Crumpton Administrative Assistant, Sr.

Paula Marino Southern Nuclear Operating Company, Inc.

Vice President Electronic Mail Distribution Engineering Southern Nuclear Operating Company, Inc. William D. Oldfield Electronic Mail Distribution Principal Licensing Engineer Joseph M. Farley Nuclear Plant T. E. Tynan Electronic Mail Distribution Site Vice President Vogtle Electric Generating Plant Todd L. Youngblood Southern Nuclear Operating Company, Inc. Vice President Electronic Mail Distribution Fleet Oversight Southern Nuclear Operating Company, Inc.

Mark Williams Electronic Mail Distribution Commissioner Georgia Department of Natural Resources (cc w/encls continued next page)

Electronic Mail Distribution

T. Lynch 3 (cc w/encls continued)

John G. Horn Site Support Manager Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Mark Culver Chairman Houston County Commission P. O. Box 6406 Dothan, AL 36302 James L. McNees, CHP Director Office of Radiation Control Alabama Dept. of Public Health P. O. Box 303017 Montgomery, AL 36130-3017 State Health Officer Alabama Dept. of Public Health P.O. Box 303017 Montgomery, AL 36130-3017 Chuck Mueller Manager Policy and Radiation Program Georgia Department of Natural Resources Electronic Mail Distribution

T. Lynch 4 Letter to Thomas A. Lynch from Frank Ehrhardt dated March 20, 2013

SUBJECT:

PUBLIC MEETING

SUMMARY

- JOSEPH M. FARLEY NUCLEAR PLANT -

DOCKET NOS. 50-348 AND 50-364 Distribution w/encls:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMFarley Resource NRC Annual Assessment Summary JOSEPH M. FARLEY NUCLEAR PLANT Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.

Joseph M. Farley Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.

Enclosure 2

2 NRC Inspection Activities JOSEPH M. FARLEY NUCLEAR PLANT for 2012 2 Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports 3 Major Team Inspections Emergency Preparedness Exercise 95001 Supplemental Inspection Initial License Examination Enclosure 2

3 NRC Plans for 2013 NRC plans baseline inspections at Joseph M. Farley Nuclear Plant for the remainder of 2013 Additional Major Inspections Include:

Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Enclosure 2

4 Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Significance Threshold Threshold Threshold Action Matrix Regulatory Response Enclosure 2

5 Reactor Oversight Process Regulatory Framework PUBLIC HEALTH AND NRCs Overall SAFETY AS A RESULT OF CIVILIAN Safety Mission NUCLEAR REACTOR OPERATION Strategic Performance REACTOR RADIATION PLANT SAFETY SAFETY SECURITY Areas INITIATING MITIGATING BARRIER EMERGENCY PUBLIC OCCUPATIONAL PHYSICAL Cornerstones EVENTS SYSTEMS INTEGRITY PREPAREDNESS RADIATION RADIATION PROTECTION SAFETY SAFETY Human Performance Safety Conscious Work Problem Identification Environment and Resolution Cross-Cutting Areas Enclosure 2

Joseph M. Farley Nuclear Plant Annual Assessment Meeting 2012 Reactor Oversight Process Nuclear Regulatory Commission - Region II Enclosure 3

2 Enclosure 3

3 Significance Threshold Performance Indicators Green Baseline Inspection White Requires additional NRC oversight Yellow Requires more NRC oversight Red Requires most NRC oversight Inspection Findings Green Very low safety issue White Low to moderate safety issue Yellow Substantial safety issue Red High safety issue Enclosure 3

4 NRC Annual Assessment Summary JOSEPH M. FARLEY NUCLEAR PLANT Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.

Joseph M. Farley Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.

Enclosure 3

5 NRC Inspection Activities JOSEPH M. FARLEY NUCLEAR PLANT for 2012 2 Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports 3 Major Team Inspections Emergency Preparedness Exercise 95001 Supplemental Inspection Initial License Examination Enclosure 3

6 Joseph M. Farley Nuclear Plant PIs and Findings January 1 through December 31, 2012 All Green Performance Indicators 9 Green / Severity Level IV inspection findings Enclosure 3

7 NRC Inspection Findings Joseph M. Farley Nuclear Plant Loss of shutdown cooling due to loss of Train A 4160v safety related switchgear Failure to perform ISI general visual examinations of containment moisture barrier Inadvertent transfer of approximately 5000 gallons of borated water from the RWST to the RCS refueling cavity and spent fuel pool Enclosure 3

8 NRC Plans for 2013 NRC plans baseline inspections at Joseph M. Farley Nuclear Plant for the remainder of 2013 Additional Major Inspections Include:

Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Enclosure 3

9 Enclosure 3

10 Enclosure 3

11 Nuclear Regulatory Commission Region II Atlanta, Georgia March 11, 2013 Enclosure 3