ID TaskName Duration 1
PlantFarleyFloodHazardReevaluation 120days 2
USACEprovidesnecessaryinformationforBuford, WestPointandWFGeorgePMFandSeismic StabilityAnalysis 1day 3
EvaluationofPlantFarleyDamBreachesand FailuresSevereAccidentManagement(SAM)for FukushimaNearTermTaskForce(NTTF)
Recommendation2.1FloodingReevaluation SCSNC453276002 43days 4
FinalizeDamBreakAnalysis 7days 5
InternalTechnicalReview(ITR) 3days 6
VersionBDRAFTCalculationPackage 4days 7
ITRofVersionBDRAFTCalculationPackage 2days 8
AddressITRcommentsofVersionBDRAFT CalculationPackage 2days 9
SubmitVersionBDRAFTCalculationPackage 1day 10 SNCReview 7days 11 AddressVersionBSNCReviewComments 4days 12 Ver1.0CalculationPackage 1day 13 FarleyProbableMaximumFloodHydraulics SevereAccidentManagement(SAM)for FukushimaNearTermTaskForce(NTTF)
Recommendation2.1FloodingReevaluation SCSNC453276003 30days 14 RunHECRASModelwithGoverningDamBreak Scenario 1day 15 ITR 2days 16 VersionBDRAFTCalculationPackage 2days 17 ITRofVersionBDRAFTCalculationPackage 2days 18 AddressITRcommentsofVersionBDRAFT CalculationPackage 2days 19 SubmitVersionBDRAFTCalculationPackage 1day 20 SNCReview 7days 21 AddressVersionBSNCReviewComments 4days 22 Ver1.0CalculationPackage 1day Day8 Day1 Day9 Day17 Day25 Day33 Day41 Day49 Day57 Day65 Day73 Day81 Day89 Day97 Day105 Day113 Day121 Task Split Milestone Summary ProjectSummary ExternalTasks ExternalMilestone InactiveTask InactiveMilestone InactiveSummary ManualTask Durationonly ManualSummaryRollup ManualSummary Startonly Finishonly Deadline Progress DurationforCompletion SouthernNuclearPlantFarley FloodHazardReevalution February26,2014 Page1
ID TaskName Duration 23 PlantFarleyWindGeneratedWaveAnalysis SevereAccidentManagement(SAM)for FukushimaNearTermTaskForce(NTTF)
Recommendation2.1FloodingReevaluation 36days 24 UpdateWindGeneratedWaveAnalysis 3days 25 ITR 2days 26 VersionBDRAFTCalculationPackage 2days 27 ITRofVersionBDRAFTCalculationPackage 3days 28 AddressITRcommentsofVersionBDRAFT CalculationPackage 3days 29 SubmitVersionBDRAFTCalculationPackage 1day 30 SNCReview 7days 31 AddressVersionBSNCReviewComments 4days 32 Ver1.0CalculationPackage 1day 33 95%DraftCOMPLETEFloodHazardReevaluation Report 32days 34 Prepare95%COMPLETEReport 10days 35 ITR 3days 36 Finalize95%COMPLETEReport 3days 37 Submit95%DraftCOMPLETEReport 1day 38 SNCProvideComments 7days 39 99%COMPLETEReport 20days 40 Prepare99%COMPLETEReport 4days 41 ITR 2days 42 Finalize99%COMPLETEReport 2days 43 Submit99%COMPLETEReport 1day 44 SNCProvideComments 7days 45 100%COMPLETEReport 21days 46 IncorporateFinalLicensing/PlantManagement SNCComments 5days 47 SubmitRev.1COMPLETEFHRRtoSNC 1day 48 SNCSubmitsFinalCOMPLETEFHRRtoNRC 1day Day8 Day1 Day9 Day17 Day25 Day33 Day41 Day49 Day57 Day65 Day73 Day81 Day89 Day97 Day105 Day113 Day121 Task Split Milestone Summary ProjectSummary ExternalTasks ExternalMilestone InactiveTask InactiveMilestone InactiveSummary ManualTask Durationonly ManualSummaryRollup ManualSummary Startonly Finishonly Deadline Progress DurationforCompletion SouthernNuclearPlantFarley FloodHazardReevalution February26,2014 Page2