Summary of Public Meeting Concerning Annual Assessment of the Farley Nuclear Plant, Units 1 and 2, Docket Nos. 05000348 and 05000361
ML19149A422
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 05/29/2019
From: Necota Staples
Division Reactor Projects II
To: Alan Blamey
Division Reactor Projects II
Geanette D
References
Download: ML19149A422 (10)


Text

May 29, 2019 MEMORANDUM TO: Alan Blamey, Chief Reactor Projects Branch 2 Division of Reactor Projects FROM: Necota Staples, Senior Project Engineer /RA/

Reactor Projects Branch 2 Division of Reactor Projects

SUBJECT:

PUBLIC MEETING

SUMMARY

- FARLEY NUCLEAR PLANT DOCKET NOS. 50-348, 50-364 On May 20, 2019, the Nuclear Regulatory Commission (NRC) staff met with members of the public concerning the annual assessment of the Farley Nuclear Plant, Units 1 and 2, in Dothan, AL. The purpose of the open house session was to provide opportunities to discuss the annual assessment of the Farley Nuclear Plant, Units 1 and 2, with the public for the period of January 1, 2018 - December 31, 2018. Enclosed are a list of attendees and a copy of the information displayed at the meeting.

Docket Nos.: 50-348 and 50-364 License No.: NPF-2 and NPF-8

Enclosures:

1. List of Attendees
2. Presentation CONTACT: Necota Staples, RII/DRP 404-997-4644

ML19149A422 OFFICE RII:DRP NAME NStaples DATE 5/ 29 /2018 U.S. Nuclear Regulatory Commission - Annual Public Meeting Farley Nuclear Plant, Columbia, AL May 20, 2019 ATTENDEE NAME ORGANIZATION Mary Coleman Public Cindy Mulvaney Pate Field Representative, U.S.

Representative, Martha Roby Daniel A. Komm Plant Manager, Farley Keith Brown SNC Regulator Affairs Laurel Tolar Communications, Farley Christen Storm Communications, Farley Carol H. Riley SNC Oversight, Farley Alan Blamey U.S. NRC Peter Meier U.S. NRC Kenneth Miller U.S. NRC Enclosure 1

JOSEPH M. FARLEY NUCLEAR PLANT UNITS 1 AND 2 2018 Annual Assessment Reactor Oversight Process Nuclear Regulatory Commission - Region II Meetings Purpose Public forum to address Joseph M. Farley Nuclear Plants performance in 2018 Provide an overview on NRC inspection activities NRC Resident Inspectors and Representatives are available for individual discussion; questions and answers Enclosure 2

2 Region II Organization Catherine Haney Regional Administrator Laura A. Dudes Deputy Regional Administrator Joel Munday Anthony Gody Director, Division of Director, Division of Reactor Projects Reactor Safety Mark Franke Mark Miller Deputy Director Deputy Director Alan Blamey Branch Chief Inspectors Various Farley Project Engineers Resident Inspectors Necota Staples Pete Meier Delza Mas Ken Miller Resident Inspector Program Inspectors live in the community and work at Farley Nuclear Plant Provide daily coverage and oversight of plant activity

3 4

NRC Annual Assessment Summary Farley Nuclear Plant Farley Nuclear Plant operated safely and in a manner that preserved the public health and safety and protected the environment All inspection findings identified were of very low safety significance (Green)

Farley Nuclear Plant PIs and Findings 2018 All Performance Indicators were Green (no performance thresholds exceeded) 10 Green non-cited violations.

One Green, Notice of a Violation, Severity Level IV, Interference with the operation of a respirator.

One Apparent Violation (open) for protection of safeguards information was issued.

The licensee agreed to alternative dispute resolution with the NRC. On January 29, 2019, the NRC issued a Confirmatory Order to Plant Farley for the protection of safeguards information.

5 NRC Annual Assessment Summary Farley Nuclear Plant Farley Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2018 Cross-cutting issues: None NRC plans baseline inspections at Farley Nuclear Plant for 2019 and to conduct an additional inspection in accordance with Inspection Procedure 92702, Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders to assess your implementation of the confirmatory order from the protection of safeguards information.

(AV 05000348, 364/2018411-01; EA 032).

6 7

End of Presentation Nuclear Regulatory Commission Region II Dothan, AL May 20, 2019