ML18156A553: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML18156A553
| number = ML18156A553
| issue date = 06/05/2018
| issue date = 06/05/2018
| title = Ltr 06/05/18 Prairie Island Nuclear Generating Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2018004; 05000306/2018004 (DRS-M.Holmberg)
| title = Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2018004; 05000306/2018004 (DRS-M.Holmberg)
| author name = Holmberg M S
| author name = Holmberg M
| author affiliation = NRC/RGN-III/DRS/EB1
| author affiliation = NRC/RGN-III/DRS/EB1
| addressee name = Sharp S
| addressee name = Sharp S
Line 14: Line 14:
| page count = 9
| page count = 9
}}
}}
See also: [[followed by::IR 05000282/2018004]]
See also: [[see also::IR 05000282/2018004]]


=Text=
=Text=
{{#Wiki_filter:June 5, 2018 Mr. Scott Sharp Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company, Minnesota 1717 Wakonade Drive East Welch, MN 55089-9642 SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1NOTIFICATION OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION REPORT 05000282/2018004; 05000306/2018004 Dear Mr. Sharp: On October 1, 2018, the U. S. Nuclear Regulatory Commission (NRC) will begin the Baseline Inservice Inspection (Procedure 71111.08). This onsite inspection is scheduled to be performed October 1, 2018, through October 19, 2018. Experience has shown that this inspection is resource intensive both for the NRC inspector and your staff. In order to minimize the impact to your onsite resources, and to ensure a productive inspection for both sides, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups.   The first group identifies information necessary to ensure that the inspector is adequately prepared. The second group identifies the information the inspector will need upon arrival at the site. It is important that all of these documents are up-to-date, and complete, in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. We have discussed the schedule for inspection activities with your staff and understand that our regulatory contact for this inspection will be Ms. P. Johnson, of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector Mr. M. Holmberg at 630-829-9748 or via e-mail at msh@nrc.gov.   This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.  
{{#Wiki_filter:June 5, 2018
S. Sharp -2- This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part   Sincerely, /RA/   Mel Holmberg, Reactor Inspector Engineering Branch 1 Division of Reactor Safety Docket Nos. 50282, 50306 License Nos. DPR42, DPR60  Enclosure: Inservice Inspection Document Request cc: Distribution via LISTSERV
Mr. Scott Sharp
S. Sharp -2- Letter to Scott Sharp from Mel Holmberg dated June 5, 2018 SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1NOTIFICATION OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION REPORT 05000282/2018004; 05000306/2018004 DISTRIBUTION: Jeremy Bowen RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3 RidsNrrDirsIrib Resource Steven West Darrell Roberts Richard Skokowski Allan Barker DRPIII DRSIII                             ADAMS Accession Number ML:  18156A553 OFFICE RIII RIII RIII RIII  NAME MHolmberg:cl   DATE 06/05/18   OFFICIAL RECORD COPY
Site Vice President
INSERVICE INSPECTION DOCUMENT REQUEST Enclosure Inspection Dates: October 1, 2018, through October 19, 2018   Inspection Procedures: IP 71111-08Inservice Inspection   Lead Inspector: M. Holmberg, DRS 630-829-9748 msh@nrc.gov   A. Information for the In-Office Preparation Week The following information is requested as an (electronic copy CD ROM if possible) by September 11, 2018, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and a list of additional documents needed on-site from your staff. We request that the specific items selected from the lists be available and ready for review on the first day of inspection. The following information is applicable to the outage unit unless otherwise indicated. If you have any questions regarding this information, please call the inspector as soon as possible. 1. For the upcoming outage, a detailed schedule and description of: a. Non-destructive examinations (NDE) planned for Class 1 and 2 Systems and containment, performed as part of your American Society of Mechanical Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition and addenda of Code committed to), and NDEs planned for other systems performed as part of a Risk-Informed ISI Program, or other augmented inspection programs (e.g., ASME Code Case N-770-1 examination of dissimilar metal welds and examinations to meet an industry initiative). For each weld examination, include the weld identification number, description of weld (component name), category, class, type of exam and procedure number, and date of examination; b. Reactor vessel upper head examinations required by Title 10 of the Code of Federal Regulations (CFR), Part 50.55a(g)(6)(ii)(D) and Code Case N-729-1; c. Steam generator (SG) tube inspection and repair activities for the upcoming outage or SG secondary side examinations1; and d. Welding on Code Class 1, 2, or 3 components.                                                 1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur and no further information is required for the items identified above requesting SG related information.
Prairie Island Nuclear Generating Plant
INSERVICE INSPECTION DOCUMENT REQUEST 2 2. A copy of the NDE procedures, SG eddy current examination (ET) acquisition and analysis procedures, and welding procedures used to perform the activities identified in Item A.1 (including NDE calibration and flaw characterization/sizing procedures and Welding Procedure Qualification Records). For ultrasonic examination procedures qualified in accordance with Appendix VIII, of Section XI of the ASME Code, provide documentation supporting the procedure qualification (e.g., the Electric Power Research Institute (EPRI) performance demonstration qualification summary sheets). For SG tube ET testing this includes the acquisition and analysis procedures. 3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations identified in Item A.1.   4. A copy of the 10-year ISI Program showing those required exams scheduled to be performed this outage, and those which have been completed. 5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye penetrant), which have identified relevant indications on Code Class 1 and 2 Systems since the beginning of the last refueling outage. 6. List with short description of the welds in Code Class 1 and 2 Systems, which have been fabricated due to component repair/replacement activities since the beginning of the last refueling outage and identify the system, weld number, and reference applicable documentation (e.g., NIS-2 forms with definitions of system and component acronyms). 7. If reactor vessel weld examinations required by the ASME Code are scheduled to occur during the inspection period, provide a detailed description of the welds to be examined, and the extent of the planned examination. 8. List with description of ISI and SG-related issues such as piping or SG tube degradation or damage (e.g., cracks, wall thinning, wear, microbiologically induced corrosion) or errors identified during piping/SG tube examinations that have been entered into your corrective action system since the beginning of the last refueling outage. Also, include a list of corrective action records associated with foreign material introduced/identified in the reactor vessel, primary coolant system, steam generator or feed systems since the beginning of the last refueling outage. 9. Copy of any 10 CFR Part 21 reports applicable to your structures systems or components within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage. 10. Copy of SG history documentation given to vendors performing ET testing of the SGs during the upcoming outage1.                                                 1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur and no further information is required for the items identified above requesting SG related information.
Northern States Power Company, Minnesota
INSERVICE INSPECTION DOCUMENT REQUEST 3 11. Copy of procedure containing screening criteria used for selecting tubes for in-situ pressure testing and the procedure to be used for in-situ pressure testing1. 12. Copy of previous outage SG tube operational assessment completed following ET of the SGs (provide this document even if no SG ET is planned for current outage). 13. Copy of most recent SG Degradation Assessment (provide this document even if no SG ET is planned for current outage). 14. Copy of most recent SG Condition Monitoring Assessments1. 15. Copy of the document defining the planned SG ET scope (e.g., 100 percent of unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion transition regions with rotating probe) and identify the scope expansion criteria, which will be applied. Also identify and describe any deviations in this scope or expansion criteria from the EPRI Guidelines1. 16. Copy of the document describing the ET acquisition equipment to be applied including ET probe types. Also identify the extent of planned tube examination coverage with each probe type (e.g., rotating probe - 0.080 inches, 0.115 inches pancake coils and mid-range + point coil applied at the top-of-tube-sheet plus 3 inches to minus 12 inches). 17. Provide procedures with guidance/instructions for identifying (e.g. physically locating the tubes that require repair) and plugging SG tubes1. 18. Identify and quantify any SG tube leakage experienced during the previous operating cycle. Also provide documentation identifying which SG was leaking and corrective actions completed or planned for this condition. 19. Deleted. 20. Point of contact information (name and site number) for the following activities: a. ISISite and vendor leads b. Boric Acid Inspections and Evaluations c. Reactor Vessel Head InspectionSite and vendor leads d. SG InspectionSite and vendor leads e. Aging Management Programs f. Site Welding Engineer                                                 1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur and no further information is required for the items identified above requesting SG related information.
1717 Wakonade Drive East
INSERVICE INSPECTION DOCUMENT REQUEST 4 B. Onsite Information to be Provided to the Inspector on the First Day of the Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies (e.g., Paper Records) of the Following Documents. 1. For welds selected by the inspector from Item A.1.d and A.6 above, provide copies of the following documents: a. Document of the weld number and location (e.g., system, train, branch); b. Document with a detail of the weld construction (e.g., drawing); c. Applicable portions of the Design Specification and applicable Code of construction for the weldment (e.g., B31.1 or ASME Section III); d. Applicable Code Edition and Addenda for weld procedure qualification; e. Applicable weld procedure specifications and weld data sheets used to fabricate the welds; f. Copies of procedure qualification records supporting the weld procedure specifications; g.   h. Copies of mechanical test reports identified in the weld procedure qualification records above; i. Copies of the nonconformance reports for the selected welds; j. Access to radiographs and equipment to view radiographs of the selected welds;   k. ASME Code Section XI repair replacement plan and reconciliation for replacement components/materials; l. Certified Material Test Reports for replacement pressure boundary materials; and m. Copies of the NDE required by the construction Code and the pre-service examination records required by the ASME Code Section XI for the selected welds. 2. For the ISI-related corrective action issues selected by the inspector from Item A.8 above, provide a copy of the corrective actions and supporting documentation. 3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems selected by the inspector from Item A.5 above, provide a copy of the examination records and associated corrective action documents. Updated schedules for Item A.1 (including schedule showing contingency repair plans if available).  
Welch, MN 55089-9642
INSERVICE INSPECTION DOCUMENT REQUEST 5 4. Copy of the procedures which govern the scope, equipment used, and implementation of the inspections required to identify boric acid leakage from systems and components above the vessel head. 5. Copy of: a. Engineering evaluations/assessments of boric acid related deposits and associated wastage or corrosion for safety-significant components; and b. Corrective action records for coolant leakage including boric acid deposits on safety-related components identified since the beginning of the last refueling outage. 6. Copy of the plant procedures used to perform inspections to identify reactor coolant system leaks or boric acid deposits and the procedures for resolution of leaks or boric acid deposits. 7. Fabrication Drawings (D size) of the reactor vessel welds (including vessel head J-groove welds) if any are to be examined during the outage. Also provide any drawings used by NDE vendors to locate these welds. 8. Copy of the documents which demonstrate that the procedures to be used for volumetric examination of the reactor vessel head penetration J-groove welds were qualified by a blind demonstration test in accordance with 10 CFR 50.55a(g)(6)(ii)(D). 9. Copy of volumetric, surface and visual examination records for the prior inspection of the reactor vessel head and head penetration J-groove welds. 10. Provide a copy of the EPRI Examination Technique Specification Sheets and vendor related documents, which support qualification of the ET probes to be used during the upcoming SG tube inspections1. 11. Provide a copy of the guidance to be followed if a loose part or foreign material is identified in the SGs1. 12. Identify the types of SG tube repair processes which will be implemented for defective SG tubes (including any U.S. Nuclear Regulatory Commission reviews/evaluation/approval of this repair process). Provide the flaw depth sizing criteria to be applied for ET indications identified in the SG tubes1. 13. Copy of document describing actions to be taken if a new SG tube degradation mechanism is identified1. 14. Provide document which defines the scope of SG secondary side examinations (if any are planned) and identify site specific operational history related to degradation of SG secondary side components (if any).                                                 1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur and no further information is required for the items identified above requesting SG related information.
SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1NOTIFICATION
INSERVICE INSPECTION DOCUMENT REQUEST 6 15. Provide procedures with guidance/instructions for identifying (e.g., physically locating the tubes that require repair) and plugging SG tubes1. 16. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory Commission inspection location for the duration of the inspection: a. Sections V, IX, and XI of the ASME Code with Editions applicable to the ISI Program and the Repair/Replacement Program; b. Copy of the performance demonstration initiative (PDI) generic procedures with the latest applicable revisions that support site qualified ultrasonic examination of piping welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3, PDI-UT-10 etc.);   c. EPRI and industry standards referenced in the site procedures used to perform the SG tube ET, which includes EPRI documents: SG Examination Guidelines, SG Integrity Assessment Guidelines, SG In-Situ Pressure Test Guidelines1; and d. Boric Acid Corrosion Guidebook Revision 1EPRI Technical Report 1000975. 17. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if required to access the NDEs selected by the inspector for observation. If you have questions regarding the information requested, please contact the lead inspector.                                                   1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur and no further information is required for the items identified above requesting SG related information.
              OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION;
              INSPECTION REPORT 05000282/2018004; 05000306/2018004
Dear Mr. Sharp:
On October 1, 2018, the U. S. Nuclear Regulatory Commission (NRC) will begin the Baseline
Inservice Inspection (Procedure 71111.08). This onsite inspection is scheduled to be performed
October 1, 2018, through October 19, 2018.
Experience has shown that this inspection is resource intensive both for the NRC inspector and
your staff. In order to minimize the impact to your onsite resources, and to ensure a productive
inspection for both sides, we have enclosed a request for documents needed for this inspection.
These documents have been divided into two groups.
The first group identifies information necessary to ensure that the inspector is adequately
prepared. The second group identifies the information the inspector will need upon arrival at
the site. It is important that all of these documents are up-to-date, and complete, in order to
minimize the number of additional documents requested during the preparation and/or the
onsite portions of the inspection.
We have discussed the schedule for inspection activities with your staff and understand that our
regulatory contact for this inspection will be Ms. P. Johnson, of your organization. If there are
any questions about this inspection or the material requested, please contact the lead inspector
Mr. M. Holmberg at 630-829-9748 or via e-mail at msh@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
 
S. Sharp                                     -2-
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
Exemptions, Requests for Withholding.
                                            Sincerely,
                                            /RA/
                                            Mel Holmberg, Reactor Inspector
                                            Engineering Branch 1
                                            Division of Reactor Safety
Docket Nos. 50-282, 50-306
License Nos. DPR-42, DPR-60
Enclosure:
Inservice Inspection Document Request
cc: Distribution via LISTSERV
 
S. Sharp                                   -2-
Letter to Scott Sharp from Mel Holmberg dated June 5, 2018
SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1NOTIFICATION
            OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION;
            INSPECTION REPORT 05000282/2018004; 05000306/2018004
DISTRIBUTION:
Jeremy Bowen
RidsNrrPMPrairieIsland Resource
RidsNrrDorlLpl3
RidsNrrDirsIrib Resource
Steven West
Darrell Roberts
Richard Skokowski
Allan Barker
DRPIII
DRSIII
ADAMS Accession Number ML: 18156A553
  OFFICE RIII                     RIII             RIII       RIII
  NAME       MHolmberg:cl
DATE       06/05/18
                                  OFFICIAL RECORD COPY
 
                            INSERVICE INSPECTION DOCUMENT REQUEST
Inspection Dates:                               October 1, 2018, through October 19, 2018
Inspection Procedures:                         IP 71111-08, Inservice Inspection
Lead Inspector:                                 M. Holmberg, DRS
                                                630-829-9748
                                                msh@nrc.gov
A.       Information for the In-Office Preparation Week
        The following information is requested as an (electronic copy CD ROM if possible) by
        September 11, 2018, to facilitate the selection of specific items that will be reviewed
        during the onsite inspection week. The inspector will select specific items from the
        information requested below and a list of additional documents needed on-site from your
        staff. We request that the specific items selected from the lists be available and ready
        for review on the first day of inspection. The following information is applicable to the
        outage unit unless otherwise indicated. If you have any questions regarding this
        information, please call the inspector as soon as possible.
        1.       For the upcoming outage, a detailed schedule and description of:
                  a. Non-destructive examinations (NDE) planned for Class 1 and 2 Systems and
                      containment, performed as part of your American Society of Mechanical
                      Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition
                      and addenda of Code committed to), and NDEs planned for other systems
                      performed as part of a Risk-Informed ISI Program, or other augmented
                      inspection programs (e.g., ASME Code Case N-770-1 examination of
                      dissimilar metal welds and examinations to meet an industry initiative). For
                      each weld examination, include the weld identification number, description of
                      weld (component name), category, class, type of exam and procedure
                      number, and date of examination;
                  b. Reactor vessel upper head examinations required by Title 10 of the Code of
                      Federal Regulations (CFR), Part 50.55a(g)(6)(ii)(D) and Code Case N-729-1;
                  c. Steam generator (SG) tube inspection and repair activities for the upcoming
                      outage or SG secondary side examinations1; and
                  d. Welding on Code Class 1, 2, or 3 components.
1
  Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
                                                                                                        Enclosure
 
                            INSERVICE INSPECTION DOCUMENT REQUEST
        2.       A copy of the NDE procedures, SG eddy current examination (ET) acquisition
                  and analysis procedures, and welding procedures used to perform the activities
                  identified in Item A.1 (including NDE calibration and flaw characterization/sizing
                  procedures and Welding Procedure Qualification Records). For ultrasonic
                  examination procedures qualified in accordance with Appendix VIII, of Section XI
                  of the ASME Code, provide documentation supporting the procedure qualification
                  (e.g., the Electric Power Research Institute (EPRI) performance demonstration
                  qualification summary sheets). For SG tube ET testing this includes the
                  acquisition and analysis procedures.
        3.       A copy of ASME Section XI, Code Relief Requests applicable to the
                  examinations identified in Item A.1.
        4.       A copy of the 10-year ISI Program showing those required exams scheduled to
                  be performed this outage, and those which have been completed.
        5.       A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye
                  penetrant), which have identified relevant indications on Code Class 1 and 2
                  Systems since the beginning of the last refueling outage.
        6.       List with short description of the welds in Code Class 1 and 2 Systems, which
                  have been fabricated due to component repair/replacement activities since the
                  beginning of the last refueling outage and identify the system, weld number, and
                  reference applicable documentation (e.g., NIS-2 forms with definitions of system
                  and component acronyms).
        7.       If reactor vessel weld examinations required by the ASME Code are scheduled to
                  occur during the inspection period, provide a detailed description of the welds to
                  be examined, and the extent of the planned examination.
        8.       List with description of ISI and SG-related issues such as piping or SG tube
                  degradation or damage (e.g., cracks, wall thinning, wear, microbiologically
                  induced corrosion) or errors identified during piping/SG tube examinations that
                  have been entered into your corrective action system since the beginning of the
                  last refueling outage. Also, include a list of corrective action records associated
                  with foreign material introduced/identified in the reactor vessel, primary coolant
                  system, steam generator or feed systems since the beginning of the last refueling
                  outage.
        9.       Copy of any 10 CFR Part 21 reports applicable to your structures systems or
                  components within the scope of Section XI of the ASME Code that have been
                  identified since the beginning of the last refueling outage.
        10.       Copy of SG history documentation given to vendors performing ET testing of the
                  SGs during the upcoming outage1.
1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
                                                              2
 
                            INSERVICE INSPECTION DOCUMENT REQUEST
        11.       Copy of procedure containing screening criteria used for selecting tubes for
                  in-situ pressure testing and the procedure to be used for in-situ pressure testing1.
        12.       Copy of previous outage SG tube operational assessment completed following
                  ET of the SGs (provide this document even if no SG ET is planned for current
                  outage).
        13.       Copy of most recent SG Degradation Assessment (provide this document even if
                  no SG ET is planned for current outage).
        14.       Copy of most recent SG Condition Monitoring Assessments1.
        15.       Copy of the document defining the planned SG ET scope (e.g., 100 percent of
                  unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion
                  transition regions with rotating probe) and identify the scope expansion criteria,
                  which will be applied. Also identify and describe any deviations in this scope or
                  expansion criteria from the EPRI Guidelines1.
        16.       Copy of the document describing the ET acquisition equipment to be applied
                  including ET probe types. Also identify the extent of planned tube examination
                  coverage with each probe type (e.g., rotating probe - 0.080 inches, 0.115 inches
                  pancake coils and mid-range + point coil applied at the top-of-tube-sheet plus
                  3 inches to minus 12 inches).
        17.       Provide procedures with guidance/instructions for identifying (e.g. physically
                  locating the tubes that require repair) and plugging SG tubes1.
        18.       Identify and quantify any SG tube leakage experienced during the previous
                  operating cycle. Also provide documentation identifying which SG was leaking
                  and corrective actions completed or planned for this condition.
        19.       Deleted.
        20.       Point of contact information (name and site number) for the following activities:
                  a. ISISite and vendor leads
                  b. Boric Acid Inspections and Evaluations
                  c. Reactor Vessel Head InspectionSite and vendor leads
                  d. SG InspectionSite and vendor leads
                  e. Aging Management Programs
                  f. Site Welding Engineer
1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
                                                              3
 
                  INSERVICE INSPECTION DOCUMENT REQUEST
B. Onsite Information to be Provided to the Inspector on the First Day of the
  Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies
  (e.g., Paper Records) of the Following Documents.
  1.     For welds selected by the inspector from Item A.1.d and A.6 above, provide
          copies of the following documents:
          a. Document of the weld number and location (e.g., system, train, branch);
          b. Document with a detail of the weld construction (e.g., drawing);
          c. Applicable portions of the Design Specification and applicable Code of
              construction for the weldment (e.g., B31.1 or ASME Section III);
          d. Applicable Code Edition and Addenda for weld procedure qualification;
          e. Applicable weld procedure specifications and weld data sheets used to
              fabricate the welds;
          f. Copies of procedure qualification records supporting the weld procedure
              specifications;
          g. Copies of welders performance qualification records;
          h. Copies of mechanical test reports identified in the weld procedure
              qualification records above;
          i. Copies of the nonconformance reports for the selected welds;
          j. Access to radiographs and equipment to view radiographs of the selected
              welds;
          k. ASME Code Section XI repair replacement plan and reconciliation for
              replacement components/materials;
          l. Certified Material Test Reports for replacement pressure boundary materials;
              and
          m. Copies of the NDE required by the construction Code and the pre-service
              examination records required by the ASME Code Section XI for the selected
              welds.
  2.     For the ISI-related corrective action issues selected by the inspector from Item
          A.8 above, provide a copy of the corrective actions and supporting
          documentation.
  3.     For the NDE reports with relevant indications on Code Class 1 and 2 Systems
          selected by the inspector from Item A.5 above, provide a copy of the examination
          records and associated corrective action documents. Updated schedules for
          Item A.1 (including schedule showing contingency repair plans if available).
                                              4
 
                            INSERVICE INSPECTION DOCUMENT REQUEST
        4.       Copy of the procedures which govern the scope, equipment used, and
                  implementation of the inspections required to identify boric acid leakage from
                  systems and components above the vessel head.
        5.       Copy of:
                  a. Engineering evaluations/assessments of boric acid related deposits and
                        associated wastage or corrosion for safety-significant components; and
                  b. Corrective action records for coolant leakage including boric acid deposits on
                        safety-related components identified since the beginning of the last refueling
                        outage.
        6.       Copy of the plant procedures used to perform inspections to identify reactor
                  coolant system leaks or boric acid deposits and the procedures for resolution of
                  leaks or boric acid deposits.
        7.       Fabrication Drawings (D size) of the reactor vessel welds (including vessel head
                  J-groove welds) if any are to be examined during the outage. Also provide any
                  drawings used by NDE vendors to locate these welds.
        8.       Copy of the documents which demonstrate that the procedures to be used
                  for volumetric examination of the reactor vessel head penetration J-groove
                  welds were qualified by a blind demonstration test in accordance with
                  10 CFR 50.55a(g)(6)(ii)(D).
        9.       Copy of volumetric, surface and visual examination records for the prior
                  inspection of the reactor vessel head and head penetration J-groove welds.
        10.       Provide a copy of the EPRI Examination Technique Specification Sheets and
                  vendor related documents, which support qualification of the ET probes to be
                  used during the upcoming SG tube inspections1.
        11.       Provide a copy of the guidance to be followed if a loose part or foreign material is
                  identified in the SGs1.
        12.       Identify the types of SG tube repair processes which will be implemented for
                  defective SG tubes (including any U.S. Nuclear Regulatory Commission
                  reviews/evaluation/approval of this repair process). Provide the flaw depth
                  sizing criteria to be applied for ET indications identified in the SG tubes1.
        13.       Copy of document describing actions to be taken if a new SG tube degradation
                  mechanism is identified1.
        14.       Provide document which defines the scope of SG secondary side examinations
                  (if any are planned) and identify site specific operational history related to
                  degradation of SG secondary side components (if any).
1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
                                                              5
 
                            INSERVICE INSPECTION DOCUMENT REQUEST
        15.       Provide procedures with guidance/instructions for identifying (e.g., physically
                  locating the tubes that require repair) and plugging SG tubes1.
        16.       Provide copies of the following standards at the onsite U.S. Nuclear Regulatory
                  Commission inspection location for the duration of the inspection:
                  a. Sections V, IX, and XI of the ASME Code with Editions applicable to the
                      ISI Program and the Repair/Replacement Program;
                  b. Copy of the performance demonstration initiative (PDI) generic procedures
                      with the latest applicable revisions that support site qualified ultrasonic
                      examination of piping welds and components (e.g., PDI-UT-1, PDI-UT-2,
                      PDI-UT-3, PDI-UT-10 etc.);
                  c. EPRI and industry standards referenced in the site procedures used to
                      perform the SG tube ET, which includes EPRI documents: SG Examination
                      Guidelines, SG Integrity Assessment Guidelines, SG In-Situ Pressure Test
                      Guidelines1; and
                  d. Boric Acid Corrosion Guidebook Revision 1EPRI Technical
                      Report 1000975.
        17.       Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if
                  required to access the NDEs selected by the inspector for observation.
If you have questions regarding the information requested, please contact the lead inspector.
1
  Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur
and no further information is required for the items identified above requesting SG related information.
                                                              6
}}
}}

Latest revision as of 16:57, 15 November 2019

Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2018004; 05000306/2018004 (DRS-M.Holmberg)
ML18156A553
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 06/05/2018
From: Mel Holmberg
NRC/RGN-III/DRS/EB1
To: Sharp S
Northern States Power Company, Minnesota
References
IR 2018004
Download: ML18156A553 (9)


See also: IR 05000282/2018004

Text

June 5, 2018

Mr. Scott Sharp

Site Vice President

Prairie Island Nuclear Generating Plant

Northern States Power Company, Minnesota

1717 Wakonade Drive East

Welch, MN 55089-9642

SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1NOTIFICATION

OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION;

INSPECTION REPORT 05000282/2018004; 05000306/2018004

Dear Mr. Sharp:

On October 1, 2018, the U. S. Nuclear Regulatory Commission (NRC) will begin the Baseline

Inservice Inspection (Procedure 71111.08). This onsite inspection is scheduled to be performed

October 1, 2018, through October 19, 2018.

Experience has shown that this inspection is resource intensive both for the NRC inspector and

your staff. In order to minimize the impact to your onsite resources, and to ensure a productive

inspection for both sides, we have enclosed a request for documents needed for this inspection.

These documents have been divided into two groups.

The first group identifies information necessary to ensure that the inspector is adequately

prepared. The second group identifies the information the inspector will need upon arrival at

the site. It is important that all of these documents are up-to-date, and complete, in order to

minimize the number of additional documents requested during the preparation and/or the

onsite portions of the inspection.

We have discussed the schedule for inspection activities with your staff and understand that our

regulatory contact for this inspection will be Ms. P. Johnson, of your organization. If there are

any questions about this inspection or the material requested, please contact the lead inspector

Mr. M. Holmberg at 630-829-9748 or via e-mail at msh@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

S. Sharp -2-

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

/RA/

Mel Holmberg, Reactor Inspector

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-282, 50-306

License Nos. DPR-42, DPR-60

Enclosure:

Inservice Inspection Document Request

cc: Distribution via LISTSERV

S. Sharp -2-

Letter to Scott Sharp from Mel Holmberg dated June 5, 2018

SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1NOTIFICATION

OF NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION;

INSPECTION REPORT 05000282/2018004; 05000306/2018004

DISTRIBUTION:

Jeremy Bowen

RidsNrrPMPrairieIsland Resource

RidsNrrDorlLpl3

RidsNrrDirsIrib Resource

Steven West

Darrell Roberts

Richard Skokowski

Allan Barker

DRPIII

DRSIII

ADAMS Accession Number ML: 18156A553

OFFICE RIII RIII RIII RIII

NAME MHolmberg:cl

DATE 06/05/18

OFFICIAL RECORD COPY

INSERVICE INSPECTION DOCUMENT REQUEST

Inspection Dates: October 1, 2018, through October 19, 2018

Inspection Procedures: IP 71111-08, Inservice Inspection

Lead Inspector: M. Holmberg, DRS

630-829-9748

msh@nrc.gov

A. Information for the In-Office Preparation Week

The following information is requested as an (electronic copy CD ROM if possible) by

September 11, 2018, to facilitate the selection of specific items that will be reviewed

during the onsite inspection week. The inspector will select specific items from the

information requested below and a list of additional documents needed on-site from your

staff. We request that the specific items selected from the lists be available and ready

for review on the first day of inspection. The following information is applicable to the

outage unit unless otherwise indicated. If you have any questions regarding this

information, please call the inspector as soon as possible.

1. For the upcoming outage, a detailed schedule and description of:

a. Non-destructive examinations (NDE) planned for Class 1 and 2 Systems and

containment, performed as part of your American Society of Mechanical

Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition

and addenda of Code committed to), and NDEs planned for other systems

performed as part of a Risk-Informed ISI Program, or other augmented

inspection programs (e.g., ASME Code Case N-770-1 examination of

dissimilar metal welds and examinations to meet an industry initiative). For

each weld examination, include the weld identification number, description of

weld (component name), category, class, type of exam and procedure

number, and date of examination;

b. Reactor vessel upper head examinations required by Title 10 of the Code of

Federal Regulations (CFR), Part 50.55a(g)(6)(ii)(D) and Code Case N-729-1;

c. Steam generator (SG) tube inspection and repair activities for the upcoming

outage or SG secondary side examinations1; and

d. Welding on Code Class 1, 2, or 3 components.

1

Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur

and no further information is required for the items identified above requesting SG related information.

Enclosure

INSERVICE INSPECTION DOCUMENT REQUEST

2. A copy of the NDE procedures, SG eddy current examination (ET) acquisition

and analysis procedures, and welding procedures used to perform the activities

identified in Item A.1 (including NDE calibration and flaw characterization/sizing

procedures and Welding Procedure Qualification Records). For ultrasonic

examination procedures qualified in accordance with Appendix VIII, of Section XI

of the ASME Code, provide documentation supporting the procedure qualification

(e.g., the Electric Power Research Institute (EPRI) performance demonstration

qualification summary sheets). For SG tube ET testing this includes the

acquisition and analysis procedures.

3. A copy of ASME Section XI, Code Relief Requests applicable to the

examinations identified in Item A.1.

4. A copy of the 10-year ISI Program showing those required exams scheduled to

be performed this outage, and those which have been completed.

5. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye

penetrant), which have identified relevant indications on Code Class 1 and 2

Systems since the beginning of the last refueling outage.

6. List with short description of the welds in Code Class 1 and 2 Systems, which

have been fabricated due to component repair/replacement activities since the

beginning of the last refueling outage and identify the system, weld number, and

reference applicable documentation (e.g., NIS-2 forms with definitions of system

and component acronyms).

7. If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the inspection period, provide a detailed description of the welds to

be examined, and the extent of the planned examination.

8. List with description of ISI and SG-related issues such as piping or SG tube

degradation or damage (e.g., cracks, wall thinning, wear, microbiologically

induced corrosion) or errors identified during piping/SG tube examinations that

have been entered into your corrective action system since the beginning of the

last refueling outage. Also, include a list of corrective action records associated

with foreign material introduced/identified in the reactor vessel, primary coolant

system, steam generator or feed systems since the beginning of the last refueling

outage.

9. Copy of any 10 CFR Part 21 reports applicable to your structures systems or

components within the scope of Section XI of the ASME Code that have been

identified since the beginning of the last refueling outage.

10. Copy of SG history documentation given to vendors performing ET testing of the

SGs during the upcoming outage1.

1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur

and no further information is required for the items identified above requesting SG related information.

2

INSERVICE INSPECTION DOCUMENT REQUEST

11. Copy of procedure containing screening criteria used for selecting tubes for

in-situ pressure testing and the procedure to be used for in-situ pressure testing1.

12. Copy of previous outage SG tube operational assessment completed following

ET of the SGs (provide this document even if no SG ET is planned for current

outage).

13. Copy of most recent SG Degradation Assessment (provide this document even if

no SG ET is planned for current outage).

14. Copy of most recent SG Condition Monitoring Assessments1.

15. Copy of the document defining the planned SG ET scope (e.g., 100 percent of

unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion

transition regions with rotating probe) and identify the scope expansion criteria,

which will be applied. Also identify and describe any deviations in this scope or

expansion criteria from the EPRI Guidelines1.

16. Copy of the document describing the ET acquisition equipment to be applied

including ET probe types. Also identify the extent of planned tube examination

coverage with each probe type (e.g., rotating probe - 0.080 inches, 0.115 inches

pancake coils and mid-range + point coil applied at the top-of-tube-sheet plus

3 inches to minus 12 inches).

17. Provide procedures with guidance/instructions for identifying (e.g. physically

locating the tubes that require repair) and plugging SG tubes1.

18. Identify and quantify any SG tube leakage experienced during the previous

operating cycle. Also provide documentation identifying which SG was leaking

and corrective actions completed or planned for this condition.

19. Deleted.

20. Point of contact information (name and site number) for the following activities:

a. ISISite and vendor leads

b. Boric Acid Inspections and Evaluations

c. Reactor Vessel Head InspectionSite and vendor leads

d. SG InspectionSite and vendor leads

e. Aging Management Programs

f. Site Welding Engineer

1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur

and no further information is required for the items identified above requesting SG related information.

3

INSERVICE INSPECTION DOCUMENT REQUEST

B. Onsite Information to be Provided to the Inspector on the First Day of the

Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies

(e.g., Paper Records) of the Following Documents.

1. For welds selected by the inspector from Item A.1.d and A.6 above, provide

copies of the following documents:

a. Document of the weld number and location (e.g., system, train, branch);

b. Document with a detail of the weld construction (e.g., drawing);

c. Applicable portions of the Design Specification and applicable Code of

construction for the weldment (e.g., B31.1 or ASME Section III);

d. Applicable Code Edition and Addenda for weld procedure qualification;

e. Applicable weld procedure specifications and weld data sheets used to

fabricate the welds;

f. Copies of procedure qualification records supporting the weld procedure

specifications;

g. Copies of welders performance qualification records;

h. Copies of mechanical test reports identified in the weld procedure

qualification records above;

i. Copies of the nonconformance reports for the selected welds;

j. Access to radiographs and equipment to view radiographs of the selected

welds;

k. ASME Code Section XI repair replacement plan and reconciliation for

replacement components/materials;

l. Certified Material Test Reports for replacement pressure boundary materials;

and

m. Copies of the NDE required by the construction Code and the pre-service

examination records required by the ASME Code Section XI for the selected

welds.

2. For the ISI-related corrective action issues selected by the inspector from Item

A.8 above, provide a copy of the corrective actions and supporting

documentation.

3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems

selected by the inspector from Item A.5 above, provide a copy of the examination

records and associated corrective action documents. Updated schedules for

Item A.1 (including schedule showing contingency repair plans if available).

4

INSERVICE INSPECTION DOCUMENT REQUEST

4. Copy of the procedures which govern the scope, equipment used, and

implementation of the inspections required to identify boric acid leakage from

systems and components above the vessel head.

5. Copy of:

a. Engineering evaluations/assessments of boric acid related deposits and

associated wastage or corrosion for safety-significant components; and

b. Corrective action records for coolant leakage including boric acid deposits on

safety-related components identified since the beginning of the last refueling

outage.

6. Copy of the plant procedures used to perform inspections to identify reactor

coolant system leaks or boric acid deposits and the procedures for resolution of

leaks or boric acid deposits.

7. Fabrication Drawings (D size) of the reactor vessel welds (including vessel head

J-groove welds) if any are to be examined during the outage. Also provide any

drawings used by NDE vendors to locate these welds.

8. Copy of the documents which demonstrate that the procedures to be used

for volumetric examination of the reactor vessel head penetration J-groove

welds were qualified by a blind demonstration test in accordance with

10 CFR 50.55a(g)(6)(ii)(D).

9. Copy of volumetric, surface and visual examination records for the prior

inspection of the reactor vessel head and head penetration J-groove welds.

10. Provide a copy of the EPRI Examination Technique Specification Sheets and

vendor related documents, which support qualification of the ET probes to be

used during the upcoming SG tube inspections1.

11. Provide a copy of the guidance to be followed if a loose part or foreign material is

identified in the SGs1.

12. Identify the types of SG tube repair processes which will be implemented for

defective SG tubes (including any U.S. Nuclear Regulatory Commission

reviews/evaluation/approval of this repair process). Provide the flaw depth

sizing criteria to be applied for ET indications identified in the SG tubes1.

13. Copy of document describing actions to be taken if a new SG tube degradation

mechanism is identified1.

14. Provide document which defines the scope of SG secondary side examinations

(if any are planned) and identify site specific operational history related to

degradation of SG secondary side components (if any).

1 Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur

and no further information is required for the items identified above requesting SG related information.

5

INSERVICE INSPECTION DOCUMENT REQUEST

15. Provide procedures with guidance/instructions for identifying (e.g., physically

locating the tubes that require repair) and plugging SG tubes1.

16. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory

Commission inspection location for the duration of the inspection:

a. Sections V, IX, and XI of the ASME Code with Editions applicable to the

ISI Program and the Repair/Replacement Program;

b. Copy of the performance demonstration initiative (PDI) generic procedures

with the latest applicable revisions that support site qualified ultrasonic

examination of piping welds and components (e.g., PDI-UT-1, PDI-UT-2,

PDI-UT-3, PDI-UT-10 etc.);

c. EPRI and industry standards referenced in the site procedures used to

perform the SG tube ET, which includes EPRI documents: SG Examination

Guidelines, SG Integrity Assessment Guidelines, SG In-Situ Pressure Test

Guidelines1; and

d. Boric Acid Corrosion Guidebook Revision 1EPRI Technical

Report 1000975.

17. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if

required to access the NDEs selected by the inspector for observation.

If you have questions regarding the information requested, please contact the lead inspector.

1

Note 1- If no SG examinations are planned for this outage, please confirm when the next SG examination will occur

and no further information is required for the items identified above requesting SG related information.

6