Category:Inspection Plan
MONTHYEARIR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20220062023-03-0101 March 2023 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report, Units 1 and 2 (Report 05000282/2022006 and 05000306/2022006) ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 IR 05000282/20220052022-08-29029 August 2022 Updated Inspection Plan for Prairie Island Nuclear Generating Plant (Report 05000282/2022005; 05000306/2022005) ML22007A1542022-01-0707 January 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report 05000282/2022010 and 05000306/2022010 ML21363A0542021-12-29029 December 2021 Prairie Nuclear Generating Plant - Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information; Inspection Report 05000282/2022002 05000306/2022002 IR 05000282/20210052021-09-0101 September 2021 Updated Inspection Plan for Prairie Island Nuclear Generating Plant Units 1 and 2 (Report 05000282/2021005 and 05000306/2021005) IR 05000282/20200062021-03-0404 March 2021 Annual Assessment Letter for the Prairie Island Nuclear Generating Plant (Report 05000282/2020006 and 05000306/2020006) ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant IR 05000282/20200052020-09-0101 September 2020 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2020005 and 05000306/2020005) ML20189A1782020-07-0606 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2020004; 05000306/2020004 IR 05000282/20190062020-03-0303 March 2020 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2019006 and 05000306/2019006) IR 05000282/20190052019-08-28028 August 2019 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2019005; 05000306/2019005) ML19136A1562019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19071A3532019-03-12012 March 2019 Ltr. 03/12/19 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000282/2019012; 05000306/2019012 (DRS-A.Dahbur) IR 05000282/20180062019-03-0404 March 2019 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2018006 and 05000306/2018006) ML18324A6122018-11-20020 November 2018 Ltr. 11/20/18 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2019001 and 05000306/2019001 (DRS-N.Feliz-Adorn IR 05000282/20180052018-08-28028 August 2018 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2018005 and 05000286/2018005) ML18156A5532018-06-0505 June 2018 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2018004; 05000306/2018004 (DRS-M.Holmberg) IR 05000282/20170062018-03-0202 March 2018 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2017006; 05000306/2017006) IR 05000282/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000282/2017005 and 05000306/2017005) IR 05000282/20160062017-03-0101 March 2017 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2016006) ML16265A1652016-09-20020 September 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2016004; 05000306/2016004 (Gfo) IR 05000282/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2016005; 05000306/2016005) ML16222A7022016-08-0909 August 2016 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000282/20150062016-03-0202 March 2016 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Inspection Report 05000282/2015006 and 05000306/2015006) ML15261A7182015-09-15015 September 2015 Ltr. 09/15/2015 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000282/2016008; 05000306/2016008. (Dxs) IR 05000282/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2015005; 05000306/2015005) IR 05000282/20140012015-03-0404 March 2015 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2, (Report 05000282/2014001 and 05000306/2014001) ML14245A2012014-09-0202 September 2014 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 ML14209A9342014-07-28028 July 2014 Notification of NRC Inspection and Request for Information IR 05000282/20130012014-03-0404 March 2014 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2(Report 05000282/2013001; 05000306/2013001) ML13246A2392013-09-0303 September 2013 2013 Prairie Island MOC Letter Combined ML13203A2862013-07-22022 July 2013 Notification of Baseline Inspection and Information Request ML13077A4742013-03-18018 March 2013 Information Request for a Post-approval Site Inspection for License Renewal IR 05000282/20120012013-03-0404 March 2013 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2012001 and 05000306/2012001) ML12249A4252012-09-0404 September 2012 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 IR 05000282/20110072012-03-0505 March 2012 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2011007 and 05000306/2011007) IR 05000282/20110062011-09-0101 September 2011 Mid-Cycle Letter for Prairie Island Nuclear Plant, Units 1 and 2, 05000282-11-006; 05000306-11-006 ML1106203132011-03-0404 March 2011 EOC Annual Assessment Letter and Inspection/Activity Plan ML1024400922010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Prairie Island Nuclear Power Plant IR 05000282/20100012010-03-0303 March 2010 Prairie Island Power Plant EOC Assessment Letter (05000282-10-001; 05000306-10-001) ML0924403672009-09-0101 September 2009 Prairie Island - Mid-Cycle Performance Review and Inspection Plan IR 05000282/20090012009-03-0404 March 2009 Annual Assessment Letter - Prairie Island Nuclear Generating Plant, Units 1 and 2 (05000282-09-001 and 050000306-09-001) ML0824603142008-09-0202 September 2008 Prairie Island, Units 1 & 2 - Mid-Cycle Performance Review and Inspection Plan IR 05000282/20080012008-03-0303 March 2008 Prairie Island, EOC Annual Assessment Letter (Inspection Report 05000282-08-001 and 05000306-08-001) ML0735402802007-12-19019 December 2007 Change to the Inspection Plan 1/1/08 - 12/31/08 ML0724302372007-08-31031 August 2007 8/31/07 Prairie Island - Mid-Cycle Performance Review and Inspection Plan 2024-08-28
[Table view] Category:Inspection Report
MONTHYEARIR 05000282/20244032024-10-25025 October 2024 – Security Baseline Inspection Report 05000282/2024403 and 05000306/2024403 IR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 IR 05000282/20244012024-04-25025 April 2024 – Security Baseline Inspection Report 05000282/2024401 and 05000306/2024401 IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) IR 05000282/20230042024-02-0101 February 2024 Integrated Inspection Report 05000282/2023004 and 05000306/2023004 IR 07200010/20234012023-12-20020 December 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200010/2023401 IR 05000282/20234012023-12-13013 December 2023 Security Baseline Inspection Report 05000282/2023401 and 05000306/2023401 IR 05000282/20230032023-11-0808 November 2023 Integrated Inspection Report 05000282/2023003 and 05000306/2023003 IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20230102023-08-17017 August 2023 NRC Inspection Report 05000282/2023010 and 05000306/2023010 IR 05000282/20230022023-08-0303 August 2023 Integrated Inspection Report 05000282/2023002 and 05000306/2023002 IR 05000282/20234202023-06-0101 June 2023 Security Baseline Inspection Report 05000282/2023420 and 05000306/2023420 IR 05000282/20230112023-05-16016 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000282/2023011 and 05000306/2023011 IR 05000282/20230012023-05-10010 May 2023 Integrated Inspection Report 05000282/2023001 and 05000306/2023001 IR 05000282/20220062023-03-0101 March 2023 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report, Units 1 and 2 (Report 05000282/2022006 and 05000306/2022006) IR 05000282/20224042023-01-30030 January 2023 Material Control and Accounting Program Inspection Report 05000282/2022404 and 05000306/2022404 (Public) IR 05000282/20220042023-01-26026 January 2023 Integrated Inspection Report 05000282/2022004 and 05000306/2022004 IR 05000282/20224032023-01-24024 January 2023 – Security Baseline Inspection Report 05000282/2022403 and 05000306/2022403 IR 05000282/20220022022-12-0808 December 2022 RE-Issue Prairie Island Nuclear Generating Plant Integrated Inspection Report 05000282/2022002 and 05000306/2022002 IR 07200010/20222012022-11-0909 November 2022 TN-40HT, Dry Storage Cask, Inspection Report No. 07200010/2022201 IR 05000282/20220032022-11-0101 November 2022 Integrated Inspection Report 05000282/2022003 and 05000306/2022003 IR 05000282/20220112022-09-26026 September 2022 Phase 4 Post-Approval Site Inspection for License Renewal Report 05000282/2022011 and 05000306/2022011 IR 05000282/20223012022-08-31031 August 2022 NRC Initial License Examination Report 05000282/2022301; 05000306/2022301 IR 05000282/20220052022-08-29029 August 2022 Updated Inspection Plan for Prairie Island Nuclear Generating Plant (Report 05000282/2022005; 05000306/2022005) IR 05000282/20225012022-08-22022 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000282/2022501 and 05000306/2022501 ML22227A1902022-08-16016 August 2022 Island Nuclear Generating Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information: Inspection Report 05000282/2022004 ML22222A1732022-08-11011 August 2022 Integrated Inspection Report 05000282/2022002 and 05000306/2022002 IR 05000282/20220102022-06-24024 June 2022 Triennial Fire Protection Inspection Report 05000282/2022010 and 05000306/2022010 IR 05000282/20224022022-05-25025 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000282/2022402 05000306/2022402 IR 05000282/20224012022-05-23023 May 2022 Security Baseline Inspection Report 05000282/2022401 and 05000306/2022401 ML22103A2522022-05-0404 May 2022 Review of the 2021 Steam Generator Tube Inspection Report IR 05000282/20220012022-05-0303 May 2022 Integrated Inspection Report 05000282/2022001, 05000306/2022001, and 07200010/2020001 IR 05000282/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000282/2021006 and 05000306/2021006) IR 05000282/20210042022-02-11011 February 2022 Integrated Inspection Report 05000282/2021004 and 05000306/2021004 ML22017A0052022-01-17017 January 2022 (PINGP) 2021 Unit 2 180-Day Steam Generator Tube Inspection Report IR 05000282/20214032021-12-0202 December 2021 Security Baseline Inspection Report 05000282/2021403 and 05000306/2021403 IR 05000282/20210032021-11-12012 November 2021 Integrated Inspection Report 05000282/2021003 and 05000306/2021003 IR 05000282/20210122021-10-27027 October 2021 NRC Inspection Report 05000282/2021012 and 05000306/2021012 IR 05000282/20210052021-09-0101 September 2021 Updated Inspection Plan for Prairie Island Nuclear Generating Plant Units 1 and 2 (Report 05000282/2021005 and 05000306/2021005) IR 05000282/20215012021-08-25025 August 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000282/2021501 and 05000306/2021501 IR 05000282/20210022021-08-0606 August 2021 Integrated Inspection Report 05000282/2021002 and 05000306/2021002 IR 05000282/20214022021-07-28028 July 2021 Security Baseline Inspection Report 05000282/2021402 and 05000306/2021402 IR 05000282/20210102021-06-22022 June 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000282/2021010 and 05000306/2021010 IR 05000282/20210112021-06-0303 June 2021 Biennial Problem Identification and Resolution Inspection Report 05000282/2021011 and 05000306/2021011 IR 05000282/20210012021-05-0606 May 2021 Integrated Inspection Report 05000282/2021001 and 05000306/2021001 2024-09-13
[Table view] Category:Letter
MONTHYEARML24298A0552024-10-30030 October 2024 Response to Alternative RR-10, Auxiliary Feedwater Valve Testing IR 05000282/20244032024-10-25025 October 2024 – Security Baseline Inspection Report 05000282/2024403 and 05000306/2024403 05000282/LER-2024-001-01, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-10-22022 October 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies L-PI-24-044, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-10-21021 October 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML24277A1012024-10-0303 October 2024 Closure of Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software ML24221A3622024-09-27027 September 2024 Issuance of Amendment Nos. 245 and 233 Revise Technical Specification 3.8.1, AC Sources-Operating, Surveillance Requirement 3.8.1.2, Note 3 ML24241A1682024-09-23023 September 2024 Transmittal Letter Amendment No. 13 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation 05000282/LER-2024-001, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-09-16016 September 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies IR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) L-PI-24-040, Post-Submittal Package Letter2024-08-23023 August 2024 Post-Submittal Package Letter IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 ML24213A1592024-07-31031 July 2024 Operator Licensing Examination Approval - Prairie Island Nuclear Generating Plant IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 L-PI-24-036, – Preparation and Scheduling of Operator Licensing Examinations2024-06-28028 June 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24158A5912024-06-0606 June 2024 CFR 50.46 LOCA Annual Report L-PI-24-031, Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-06-0505 June 2024 Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption 05000306/LER-2024-001-01, Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump2024-05-31031 May 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24155A1922024-05-31031 May 2024 Refueling Outage Unit 2 R33 Owners Activity Report for Class 1, 2, 3 and Mc Inservice Inspections ML24262A1992024-05-29029 May 2024 L-PI-24-018 PINGP 75 Day Letter ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24128A2572024-05-16016 May 2024 ISFSI A13 Acceptance Letter IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 ML24130A2362024-05-0909 May 2024 Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Monitoring Program Report ML24130A2392024-05-0909 May 2024 2023 Annual Radioactive Effluent Report ML24071A1162024-05-0101 May 2024 Issuance of Amendment Nos. 244 and 232 Revise TS 3.7.8, Cooling Water (Cl) System ML24128A0882024-04-30030 April 2024 Submittal of Updated Safety Analysis Report (Usar), Revision 38 05000306/LER-2024-001, Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump2024-04-29029 April 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance IR 05000282/20244012024-04-25025 April 2024 – Security Baseline Inspection Report 05000282/2024401 and 05000306/2024401 ML24100A8042024-04-24024 April 2024 – Alternative Request RR-09 for Safety Injection and Volume Control System Category C Check Valve Inservice Testing ML24114A0882024-04-23023 April 2024 Annual Report of Individual Monitoring for the Prairie Island Nuclear Generating Plant (PINGP) ML24113A1182024-04-12012 April 2024 NRC Letter Re NRC Office of Investigations Report No. 3-2023-004 ML24100A1212024-04-0909 April 2024 Submittal of Revised Pressure and Temperature Limits Report ML24093A2832024-04-0202 April 2024 Nuclear Material Transaction Report L-PI-24-012, Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-04-0202 April 2024 Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) ML24089A2402024-03-29029 March 2024 Guarantee of Payment of Deferred Premiums ML24060A1232024-03-27027 March 2024 To Request 1-RR-5-10 and 2-RR-5-10 Regarding Reactor Pressure Vessel Welds and Nozzle Welds 05000282/LER-2023-001-01, Reactor Trip, Auxiliary Feedwater and Emergency Service Water System Actuation Due to Electrical Transient in DC Control Power Cables2024-03-21021 March 2024 Reactor Trip, Auxiliary Feedwater and Emergency Service Water System Actuation Due to Electrical Transient in DC Control Power Cables ML24262A1512024-03-15015 March 2024 L-PI-24-011 150 Day Letter 2024 PINGP ILT NRC Exam ML24010A0582024-03-0505 March 2024 Amendment No. 12 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation L-PI-24-004, Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 20232024-02-29029 February 2024 Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 2023 IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) 2024-09-27
[Table view] |
Text
gust 31, 2016
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 (REPORT 05000282/2016005; 05000306/2016005)
Dear Mr. Northard:
On August 10, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of [official plant name and applicable units]. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Prairie Island Plant Unit 1 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Prairie Island Plant Unit 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green).
Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The NRC determined the performance at Prairie Island Plant Unit 2 during the most recent quarter was within the Regulatory Response Column of the NRCs ROP Action Matrix because of one low-to-moderate (White) PI for Unplanned Scrams per 7000 critical hours. Therefore, in addition to ROP baseline inspections, the NRC will conduct a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area. On May 23, 2016, your staff notified the NRC of your readiness for this supplemental inspection. to review the actions taken to address the performance issues. Therefore, the NRC plans to perform Inspection Procedure 95001 beginning on September 12, 2016. This inspection procedure is conducted to provide assurance that the root cause and contributing cause of risk significant performance issues related to the Performance Indicator are understood, the extent of condition and the extent of cause are identified, and the corrective actions are sufficient to prevent recurrence. The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The NRC conducted audits of licensee efforts towards compliance with these Orders, and the information gathered will aid staff in development of the ultimate Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
In Staff Requirements Memorandum - SECY 16-0009, Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities, the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, Operating Reactor Assessment Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact Kenneth Riemer at 630-829-9628 with any questions you have regarding this letter.
Sincerely,
/RA/
Patrick L. Louden, Director Division of Reactor Projects Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60 Enclosure:
Inspection Plan cc: Distribution via LISTSERV