August 31, 2006 Mr. T. Palmisano Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
PRAIRIE ISLAND NUCLEAR GENERATING PLANT
Dear Mr. Palmisano:
On August 7, 2006, the NRC staff completed its performance review of the Prairie Island Nuclear Generating Plant for the first half of the calender year 2006 assessment cycle.
Our technical staff reviewed the performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.
Plant performance for the most recent quarter at the Prairie Island Nuclear Generating Plant Units 1 and 2 was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2008. Significant inspections planned include a Component Design Basis Inspection in May 2007, an Independent Spent Fuel Storage Installation (ISFSI)
Operation Inspection in June 2007, and a Modifications/50.59 Inspection in March 2008. In addition, the resident inspectors plan to perform Temporary Inspections 2515/166, Pressurized Water Reactor Containment Sump Blockage on Unit 2 and 2515/169, Mitigating Systems Performance Index (MSPI) Verification, before the end of calendar year 2006. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the end-of-cycle review.
T. Palmisano In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9620 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects Docket Nos. 50-282, 50-306 License No. DPR-42; DPR-60
Enclosure:
Prairie Island Nuclear Generating Plant Inspection/Activity Plan DISTRIBUTION:
See next page
T. Palmisano In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9620 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects Docket Nos. 50-282, 50-306 License No. DPR-42; DPR-60
Enclosure:
Prairie Island Nuclear Generating Plant Inspection/Activity Plan DISTRIBUTION:
See next page DOCUMENT NAME:G:\\Branch TSS\\ALL MOC\\midcycle 2005 to 2006\\prairie island\\Prairie Island 2006 MOC letter.wpd X Publicly Available G Non-Publicly Available G Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII NAME RSkokowski:dtp DATE 08/30/06 OFFICIAL RECORD COPY
T. Palmisano cc w/encl:
C. Anderson, Senior Vice President, Group Operations M. Sellman, Chief Executive Officer and Chief Nuclear Officer Regulatory Affairs Manager J. Rogoff, Vice President, Counsel & Secretary Nuclear Asset Manager State Liaison Officer, Minnesota Department of Health Tribal Council, Prairie Island Indian Community Administrator, Goodhue County Courthouse Commissioner, Minnesota Department of Commerce Manager, Environmental Protection Division Office of the Attorney General of Minnesota Council Administrator President, Prairie Island Tribal Council Goodhue County Sheriff Director, Pierce County Emergency Management Agency Chair, Pierce County Board of Commissioners Chair, Dakota County Board of Commissioners Mayor of Red Wing Director, Goodhue County Emergency Management Agency Chair, Goodhue County Board of Commissioners Pierce County Sheriff Dakota County Sheriff INPO
T. Palmisano ADAMS Distribution:
TEB MLC RidsNrrDirslpab JLC1 GEG KGO RML2 SRI Prairie Island DRPIII DRSIII PLB1 TXN
Prairie Island Inspection / Activity Plan 09/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/30/2006 13:03:10 Report 22 2
INSPECTI
- ISFSI INSPECTION Other Routine 08/01/2006 09/30/2006 1
60855.1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 1
ENF. F/U
- OPERATOR LICENSING FOLLOWUP - IR 2006013 Baseline Inspections 08/28/2006 09/29/2006 1, 2 7111111B IP Licensed Operator Requalification Program 1
BI
- RAD INSTRUMENTATION Baseline Inspections 09/11/2006 09/15/2006 1, 2 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 1
- PRAIRIE ISLAND UNIT 2 ISI INSPECTION Baseline Inspections 11/13/2006 12/01/2006 2
7111108P IP Inservice Inspection Activities - PWR 1
BI
- OUTAGE ALARA AND OCC RP Baseline Inspections 11/27/2006 12/01/2006 2
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 11/27/2006 12/01/2006 2
7112102 IP ALARA Planning and Controls 1
BI
- POST OUTAGE ALARA AND ACCESS CONTROL Baseline Inspections 01/29/2007 02/02/2007 1
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 01/29/2007 02/02/2007 1
7112102 IP ALARA Planning and Controls 1
EP BI
- BASELINE EP INSPECTION Baseline Inspections 04/09/2007 04/13/2007 1, 2 7111402 IP Alert and Notification System Testing Baseline Inspections 04/09/2007 04/13/2007 1, 2 7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 04/09/2007 04/13/2007 1, 2 7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 04/09/2007 04/13/2007 1, 2 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 04/09/2007 04/13/2007 1, 2 71151-EP02 IP ERO Drill Participation Baseline Inspections 04/09/2007 04/13/2007 1, 2 71151-EP03 IP Alert & Notification System 4
- COMPONENT DESIGN BASIS INSPECTION Baseline Inspections 05/14/2007 06/15/2007 2
7111121 IP Component Design Bases Inspection 1
- ISFSI INSPECTIONS Other Routine 06/01/2007 06/30/2007 1, 2 60855.1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 1
- REMP AND RAM CONTROL Baseline Inspections 06/25/2007 06/29/2007 1, 2 7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P Baseline Inspections 06/25/2007 06/29/2007 1, 2 71151 IP Performance Indicator Verification 1
HEATSINK
- HEAT SINK INSPECTION Baseline Inspections 06/25/2007 07/02/2007 1, 2 7111107B IP Heat Sink Performance 3
FY 2007
- PRAIRIE ISLAND INIT PREP 07/2007 Not Applicable 07/09/2007 07/13/2007 1
W90165 OL - INITIAL EXAM - PRAIRIE ISLAND - JUL/AUG 2007 3
FY 2007
- PRAIRIE ISLAND INIT EXAM 07&08/2007 Not Applicable 07/30/2007 08/10/2007 1
W90165 OL - INITIAL EXAM - PRAIRIE ISLAND - JUL/AUG 2007 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Prairie Island Inspection / Activity Plan 09/01/2006 - 03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/30/2006 13:03:10 Report 22 1
7112101
- ACCESS CONTROL AND ALARA Baseline Inspections 09/24/2007 09/28/2007 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/24/2007 09/28/2007 1, 2 7112102 IP ALARA Planning and Controls 2
- LIC OPERATOR REQUAL PROGRAM EVALUATION Baseline Inspections 10/15/2007 10/19/2007 1, 2 7111111B IP Licensed Operator Requalification Program 1
- TRANSPORTATION Baseline Inspections 12/03/2007 12/07/2007 1, 2 7112202 IP Radioactive Material Processing and Transportation 2
MOD/5059
- MODIFICATIONS/50.59 INSPECTION Baseline Inspections 03/03/2008 03/21/2008 1, 2 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 03/03/2008 03/21/2008 1, 2 7111117B IP Permanent Plant Modifications 1
MAIN
- MAINTENANCE EFFECTIVENESS INSPECTION Baseline Inspections 03/31/2008 04/04/2008 1, 2 7111112B IP Maintenance Effectiveness This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.