ML15292A013: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(4 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML15292A013
| number = ML15292A013
| issue date = 10/20/2015
| issue date = 10/20/2015
| title = Pilgrim Nuclear Power Station - ERO Staffing and Training Teleconference with NRC Staff
| title = ERO Staffing and Training Teleconference with NRC Staff
| author name =  
| author name =  
| author affiliation = Entergy Nuclear Generation Co
| author affiliation = Entergy Nuclear Generation Co
Line 13: Line 13:
| page count = 11
| page count = 11
}}
}}
=Text=
{{#Wiki_filter:Pilgrim Nuclear Power Station ERO Staffing and Training Teleconference with NRC Staff October 20, 2015 10/15/15 1400
Agenda
* Introduction of Participants
* Background and History
* Problem Statement
* Proposed Resolution
* Basis for Change
* Intended Actions
* NRC Staff Questions and Perspective
* Conclusions 2
Introduction of Participants
* NRC Staff
* Entergy - Pilgrim 3
Background and History
* July 14, 2006 letter from Entergy to NRC Staff o ERO substitution: Chem Tech for RP Tech o Training for Chem Techs described
* Feb 5, 2007 letter from NRC Staff to Entergy o Change does not decrease effectiveness of plan o No NRC approval necessary
* 2015: Entergy determined Chem Tech training not consistent with July 14, 2006 letter
* Immediate actions; RP Tech added back to shifts; 4
Problem Statement
* Level of training for Chem Techs acting for RP Techs described in July 14, 2006 letter exceeds actual requirements of the ERO function.
5
July 14, 2006 Letter: Chem Tech Training 6
Proposed Resolution
* Entergy proposal:
o Return to onshift Chem Techs fulfilling the RP Tech ERO function for first 30 minutes of ERO initiation o Reduce the scope of Chem Tech training o Submittal to NRC for review and approval prior to implementation
* Entergy has concluded this change is acceptable 7
Basis for Change
* Reduced level of training - consistent with limited specific actions of the Chem Techs within 30 minutes
* Specific on-shift staffing study supports limited scope of responsibilities of Chem Tech for RP Techs
* OE review identified similar implementations
* February 5, 2007 NRC Staff letter concluded:
o Previous Entergy proposal met requirements of:
10CFR50.47(b)(2) - adequate staffing provided 10CFR50, App E, IV.A - organization for coping o Chem Tech training considered an enhancement o No decrease in effectiveness / no NRC approval required 8
Intended Actions
* Conference call with NRC Staff
* Preparation and submittal of request for prior NRC Staff review and approval
* Revise training
* Revise ERO staffing 9
NRC Staff Questions and Perspective 10
Conclusions
* Proposed change in Chemistry Technician is appropriate based on ERO assignments
* Proposed change is justified by staffing study
* Entergy intends on submitting the proposed change for prior NRC review and approval 11
Pilgrim Nuclear Power Station ERO Staffing and Training Teleconference with NRC Staff October 20, 2015 10/15/15 1400
Agenda
* Introduction of Participants
* Background and History
* Problem Statement
* Proposed Resolution
* Basis for Change
* Intended Actions
* NRC Staff Questions and Perspective
* Conclusions 2
Introduction of Participants
* NRC Staff
* Entergy - Pilgrim 3
Background and History
* July 14, 2006 letter from Entergy to NRC Staff o ERO substitution: Chem Tech for RP Tech o Training for Chem Techs described
* Feb 5, 2007 letter from NRC Staff to Entergy o Change does not decrease effectiveness of plan o No NRC approval necessary
* 2015: Entergy determined Chem Tech training not consistent with July 14, 2006 letter
* Immediate actions; RP Tech added back to shifts; 4
Problem Statement
* Level of training for Chem Techs acting for RP Techs described in July 14, 2006 letter exceeds actual requirements of the ERO function.
5
July 14, 2006 Letter: Chem Tech Training 6
Proposed Resolution
* Entergy proposal:
o Return to onshift Chem Techs fulfilling the RP Tech ERO function for first 30 minutes of ERO initiation o Reduce the scope of Chem Tech training o Submittal to NRC for review and approval prior to implementation
* Entergy has concluded this change is acceptable 7
Basis for Change
* Reduced level of training - consistent with limited specific actions of the Chem Techs within 30 minutes
* Specific on-shift staffing study supports limited scope of responsibilities of Chem Tech for RP Techs
* OE review identified similar implementations
* February 5, 2007 NRC Staff letter concluded:
o Previous Entergy proposal met requirements of:
10CFR50.47(b)(2) - adequate staffing provided 10CFR50, App E, IV.A - organization for coping o Chem Tech training considered an enhancement o No decrease in effectiveness / no NRC approval required 8
Intended Actions
* Conference call with NRC Staff
* Preparation and submittal of request for prior NRC Staff review and approval
* Revise training
* Revise ERO staffing 9
NRC Staff Questions and Perspective 10
Conclusions
* Proposed change in Chemistry Technician is appropriate based on ERO assignments
* Proposed change is justified by staffing study
* Entergy intends on submitting the proposed change for prior NRC review and approval 11}}

Latest revision as of 06:33, 31 October 2019

ERO Staffing and Training Teleconference with NRC Staff
ML15292A013
Person / Time
Site: Pilgrim
Issue date: 10/20/2015
From:
Entergy Nuclear Generation Co
To:
Office of Nuclear Reactor Regulation
Venkataraman B
References
Download: ML15292A013 (11)


Text

Pilgrim Nuclear Power Station ERO Staffing and Training Teleconference with NRC Staff October 20, 2015 10/15/15 1400

Agenda

  • Introduction of Participants
  • Background and History
  • Problem Statement
  • Proposed Resolution
  • Basis for Change
  • Intended Actions
  • NRC Staff Questions and Perspective
  • Conclusions 2

Introduction of Participants

  • NRC Staff
  • Entergy - Pilgrim 3

Background and History

  • July 14, 2006 letter from Entergy to NRC Staff o ERO substitution: Chem Tech for RP Tech o Training for Chem Techs described
  • Feb 5, 2007 letter from NRC Staff to Entergy o Change does not decrease effectiveness of plan o No NRC approval necessary
  • 2015: Entergy determined Chem Tech training not consistent with July 14, 2006 letter
  • Immediate actions; RP Tech added back to shifts; 4

Problem Statement

  • Level of training for Chem Techs acting for RP Techs described in July 14, 2006 letter exceeds actual requirements of the ERO function.

5

July 14, 2006 Letter: Chem Tech Training 6

Proposed Resolution

  • Entergy proposal:

o Return to onshift Chem Techs fulfilling the RP Tech ERO function for first 30 minutes of ERO initiation o Reduce the scope of Chem Tech training o Submittal to NRC for review and approval prior to implementation

  • Entergy has concluded this change is acceptable 7

Basis for Change

  • Reduced level of training - consistent with limited specific actions of the Chem Techs within 30 minutes
  • Specific on-shift staffing study supports limited scope of responsibilities of Chem Tech for RP Techs
  • OE review identified similar implementations
  • February 5, 2007 NRC Staff letter concluded:

o Previous Entergy proposal met requirements of:

10CFR50.47(b)(2) - adequate staffing provided 10CFR50, App E, IV.A - organization for coping o Chem Tech training considered an enhancement o No decrease in effectiveness / no NRC approval required 8

Intended Actions

  • Conference call with NRC Staff
  • Preparation and submittal of request for prior NRC Staff review and approval
  • Revise training
  • Revise ERO staffing 9

NRC Staff Questions and Perspective 10

Conclusions

  • Proposed change in Chemistry Technician is appropriate based on ERO assignments
  • Proposed change is justified by staffing study
  • Entergy intends on submitting the proposed change for prior NRC review and approval 11

Pilgrim Nuclear Power Station ERO Staffing and Training Teleconference with NRC Staff October 20, 2015 10/15/15 1400

Agenda

  • Introduction of Participants
  • Background and History
  • Problem Statement
  • Proposed Resolution
  • Basis for Change
  • Intended Actions
  • NRC Staff Questions and Perspective
  • Conclusions 2

Introduction of Participants

  • NRC Staff
  • Entergy - Pilgrim 3

Background and History

  • July 14, 2006 letter from Entergy to NRC Staff o ERO substitution: Chem Tech for RP Tech o Training for Chem Techs described
  • Feb 5, 2007 letter from NRC Staff to Entergy o Change does not decrease effectiveness of plan o No NRC approval necessary
  • 2015: Entergy determined Chem Tech training not consistent with July 14, 2006 letter
  • Immediate actions; RP Tech added back to shifts; 4

Problem Statement

  • Level of training for Chem Techs acting for RP Techs described in July 14, 2006 letter exceeds actual requirements of the ERO function.

5

July 14, 2006 Letter: Chem Tech Training 6

Proposed Resolution

  • Entergy proposal:

o Return to onshift Chem Techs fulfilling the RP Tech ERO function for first 30 minutes of ERO initiation o Reduce the scope of Chem Tech training o Submittal to NRC for review and approval prior to implementation

  • Entergy has concluded this change is acceptable 7

Basis for Change

  • Reduced level of training - consistent with limited specific actions of the Chem Techs within 30 minutes
  • Specific on-shift staffing study supports limited scope of responsibilities of Chem Tech for RP Techs
  • OE review identified similar implementations
  • February 5, 2007 NRC Staff letter concluded:

o Previous Entergy proposal met requirements of:

10CFR50.47(b)(2) - adequate staffing provided 10CFR50, App E, IV.A - organization for coping o Chem Tech training considered an enhancement o No decrease in effectiveness / no NRC approval required 8

Intended Actions

  • Conference call with NRC Staff
  • Preparation and submittal of request for prior NRC Staff review and approval
  • Revise training
  • Revise ERO staffing 9

NRC Staff Questions and Perspective 10

Conclusions

  • Proposed change in Chemistry Technician is appropriate based on ERO assignments
  • Proposed change is justified by staffing study
  • Entergy intends on submitting the proposed change for prior NRC review and approval 11