MONTHYEARML23113A0232023-04-11011 April 2023 NRC Presentation: Overview of Pilgrim Liquid Discharge Considerations for the North Atlantic Right Whale Recovery Plan Northeast U.S. Implementation Team (Neit) ML22227A0742022-08-10010 August 2022 Overview of Pilgrim Liquid Discharge Considerations NOAA ML22124A3012022-04-25025 April 2022 Dialog Presentation for Mashpee Wampanoag Tribe Regarding Pilgrim Liquid Effluent Discharges, April 25, 2022 ML20045D1092020-01-31031 January 2020 PSP Pre-Submittal Meeting Jan 31 2020 Hdi ML19248C2392019-09-11011 September 2019 NEIMA Section 108 Public Meeting Slides - Pilgrim September 11, 2019 ML19119A0882019-04-29029 April 2019 Annual Assessment Meeting for Pilgrim Nuclear Power Station - NRC Presentation Slides ML19009A3432019-01-15015 January 2019 Holtec Slides PSDAR Meeting 1-15-19 ML19009A1712019-01-15015 January 2019 Post-Shutdown Decommissioning Activities Report, NRC Public Meeting January 15, 2019 ML19008A4942019-01-15015 January 2019 Post-Shutdown Decommissioning Activities Report - NRC Presentation at Public Meeting on January 15, 2019 ML18262A1352018-09-25025 September 2018 NRC License Transfer Application 9/25/2018 Pre-Submittal Meeting Presentation Slides ML18127A0282018-05-0707 May 2018 Annual Assessment Meeting for Pilgrim Nuclear Power Station - Entergy Presentation Slides ML18127A0272018-05-0707 May 2018 Annual Assessment Meeting for Pilgrim Nuclear Power Station - NRC Presentation Slides ML18107A3342018-04-10010 April 2018 Tech Spec 3.3.5.2a Change Pre-Submittal Meeting Presentation Slides ML17296A2162017-10-18018 October 2017 Presentations on Reactor Decommissioning at Ma Ndcap at Plymouth Ma Public Meeting Oct 18, 2017 ML17166A2892017-06-20020 June 2017 Entergy Slides for 06/20/2017 Public Meeting, Licensing Action Submittal Plan - Decommissioning. ML17150A0012017-06-20020 June 2017 6/20/2017 Meeting Slides - Entergy Nuclear Operations, Inc. - Licensing Action Submittal Plan - Decommissioning (CAC Nos. MF9624, MF9625, MF9626, MF9627, and MF9628) ML17086A3802017-03-21021 March 2017 3/21/2017 - Annual Assessment & IP 95003 Exit Meeting for Pilgrim Nuclear Power Station - NRC Presentation Slides ML17086A3882017-03-21021 March 2017 3/21/2017 - Annual Assessment & 95003 Exit Meeting for Pilgrim Nuclear Power Station - Entergy Presentation Slides ML16112A1562016-04-13013 April 2016 4/13/2016 - Pilgrim Nuclear Power Station Annual Assessment Meeting - Entergy Presentation Slides ML16111A8892016-04-13013 April 2016 4/13/2016 - Pilgrim Nuclear Power Station Annual Assessment Meeting - NRC Presentation Slides ML15292A0132015-10-20020 October 2015 ERO Staffing and Training Teleconference with NRC Staff ML15208A4602015-07-0808 July 2015 Slides of Regulatory Conference for July 8, 2015 ML15084A0532015-03-18018 March 2015 3/18/2015 - Pilgrim 2014 Annual Assessment Meeting - NRC Presentation (w/95002 Inspection Results) ML14136A3502014-05-14014 May 2014 Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station on 5/1/2014 (W/Nrc Presentation Slides) ML14015A1702013-12-12012 December 2013 Pilgrim Dry Cask Presentation - Dec. 12, 2013 ML14006A2732013-12-12012 December 2013 NRC Webinar Dry Cask Storage of Nuclear Fuel at Pilgrim Nuclear Power Plant ML13130A1542013-05-10010 May 2013 Slides for ISFSI Briefing for Town of Plymouth ML13130A1232013-05-10010 May 2013 2012 Annual Assessment Meeting Slides ML12101A2852012-04-10010 April 2012 Annual Assessment Meeting Slides ML11188A0192011-07-0606 July 2011 NRC Meeting with NEI Workshop June 28-29, 2011 Enhancements ML1117906392011-06-28028 June 2011 Summary of Meeting with Entergy Operations Inc ML1009900312010-04-13013 April 2010 Entergy Nuclear Operations (Entergy): Meeting Presentation 2009 Nuclear Safety Culture Assessment Meeting ML0906906982009-03-20020 March 2009 NRC Presentation Slides for Pilgrim Nuclear Power Plant Annual Assessment Meeting to Be Held 3/26/09 ML0809403832008-03-26026 March 2008 Attendance List for Pilgrim Annual Assessment Meeting ML0731902202007-11-0707 November 2007 Meeting Handout Fitzpatrick GNF2 Introduction at Entergy ML0726400222007-09-0606 September 2007 License Renewal ACRS Full Committee Brief of September 6, 2007 ML0712807662007-04-26026 April 2007 E-mail: (NPA-PD) Link to Rutgers Slides on Wrf Calcs - Pilgrim ML0705106742007-02-21021 February 2007 NMC Slides for Public Meeting, Conduct of Operations Action Plan Update. ML0704403232007-01-30030 January 2007 License Renewal Inspection Exit Meeting Slides ML0715700492007-01-16016 January 2007 Budget Presentation,Town of Plymouth Fiscal Year 2008 Budget Primer. ML0614201642006-05-17017 May 2006 Pilgrim Nuclear Power Station Environmental Scoping Meeting Handouts ML0507500022005-03-16016 March 2005 NRC Slides - Pilgrim Annual Assessment Meeting ML0309001032003-03-26026 March 2003 Annual Assessment Meeting Slides ML0225302662002-09-0909 September 2002 Attachment 2 to Summary of 07/24/2002 Meeting with Entergy Nuclear Operations, Inc., Regarding Pilgrim Nuclear Power Station Proposed Safety-Relief Valve Seismic Analysis Methodology ML0210802402002-03-28028 March 2002 Annual Assessment Meeting Slides ML0212004532002-03-28028 March 2002 Entergy Nuclear Generation Company - Pilgrim Nuclear Power Station Annual Assessment Meeting Slides ML17252A1571977-09-14014 September 1977 Summary of Meeting Held with Representatives of the Mark I Owner'S Group to Discuss the Structural Acceptance Criteria for the Mark I Containment Long Term Program 2023-04-11
[Table view] Category:Slides and Viewgraphs
MONTHYEARML23113A0232023-04-11011 April 2023 NRC Presentation: Overview of Pilgrim Liquid Discharge Considerations for the North Atlantic Right Whale Recovery Plan Northeast U.S. Implementation Team (Neit) ML22227A0742022-08-10010 August 2022 Overview of Pilgrim Liquid Discharge Considerations NOAA ML22124A3012022-04-25025 April 2022 Dialog Presentation for Mashpee Wampanoag Tribe Regarding Pilgrim Liquid Effluent Discharges, April 25, 2022 ML22088A2172022-03-16016 March 2022 Liquid Effluent Discharge Presentation ML20045D1092020-01-31031 January 2020 PSP Pre-Submittal Meeting Jan 31 2020 Hdi ML19248C2392019-09-11011 September 2019 NEIMA Section 108 Public Meeting Slides - Pilgrim September 11, 2019 ML19119A0882019-04-29029 April 2019 Annual Assessment Meeting for Pilgrim Nuclear Power Station - NRC Presentation Slides ML19009A3432019-01-15015 January 2019 Holtec Slides PSDAR Meeting 1-15-19 ML19008A4942019-01-15015 January 2019 Post-Shutdown Decommissioning Activities Report - NRC Presentation at Public Meeting on January 15, 2019 ML18262A1352018-09-25025 September 2018 NRC License Transfer Application 9/25/2018 Pre-Submittal Meeting Presentation Slides ML18127A0282018-05-0707 May 2018 Annual Assessment Meeting for Pilgrim Nuclear Power Station - Entergy Presentation Slides ML18127A0272018-05-0707 May 2018 Annual Assessment Meeting for Pilgrim Nuclear Power Station - NRC Presentation Slides ML18107A3342018-04-10010 April 2018 Tech Spec 3.3.5.2a Change Pre-Submittal Meeting Presentation Slides ML18075A1232018-03-20020 March 2018 Entergy Nuclear Operations - March 20, 2018, Presentation Slides for Surveillance Frequency Control Program, UFSAR Change Considerations ML17296A2162017-10-18018 October 2017 Presentations on Reactor Decommissioning at Ma Ndcap at Plymouth Ma Public Meeting Oct 18, 2017 ML17191A7872017-07-13013 July 2017 Regulatory Conference Presentation 07-13-17 ML17086A3802017-03-21021 March 2017 3/21/2017 - Annual Assessment & IP 95003 Exit Meeting for Pilgrim Nuclear Power Station - NRC Presentation Slides ML17086A3882017-03-21021 March 2017 3/21/2017 - Annual Assessment & 95003 Exit Meeting for Pilgrim Nuclear Power Station - Entergy Presentation Slides ML16112A1562016-04-13013 April 2016 4/13/2016 - Pilgrim Nuclear Power Station Annual Assessment Meeting - Entergy Presentation Slides ML16111A8892016-04-13013 April 2016 4/13/2016 - Pilgrim Nuclear Power Station Annual Assessment Meeting - NRC Presentation Slides ML15292A0132015-10-20020 October 2015 ERO Staffing and Training Teleconference with NRC Staff ML15208A4602015-07-0808 July 2015 Slides of Regulatory Conference for July 8, 2015 ML15084A0532015-03-18018 March 2015 3/18/2015 - Pilgrim 2014 Annual Assessment Meeting - NRC Presentation (w/95002 Inspection Results) ML14136A3502014-05-14014 May 2014 Summary of Annual Assessment Meeting for Pilgrim Nuclear Power Station on 5/1/2014 (W/Nrc Presentation Slides) ML14015A1702013-12-12012 December 2013 Pilgrim Dry Cask Presentation - Dec. 12, 2013 ML14006A2732013-12-12012 December 2013 NRC Webinar Dry Cask Storage of Nuclear Fuel at Pilgrim Nuclear Power Plant ML13130A1542013-05-10010 May 2013 Slides for ISFSI Briefing for Town of Plymouth ML13130A1232013-05-10010 May 2013 2012 Annual Assessment Meeting Slides ML12262A3282012-09-13013 September 2012 9/13/2012 Pilgrim Watch Final Presentation NUREG-0654 Public Mtg ML12101A2852012-04-10010 April 2012 Annual Assessment Meeting Slides ML11188A0192011-07-0606 July 2011 NRC Meeting with NEI Workshop June 28-29, 2011 Enhancements ML1118105122011-06-30030 June 2011 Aam Slides ML0909702992009-04-13013 April 2009 Annual Assessment Meeting Summary, Slides, Sign-in Sheet, Misc Documents, for 3/26/09 Meeting ML0906906982009-03-20020 March 2009 NRC Presentation Slides for Pilgrim Nuclear Power Plant Annual Assessment Meeting to Be Held 3/26/09 ML0807011352008-03-10010 March 2008 Slides for the Pilgrim Station Annual Assessment Meeting CY2007 - ROP8 - 03/26/2008 ML0731902202007-11-0707 November 2007 Meeting Handout Fitzpatrick GNF2 Introduction at Entergy ML0726400222007-09-0606 September 2007 License Renewal ACRS Full Committee Brief of September 6, 2007 ML0712807662007-04-26026 April 2007 E-mail: (NPA-PD) Link to Rutgers Slides on Wrf Calcs - Pilgrim ML0710102652007-04-11011 April 2007 Slides for 2006 Annual Assessment Meeting, NRC Annual Performance Assessment of Pilgrim ML0705106742007-02-21021 February 2007 NMC Slides for Public Meeting, Conduct of Operations Action Plan Update. ML0704403232007-01-30030 January 2007 License Renewal Inspection Exit Meeting Slides ML0704304762007-01-30030 January 2007 License Renewal Inspection Exit Meeting - Slides with Notes ML0703305622007-01-24024 January 2007 Dseis Meeting Presentation, Preliminary Results of Environmental Review Pilgrim Nuclear Power Station ML0715700492007-01-16016 January 2007 Budget Presentation,Town of Plymouth Fiscal Year 2008 Budget Primer. ML0634800262006-12-0606 December 2006 Drop-In Visit (Entergy) Slides ML0609404082006-04-0404 April 2006 NRC Slides for Annual Assessment Public Meeting with Entergy (Pilgrim Station) Reference CY2005 Performance ML0617802712006-03-0707 March 2006 RIC 2006 Presentation - T2E - Vincent Coulehan - Use of Operating Experience (Regulator/Operator/Licensee) ML0615902322006-03-0707 March 2006 2006/03/07- - RIC 2006 Presentation - T1F - Garry G. Young - License Renewal ML0615901582006-03-0707 March 2006 03/07/2006 - RIC 2006 Presentation - T1E - John F. Mccann - License Renewal ML0632802522005-07-18018 July 2005 Briefing Slides for 07/18/2005, Pilgrim Station Force-on-Force Inspection 2023-04-11
[Table view] |
Text
Overview of Reactor Decommissioning Pilgrim Nuclear Decommissioning Citizens Advisory Panel Briefing Bruce A. Watson, CHP Chief, Reactor Decommissioning Branch October 18, 2017
NRCs Mission
- NRCs mission is to ensure plant safety, whether the plant is operating, or transitioning from operating to decommissioning, and through the entire process until the plant has been radiologically decommissioned and the license is terminated.
Present Status
- 6 Power Plants in active decommissioning
- 14 Power Plants in SAFSTOR
- 8 announced and more shutdowns are anticipated 2
Reactor Decommissioning
- Decommissioning Experience
- Decommissioning Topics of High Public Interest
Decommissioning Experience
- Current 1997 Decommissioning Regulations are performance-based and risk-informed
- Extensive Decommissioning Experience
- A total of 10 Power Reactor sites have completed decommissioning, had the reactor license terminated and released for unrestricted use 12 10 8
6 4
2 0
Power Reactors Research Reactors Materials Sites 4
Power Reactor Decommissioning
- Notification of Intent to Permanently Shutdown
- Submission of Certifications of Permanent Shutdown and Permanent Removal of Fuel from Reactor Vessel
- Submittal of Post Shutdown Decommissioning Activities Report (PSDAR) and NRC Public Meeting
- Decommissioning must be completed within 60 years of permanent cessation of operations.
- License Termination Plan is submitted 2 years prior to requesting license termination and NRC Public Meeting
- NRC terminates the license by letter 5
Reactor Decommissioning Process Phase 1
- Reactor is permanently shutdown and nuclear fuel is transferred to the spent fuel pool
- Plant is prepared for decommissioning
- Modifications are typically made to facilitate decommissioning 6
Reactor Decommissioning Process Phase 1 (Continued)
Post Shutdown Decommissioning Activities Report (PSDAR) (Regulatory Guide 1.185)
- Decommissioning Strategy - DECON or SAFSTOR - 60 years to complete decommissioning
- Site Decommissioning Funding Status
- Affirmation of the Environmental Review NRC holds Public Meeting for comments NRC does not approve the PSDAR 7
Reactor Decommissioning Process Phase 2 - Decommissioning Phase
- DECON - immediate dismantlement
- SAFSTOR - deferred dismantlement
- 60 years to complete (50 years for radioactive decay + 10 years to dismantle)
Phase 3 - last 2 years
- License Termination Plan (License Amendment)
- NRC holds a Public Meeting 8
Reactor Decommissioning Inspection Program
- Continues until the license is terminated
- ~ 40 Inspection procedures
- Minimum Annual Inspection - 12 Core procedures are required each year
- Resident Inspector up to 1 year after shutdown, but can be extended
- Inspection Reports are publically available 9
Rancho Seco - 2009 10
Big Rock Point - 2007 11
Maine Yankee - 2005 12
Connecticut Yankee - 2007 13
Decommissioning Topics of High Public Interest
- Economic losses to the local community
- Community Involvement - Advisory Groups
- Independent Spent Fuel Storage Installations (ISFSI),Time in Storage and Transportation
- Reactor Decommissioning - 60 years to complete
- Decommissioning Fund Adequacy
- Decommissioning License Transfers 14
Yankee Rowe - 2007 15
Worcester Polytechnic Research Reactor - 2013 16
Summary
- NRCs mission is to ensure plant safety, whether the plant is operating, or transitioning from operating to decommissioning, and through the entire process until the plant has been radiologically decommissioned and the license is terminated.
Present Status
- 6 Power Plants in active decommissioning
- 14 Power Plants in SAFSTOR
- More shutdowns are anticipated 17
Transitioning from Operation to Decommissioning
- Permanently Defueled Technical Specifications
- Revised Emergency Plan and Emergency Action Level Scheme
- Exemptions from Title 10 Code of Federal Regulations
- Emergency Preparedness (Part 50, Appendix E)
- Security Plan and Procedures (CFR Part 73)
- Decommissioning Trust Fund (CFR 50.82)
- Insurance and Financial Protection (CFR 50.54 and Part 140)
- Requests to Rescind or Relax Orders
- Certified Fuel Handler Training Program
- NRC to issue lessons learned report with emphasis on decommissioning licensing and oversight activities 18
Reasonable Assurance of Decommissioning Funding
- Initial Certification of Financial Assurance.
- Maintains the NRC Minimum Funding Amount throughout the life of the reactor.
- Uses one or more funding methods specified in the regulation.
- Monitoring and Updating of Decommissioning Funding -
Operating Licensee provides Decommissioning Fund Status Report to the NRC (every 2 years).
Licensee must Provide SSCE 5 years prior to permanent cessation of operations & in PSDAR.
Reviewed Annually in decommissioning 19