NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (9-1999)

TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed or hand-printed)by the person who announcedthe meeting (i.e., the person who issued the meeting notice). The completed form, and the attached copy of meeting handout materials, will be sent to the Document Control Desk on the same day of the meeting; under no circumstances will this be done laterthan the working day after the meeting.

Do not include proprietarymaterials.

DATE OF MEETING The attached document(s), which was/were handed out in this meeting, is/are to be placed 03/28/2002 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting:

Docket Number(s) 05000293 Plant/Facility Name Pilgrim Nuclear Power Station TAC Number(s) (ifavailable)

Reference Meeting Notice 02-015 Purpose of Meeting (copy from meeting notice) Management meeting with Entergy to discuss the results of the NRC's assessment of the safety performance at Pilgrim station for 4/1 - 12/31/01.

NAME OF PERSON WHO ISSUED MEETING NOTICE TITLE Clifford J. Anderson Chief OFFICE Region I DIVISION Division of Reactor Projects BRANCH Projects Branch 5 Distribution of this form and attachments:

Docket File/Central File PUBLIC NRC FORM 658 (9-1999) PRINTED ON RECYCLED PAPER This form was designed using InForms

m l--

Entergy Pilgrim Nuclear Power Station Annual Assessment Meeting March 28, 2002

Agenda

  • 2001 Accomplishments
  • Plant Focus Areas

- Work Management

- Equipment Reliability

-Human Performance

.*Specific Topics

- Security

- Reactor Water Level Indication

  • Occupational Radiation Dose
  • Plant Performance Index

° Industrial Safety

  • Reactor Water Chemistry

° Refueling Outage

S°0 l1 Co CD h 2

Focus Area Goal

"* Improve plant safety by improving equipment reliability

"* Improve plant material condition

"* Improve the timeliness of maintenance

  • Raise standards for plant material condition

Actions Taken

"* Developed Excellence Plan

"* Increased staffing

"* Implemented process changes

  • Developed targets (goals)

Status/Plans

° All NRC Indicators in the "Green" band

  • Improving safety system performance

- High Pressure Coolant Injection

- Reactor Core Isolation Cooling

- Residual Heat Removal

- Emergency AC Power

m Cr

Focus Area Goal

"* Improve plant safety by improving equipment reliability

"* Improve Preventive and Predictive Maintenance

"* Reduce Operation and Maintenance costs

Actions Taken

"* Developed Excellence Plan

"* Formed equipment reliability group

"* Performed System Health Reviews

"* Implemented Equipment Reliability Process

"* Implemented Preventive Maintenance feedback

Status/Plans

° Improved performance in several systems

  • Develop additional equipment reliability guidance
  • Improve critical component identification
  • Optimize Preventive Maintenance for critical components

I CD 0-U' 2

Focus Area Goal

° Improve plant safety by improving human performance

° Enhance the culture to recognize that people make mistakes and put in place barriers to:

- Reduce Human Errors

- Prevent Events

Actions Taken

  • Developed Excellence Plan
  • Developed human performance training for all station personnel
  • Implemented coaching process
  • Implemented fact-finding for all human performance errors
  • Utilizing a blame free policy for human performance issues

Status/Plans

° Continuing Human Performance Fundamentals Training - >90% complete

° Providing additional tool usage training

  • Established coaching goals for management team
  • Integrating human performance into all phases of accredited discipline training

° Decreased Station error rate

Security a tergy

Actions Taken

  • Implemented enhanced security procedures
  • Enhanced coordination with intelligence and law enforcement agencies
  • Re-evaluated security, emergency planning and operating procedures
  • Working to implement the new NRC Security Order

Water Level Indication

Background

  • Three events
  • Different causes

-Air Injection

- Reverse Flow

- Non-condensable gas

Corrective Actions Taken

"* Established review teams

"* Implemented procedure changes, design changes, and improved training

"* Performed independent review

Issue Resolution

° Short-term Issue Resolution Established continuous backfill of the "B" reference leg and periodic backfill of the "A" reference leg

  • Long-term Issue Resolution Further plant modifications to address issue