Memo to File: April 29, 2019 Attached are NRC slides presented at the Annual Assessment Meeting for Pilgrim Nuclear Power Station held on March 26, 2019.
1 Pilgrim 2018 Annual Assessment Meeting March 26, 2019 1
Agenda
- Introduction
- Discussion of NRC Oversight Results
- Public Q&A
- NRC Closing Remarks 2
2 Performance Improvement Highlights
- Pilgrim operated safely in 2018
- Marked improvement in Safety Culture
- Pilgrim successfully met all CAL commitments
- No greater than green performance indicators
- No greater than green inspection findings 3
Progression of Performance
- 2015: NRC placed Pilgrim in Column 4
- 2016: NRC completed supplemental inspections and issued the CAL
- 2017: Progress observed but sustained improvement not yet demonstrated 4
3 Performance Improvement Sustained in 2018
- Entergy corrected all Column 4 Action Matrix inputs
- Inspections confirmed that all CAL actions were complete and effective
- All findings and performance indicators are Green 5
Pilgrim Addressed Underlying Causes
- Marked improvement in safety culture
- More effective and timely corrective actions
- Improved risk recognition and conservative decision-making
- Significant reduction in human performance events 6
4 Pilgrim Returned to Column 1
- NRC concluded that Entergy has addressed all causes of degraded performance at Pilgrim
- Pilgrim demonstrated sustained improvement in 2018
- NRC oversight will continue at Pilgrim through decommissioning 7
NRC Will Continue Rigorous Oversight at Pilgrim
- Inspections will continue with a strong focus on safety and security
- Maintain strong oversight through shutdown, Decommissioning and fuel storage 8
5 Pilgrim 2018 Annual Assessment Meeting 9
Questions and Answers Pilgrim 2018 Annual Assessment Meeting 10 NRC Closing Remarks