{{#Wiki_filter:Omaha Public Power District (OPPD)Fort Calhoun Station (FCS) DecommissioningOctober 18, 2016 FCS Decommissioning Team2Mary Fisher -Sr. Dir. FCS DecommissioningBrad Blome-Mgr. Site Regulatory AssuranceHerb Childs -Mgr. Site SecurityTed Maine -Mgr. Radiation ProtectionTim Uehling-Mgr. Site TrainingAlso present: David Daigle ENERCON, Emergency Preparedness Specialist Background3OPPD is a publicly-owned electric utility and is a political subdivision of the state of NebraskaGoverned by a publicly elected Board of DirectorsOn 5/12/16, OPPD management recommended ceasing FCS operations to the Board of DirectorsOn 6/16/16, OPPD Board of Directors voted and approved ceasing FCS operations and going to SAFSTOR Initial NRC Submittals4Initial certification to Permanently Cease Operations by 12/31/16 submitted on 6/24/16Updated certification submitted on 8/25/16, FCS will Permanently Cease Operations on 10/24/16Certification of Permanent Removal of Fuel from the Reactor Vessel will be submitted in November 2016 Decommissioning Approach5Multidisciplinary teams supplemented with several vendors with decommissioning experienceBenchmarking Trips to Crystal River, Vermont Yankee, Zion, Kewaunee; future trips plannedIndustry decommissioning groupsNuclear Energy Institute (NEI) Decommissioning Transition TeamIndustry Regulatory Assurance (RA) Decommissioning Users GroupEmergency Planning Decommissioning Users GroupDecommissioning Oversight Committee Key SAFSTOR Decision Points6Decommissioning FundsPossible Decommissioning Services Agreement fourth quarter 2016Independent Spent Fuel Storage Installation (ISFSI) timeline and vendor selection for additional casks second quarter 2017Evaluate SAFSTOR/DECON timelines AllSpent FuelOn ISFSIRev 1 10/13/16SHUTDOWNOct 24, 2016Fort Calhoun SAFSTOR TimelineDecom costUpdate to NRCONLINE3Q161Q172Q173Q174Q173Q194Q192Q213Q214Q161Q183Q184Q181Q192Q191Q211Q202Q203Q204Q202Q18Plant in SAFSTORYEAR20162017201820192020202120224Q212Q223Q221Q22Submit  Letter(s)-Cease Operations-Permanent DefueledPSDAR/DCESubmittal~03/31/17PDTSIssued4Q221Q23ISFSI CampaignISFSI Only Tech SpecsIssuedDecom costUpdate to NRCDecom costUpdate to NRCDecom costUpdate to NRCDecom costUpdate to NRC20233Q161Q172Q173Q174Q173Q194Q192Q213Q214Q161Q183Q184Q181Q192Q192Q181Q211Q202Q203Q204Q204Q212Q223Q221Q224Q221Q23End ZircFire Period17 monthsEvaluate SFP Cooling MODMODIFICATIONSENG/PROGRAMSSECURITY PLANORGANIZATIONCHANGESUSAR  and Accident AnalysisTech Specs ODCMRevise Security Plan(Defueled)Chapter 14 USAR updateRemaining USAR UpdatePri Sys AbandonmentDeveloped by DECOM TeamNote:This Color Graphic is a communication tool only. It is not a controlled document or schedule and subject to change.Prepare/Submit PDTSDetermine Engineering Programsrequired/not requiredPrepare/issue ODCMRevise ERO Plan(PSEP/PDEP)Change MGMTPlans-ImplementFHA Analysis System ReclassificationNRC Review PDTSSystemEval/RecategorizeSystemIsolation/draining and abandonment EMERGENCY PLANNINGTrans  toSAFSTOR (1)Transition toSAFSTOR (2)Prepare/submit ISFSIOnly Tech SpecsNRC review ISFSIOnly Tech SpecsSystems Drain/Energy Removal(Avail/Abandon)Systems Drain/Energy Removal(Avail/Abandon)(No Spent Fuel in Pool)Sec Sys AbandonmentSFP Sys AbandonPDEP/no offsite staff or facilitiesERO Plan(ISFSI ONLY)Prepare/issue ODCMRevise Security Plan(ISFSI ONLY)NRC Review of Security PlanExemption requestNRC Review of Security PlanExemption requestNRC Approval of  PDEP and exemption RequestSFP Indication MODElectrical footprint reductionHeating/cooling footprint reductionUSAR Update USAR Update Change MGMTPlans-developSystem ReclassificationPost MODsEngineering Develop ECs for MODsStaffing AdjustmentsHE-2 Aux Bldg Crane MODMaintain Cybersecurity PlanDecision MilestoneSAFSTOR/DECONLegend:DCE Decommissioning Cost EstimateERO Emergency Response OrganizationFHA Fuel Handling AnalysisISFSI Independent Spent Fuel Storage InstallationODCM Offsite Dose Calculation ManualPDEP Permanently Defueled E-PlanPSDAR Post Shutdown Decommissioning Activities ReportPSEP Post Shutdown E-PlanPDTS Permanently Defueled Tech SpecsSFP Spent Fuel PoolUSAR Updated Safety Analysis ReportMilestone ReviewSAFSTOR/DECONNRC Approval of PSEPRevise Fire Hazard AnalysisReview Fire BrigadeStaffing AdjustmentsSafstorDecon SafstorDecon Developed by Transition TeamNote:Represents our best knowledge as of this revision. This plan will be updated as new information dictates.Station procedure reviews/revisions/deletionsInstall SFP Cooling MOD Emergency Plan Changes8Post Shutdown EPlanSubmitted 9/2/16 Revised on-shift and Emergency Response Organization (ERO) staffing based on analysis of required post-shutdown ERO positions but does not change any Emergency Action Level (EALs)Meeting with all supporting offsite agencies held on 9/8/16; additional meetings are scheduledVerification drills including offsite agencies scheduled for first quarter 2017 Emergency Plan Changes9Supporting submittalsCertified Fuel Handler (CFH) Training Program submitted on 7/7/16 One Request for Additional Information (RAI) received; response provided 10/7/16Technical Specifications (TS), Section 5, Administrative Controls, License Amendment Request (LAR) submitted 9/28/16Severe Weather Security Plan Exemption Request (10CFR73.55) submitted 10/7/16 Emergency Plan Changes10Permanently Defueled EPlanRevises EALs, removes all offsite ERO functions and significantly reduces ERO staffingInitial draft prepared and undergoing cross-disciplinary team & offsite agency reviewsSupporting vendor analyses: Zirconium Fire, Shine, Radiation Monitor Set Points and updated Fuel Handling Accident Boundary Dose Permanently Defueled EPlanand associated Exemption Requests (10CFR50.47 & App E) will be submitted December 2016 Other Submittal PlansNRC fee reclassification in November 2016Exemption for Maintenance of Records in December 2016SAFSTOR Security submittal in December 2016Post Shutdown Decommissioning Activities Report (PSDAR), Decommissioning Cost Estimate (DCE), Spent Fuel Management plan and Limited Site Characterization in first quarter 2017Permanently Defueled TS LAR in first quarter 2017Insurance Exemption requests in first quarter 2017Quality Assurance Topical Report update in first quarter 201711 Other Submittal PlansFukushimaLetter submitted to NRC on 8/12/16 for relaxation of implementation date for compliance with Order EA-12-049 (Mitigation Strategies for Beyond Design Basis External Events) to 8/31/17Request to rescind Order EA-12-051 (Reliable Spent Fuel Pool Instruments) submitted 9/9/16Updated Overall Integrated Plan (OIP) for EA12049 by 10/31/16Certify compliance with EA-12-049 by 8/31/1712 Other Submittal PlansConfirmatory Action Letter (CAL) itemsSubmit LAR for Class 1 Structures (Auxiliary Building) needed to support decommissioning in October 2016Submit letter to request closure of NRC CAL items in October 2016National Fire Protection Association (NFPA) 805LAR to delete Fire Protection License Condition and utilize NFPA 805 Decommissioning Fire Program in December 2016 CyberSecurityApplicable CyberSecuritysubmittals based on proposed NRC guidance planned in first quarter 201713 FCS DecommissioningClosing Comments/Questions14}}
{{#Wiki_filter:Omaha Public Power District (OPPD)
Fort Calhoun Station (FCS) Decommissioning October 18, 2016
 
FCS Decommissioning Team
* Mary Fisher - Sr. Dir. FCS Decommissioning
* Brad Blome - Mgr. Site Regulatory Assurance
* Herb Childs - Mgr. Site Security
* Ted Maine - Mgr. Radiation Protection
* Tim Uehling - Mgr. Site Training Also present: David Daigle - ENERCON, Emergency Preparedness Specialist 2
 
===Background===
* OPPD is a publicly-owned electric utility and is a political subdivision of the state of Nebraska
* Governed by a publicly elected Board of Directors
* On 5/12/16, OPPD management recommended ceasing FCS operations to the Board of Directors
* On 6/16/16, OPPD Board of Directors voted and approved ceasing FCS operations and going to SAFSTOR 3
 
Initial NRC Submittals
* Initial certification to Permanently Cease Operations by 12/31/16 submitted on 6/24/16
* Updated certification submitted on 8/25/16, FCS will Permanently Cease Operations on 10/24/16
* Certification of Permanent Removal of Fuel from the Reactor Vessel will be submitted in November 2016 4
 
Decommissioning Approach
* Multidisciplinary teams supplemented with several vendors with decommissioning experience
* Benchmarking Trips to Crystal River, Vermont Yankee, Zion, Kewaunee; future trips planned
* Industry decommissioning groups Nuclear Energy Institute (NEI) Decommissioning Transition Team Industry Regulatory Assurance (RA) Decommissioning Users Group Emergency Planning Decommissioning Users Group
* Decommissioning Oversight Committee 5
 
Key SAFSTOR Decision Points
* Decommissioning Funds
* Possible Decommissioning Services Agreement fourth quarter 2016
* Independent Spent Fuel Storage Installation (ISFSI) timeline and vendor selection for additional casks second quarter 2017
* Evaluate SAFSTOR/DECON timelines 6
 
Fort Calhoun SAFSTOR Timeline End Zirc SHUTDOWN                                                                                                                                                                                                                                                All Fire Period Oct 24, 2016 Rev 1                                                                                                       17 months                                                                                                                                                                    Spent Fuel 10/13/16                                                                                                                                                                                                                                                                      On ISFSI Decom                                  Decom                          Decom                                      Decom ONLINE                                                                                                                        cost                          cost                                        cost cost                                                                                                                                                                      Plant in Update                                  Update                        Update                                      Update                                                  SAFSTOR to                                     to                              to                                          to NRC                                    NRC                            NRC                                        NRC Decom Submit Letter(s)                                                                                                                                                                                                                   ISFSI cost
                              - Cease Operations                                                                                                                                                                                                                   Campaign Update
                            - Permanent Defueled                PSDAR/DCE ISFSI Only to Submittal
                                                                  ~03/31/17 PDTS                                                                                                                                                      Tech Specs NRC Issued                                                                                                                                                        Issued 3Q16      4Q16        1Q17      2Q17        3Q17      4Q17      1Q18      2Q18      3Q18    4Q18      1Q19      2Q19      3Q19 4Q19 1Q20    2Q20      3Q20      4Q20        1Q21    2Q21      3Q21 4Q21 1Q22    2Q22        3Q22          4Q22        1Q23 YEAR                  2016                            2017                                        2018                                    2019                          2020                                        2021                          2022                            2023 Staffing Adjustments                                                                                                              Decon                                                                                                                                                      Decon Safstor                                                                                                                                                    Safstor Change MGMT            Change MGMT                                                          Trans to ORGANIZATION                                                                                                                                                                                                                                                                          Transition to Plans-develop      Plans-Implement                                                      SAFSTOR (1)
CHANGES                                                                                                                                                                                                                                                                            SAFSTOR (2)
Decision Milestone SAFSTOR/DECON                                      Prepare/submit ISFSI                        NRC review ISFSI Prepare/                            NRC Review PDTS Submit PDTS                                                                                                                                  Only Tech Specs                            Only Tech Specs Tech Specs ODCM                                                          Prepare/issue ODCM Prepare/issue ODCM Milestone Review SAFSTOR/DECON Chapter 14 USAR update              Remaining USAR Update                                                                          USAR Update                                                                USAR Update USAR and Accident Analysis                      FHA Analysis System                    System Reclassification System Reclassification Post MODs                                                                                                                                                                                Systems Drain/
Eval/Recategorize                                                                                                                                                                                                                                                                            Energy Removal (Avail/Abandon)
(No Spent Fuel in Pool)
System                      Systems Drain/                          Sec Sys Abandonment Energy Removal Isolation/draining            (Avail/Abandon)
SFP Sys Pri Sys Abandonment                                                                                                                                                                                        Abandon and abandonment NRC Approval of PSEP Revise ERO Plan EMERGENCY                    (PSEP/PDEP)                                                                                                                                                                                                                                                      ERO Plan NRC Approval of PDEP and exemption Request                                                                            PDEP/no offsite staff or facilities PLANNING                                                                                                                                                                                                                                                                                  (ISFSI ONLY)
Maintain Cybersecurity Plan Revise Security Plan           NRC Review of Security Plan                                                                                        Revise Security Plan              NRC Review of Security Plan SECURITY PLAN                        (Defueled)                      Exemption request                                                                                                (ISFSI ONLY)                        Exemption request Station procedure reviews/revisions/deletions                                                                                    Legend:
Determine Engineering Programs                                                                                                                                                DCE - Decommissioning Cost Estimate                                    Developed by Transition Team Review Fire Brigade                                                                ERO - Emergency Response Organization ENG/PROGRAMS                required/not required Staffing Adjustments                                                                FHA - Fuel Handling Analysis                                        Note: Represents our best knowledge Revise Fire Hazard ISFSI - Independent Spent Fuel Storage Installation                as of this revision. This plan will be Analysis ODCM - Offsite Dose Calculation Manual                              updated as new information dictates.
Engineering Develop ECs for MODs                        HE-2 Aux Bldg Crane MOD                                                                                          PDEP - Permanently Defueled E-Plan PSDAR - Post Shutdown Decommissioning Activities Report                  Developed by DECOM Team MODIFICATIONS                                      Evaluate SFP              Install SFP Cooling MOD            Cooling MOD                                                                                                            PSEP - Post Shutdown E-Plan                                          Note: This Color Graphic is a PDTS - Permanently Defueled Tech Specs                              communication tool only. It is not a SFP Indication MOD                    Heating/cooling footprint reduction SFP - Spent Fuel Pool                                                controlled document or schedule and Electrical footprint reduction                                                                                              USAR - Updated Safety Analysis Report                                subject to change.
3Q16      4Q16      1Q17      2Q17        3Q17      4Q17      1Q18      2Q18      3Q18    4Q18      1Q19      2Q19      3Q19  4Q19 1Q20    2Q20      3Q20      4Q20          1Q21    2Q21      3Q21  4Q21 1Q22    2Q22        3Q22          4Q22        1Q23
 
Emergency Plan Changes Post Shutdown EPlan
* Submitted 9/2/16
* Revised on-shift and Emergency Response Organization (ERO) staffing based on analysis of required post-shutdown ERO positions but does not change any Emergency Action Level (EALs)
* Meeting with all supporting offsite agencies held on 9/8/16; additional meetings are scheduled
* Verification drills including offsite agencies scheduled for first quarter 2017 8
 
Emergency Plan Changes Supporting submittals
* Certified Fuel Handler (CFH) Training Program submitted on 7/7/16
* One Request for Additional Information (RAI) received; response provided 10/7/16
* Technical Specifications (TS), Section 5, Administrative Controls, License Amendment Request (LAR) submitted 9/28/16
* Severe Weather Security Plan Exemption Request (10CFR73.55) submitted 10/7/16 9
 
Emergency Plan Changes Permanently Defueled EPlan
* Revises EALs, removes all offsite ERO functions and significantly reduces ERO staffing
* Initial draft prepared and undergoing cross-disciplinary team & offsite agency reviews
* Supporting vendor analyses: Zirconium Fire, Shine, Radiation Monitor Set Points and updated Fuel Handling Accident Boundary Dose
* Permanently Defueled EPlan and associated Exemption Requests (10CFR50.47 & App E) will be submitted December 2016 10
 
Other Submittal Plans
* NRC fee reclassification in November 2016
* Exemption for Maintenance of Records in December 2016
* SAFSTOR Security submittal in December 2016
* Post Shutdown Decommissioning Activities Report (PSDAR), Decommissioning Cost Estimate (DCE),
Spent Fuel Management plan and Limited Site Characterization in first quarter 2017
* Permanently Defueled TS LAR in first quarter 2017
* Insurance Exemption requests in first quarter 2017
* Quality Assurance Topical Report update in first quarter 2017 11
 
Other Submittal Plans Fukushima
* Letter submitted to NRC on 8/12/16 for relaxation of implementation date for compliance with Order EA-12-049 (Mitigation Strategies for Beyond Design Basis External Events) to 8/31/17
* Request to rescind Order EA-12-051 (Reliable Spent Fuel Pool Instruments) submitted 9/9/16
* Updated Overall Integrated Plan (OIP) for EA12049 by 10/31/16
* Certify compliance with EA-12-049 by 8/31/17 12
 
Other Submittal Plans Confirmatory Action Letter (CAL) items
* Submit LAR for Class 1 Structures (Auxiliary Building) needed to support decommissioning in October 2016
* Submit letter to request closure of NRC CAL items in October 2016 National Fire Protection Association (NFPA) 805
* LAR to delete Fire Protection License Condition and utilize NFPA 805 Decommissioning Fire Program in December 2016 CyberSecurity
* Applicable CyberSecurity submittals based on proposed NRC guidance planned in first quarter 2017 13
 
FCS Decommissioning Closing Comments/Questions 14}}

Latest revision as of 13:10, 30 October 2019

OPPD Pre-Submittal Meeting Regarding Fort Calhoun Station Decommissioning October 18, 2016
ML16291A019
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 10/17/2016
From:
Omaha Public Power District
To: Lyon C
Plant Licensing Branch IV
Lyon C, NRR-DORL 415-2296
References
TAC MF8114
Download: ML16291A019 (14)


Text

Omaha Public Power District (OPPD)

Fort Calhoun Station (FCS) Decommissioning October 18, 2016

FCS Decommissioning Team

  • Mary Fisher - Sr. Dir. FCS Decommissioning
  • Brad Blome - Mgr. Site Regulatory Assurance
  • Herb Childs - Mgr. Site Security
  • Ted Maine - Mgr. Radiation Protection

Background

  • OPPD is a publicly-owned electric utility and is a political subdivision of the state of Nebraska
  • Governed by a publicly elected Board of Directors
  • On 5/12/16, OPPD management recommended ceasing FCS operations to the Board of Directors
  • On 6/16/16, OPPD Board of Directors voted and approved ceasing FCS operations and going to SAFSTOR 3

Initial NRC Submittals

  • Initial certification to Permanently Cease Operations by 12/31/16 submitted on 6/24/16
  • Updated certification submitted on 8/25/16, FCS will Permanently Cease Operations on 10/24/16
  • Certification of Permanent Removal of Fuel from the Reactor Vessel will be submitted in November 2016 4

Decommissioning Approach

  • Multidisciplinary teams supplemented with several vendors with decommissioning experience
  • Benchmarking Trips to Crystal River, Vermont Yankee, Zion, Kewaunee; future trips planned
  • Industry decommissioning groups Nuclear Energy Institute (NEI) Decommissioning Transition Team Industry Regulatory Assurance (RA) Decommissioning Users Group Emergency Planning Decommissioning Users Group
  • Decommissioning Oversight Committee 5

Key SAFSTOR Decision Points

  • Decommissioning Funds
  • Possible Decommissioning Services Agreement fourth quarter 2016
  • Independent Spent Fuel Storage Installation (ISFSI) timeline and vendor selection for additional casks second quarter 2017
  • Evaluate SAFSTOR/DECON timelines 6

Fort Calhoun SAFSTOR Timeline End Zirc SHUTDOWN All Fire Period Oct 24, 2016 Rev 1 17 months Spent Fuel 10/13/16 On ISFSI Decom Decom Decom Decom ONLINE cost cost cost cost Plant in Update Update Update Update SAFSTOR to to to to NRC NRC NRC NRC Decom Submit Letter(s) ISFSI cost

- Cease Operations Campaign Update

- Permanent Defueled PSDAR/DCE ISFSI Only to Submittal

~03/31/17 PDTS Tech Specs NRC Issued Issued 3Q16 4Q16 1Q17 2Q17 3Q17 4Q17 1Q18 2Q18 3Q18 4Q18 1Q19 2Q19 3Q19 4Q19 1Q20 2Q20 3Q20 4Q20 1Q21 2Q21 3Q21 4Q21 1Q22 2Q22 3Q22 4Q22 1Q23 YEAR 2016 2017 2018 2019 2020 2021 2022 2023 Staffing Adjustments Decon Decon Safstor Safstor Change MGMT Change MGMT Trans to ORGANIZATION Transition to Plans-develop Plans-Implement SAFSTOR (1)

CHANGES SAFSTOR (2)

Decision Milestone SAFSTOR/DECON Prepare/submit ISFSI NRC review ISFSI Prepare/ NRC Review PDTS Submit PDTS Only Tech Specs Only Tech Specs Tech Specs ODCM Prepare/issue ODCM Prepare/issue ODCM Milestone Review SAFSTOR/DECON Chapter 14 USAR update Remaining USAR Update USAR Update USAR Update USAR and Accident Analysis FHA Analysis System System Reclassification System Reclassification Post MODs Systems Drain/

Eval/Recategorize Energy Removal (Avail/Abandon)

(No Spent Fuel in Pool)

System Systems Drain/ Sec Sys Abandonment Energy Removal Isolation/draining (Avail/Abandon)

SFP Sys Pri Sys Abandonment Abandon and abandonment NRC Approval of PSEP Revise ERO Plan EMERGENCY (PSEP/PDEP) ERO Plan NRC Approval of PDEP and exemption Request PDEP/no offsite staff or facilities PLANNING (ISFSI ONLY)

Maintain Cybersecurity Plan Revise Security Plan NRC Review of Security Plan Revise Security Plan NRC Review of Security Plan SECURITY PLAN (Defueled) Exemption request (ISFSI ONLY) Exemption request Station procedure reviews/revisions/deletions Legend:

Determine Engineering Programs DCE - Decommissioning Cost Estimate Developed by Transition Team Review Fire Brigade ERO - Emergency Response Organization ENG/PROGRAMS required/not required Staffing Adjustments FHA - Fuel Handling Analysis Note: Represents our best knowledge Revise Fire Hazard ISFSI - Independent Spent Fuel Storage Installation as of this revision. This plan will be Analysis ODCM - Offsite Dose Calculation Manual updated as new information dictates.

Engineering Develop ECs for MODs HE-2 Aux Bldg Crane MOD PDEP - Permanently Defueled E-Plan PSDAR - Post Shutdown Decommissioning Activities Report Developed by DECOM Team MODIFICATIONS Evaluate SFP Install SFP Cooling MOD Cooling MOD PSEP - Post Shutdown E-Plan Note: This Color Graphic is a PDTS - Permanently Defueled Tech Specs communication tool only. It is not a SFP Indication MOD Heating/cooling footprint reduction SFP - Spent Fuel Pool controlled document or schedule and Electrical footprint reduction USAR - Updated Safety Analysis Report subject to change.

3Q16 4Q16 1Q17 2Q17 3Q17 4Q17 1Q18 2Q18 3Q18 4Q18 1Q19 2Q19 3Q19 4Q19 1Q20 2Q20 3Q20 4Q20 1Q21 2Q21 3Q21 4Q21 1Q22 2Q22 3Q22 4Q22 1Q23

Emergency Plan Changes Post Shutdown EPlan

  • Submitted 9/2/16
  • Revised on-shift and Emergency Response Organization (ERO) staffing based on analysis of required post-shutdown ERO positions but does not change any Emergency Action Level (EALs)
  • Meeting with all supporting offsite agencies held on 9/8/16; additional meetings are scheduled
  • Verification drills including offsite agencies scheduled for first quarter 2017 8

Emergency Plan Changes Supporting submittals

  • Certified Fuel Handler (CFH) Training Program submitted on 7/7/16
  • One Request for Additional Information (RAI) received; response provided 10/7/16
  • Technical Specifications (TS), Section 5, Administrative Controls, License Amendment Request (LAR) submitted 9/28/16

Emergency Plan Changes Permanently Defueled EPlan

  • Revises EALs, removes all offsite ERO functions and significantly reduces ERO staffing
  • Initial draft prepared and undergoing cross-disciplinary team & offsite agency reviews
  • Supporting vendor analyses: Zirconium Fire, Shine, Radiation Monitor Set Points and updated Fuel Handling Accident Boundary Dose

Other Submittal Plans

  • NRC fee reclassification in November 2016
  • Exemption for Maintenance of Records in December 2016
  • SAFSTOR Security submittal in December 2016
  • Post Shutdown Decommissioning Activities Report (PSDAR), Decommissioning Cost Estimate (DCE),

Spent Fuel Management plan and Limited Site Characterization in first quarter 2017

  • Permanently Defueled TS LAR in first quarter 2017
  • Quality Assurance Topical Report update in first quarter 2017 11

Other Submittal Plans Fukushima

  • Letter submitted to NRC on 8/12/16 for relaxation of implementation date for compliance with Order EA-12-049 (Mitigation Strategies for Beyond Design Basis External Events) to 8/31/17
  • Request to rescind Order EA-12-051 (Reliable Spent Fuel Pool Instruments) submitted 9/9/16
  • Updated Overall Integrated Plan (OIP) for EA12049 by 10/31/16
  • Certify compliance with EA-12-049 by 8/31/17 12

Other Submittal Plans Confirmatory Action Letter (CAL) items

  • Submit LAR for Class 1 Structures (Auxiliary Building) needed to support decommissioning in October 2016
  • Submit letter to request closure of NRC CAL items in October 2016 National Fire Protection Association (NFPA) 805
  • LAR to delete Fire Protection License Condition and utilize NFPA 805 Decommissioning Fire Program in December 2016 CyberSecurity
  • Applicable CyberSecurity submittals based on proposed NRC guidance planned in first quarter 2017 13

FCS Decommissioning Closing Comments/Questions 14