ML090370455

From kanterella
Jump to navigation Jump to search

Licensee Slides, January 28, 2009, Meeting with Omaha Public Power District to Discuss OPPDs Plans to Submit an Extended Power Uprate Request for the Fort Calhoun Station, Unit 1
ML090370455
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 01/28/2009
From:
Omaha Public Power District
To:
Office of Nuclear Reactor Regulation
Wilkins, L E, NRR/DORL/LPL4, 415-1377
Shared Package
ML090370404 List:
References
TAC ME0592
Download: ML090370455 (17)


Text

Fort Calhoun Station Extended Power Uprate (EPU) Project January 28, 2009

Agenda Purpose Project Overview Plant Impact Pl t M difi ti

- Ron Short

- Bernie Van Sant B

i V

S t

Plant Modifications Licensing Approach PRA Risk Insights Summary Questions/Feedback

- Bernie Van Sant

- Bob Dulee

- Carmen Ovici

- Ron Short

Project Purpose Support the OPPD Integrated Resource Plan (IRP) for additional power supply by January 2013

Project Scope 17% Power Uprate - 1755 MWt Current License - 1500 MWt 75 MWe - Summer 79 MWe - Non-Summer 78 MWe Average

=

Background===

Combustion Engineering NSSS Initial operation - September 1973 License expires - August 2033 EPU studied several times Conceptual engineering is complete Detailed engineering/licensing in progress Large components replaced in 2005/2006

Project Schedule Project Initiation - April 2008 Design and licensing Engineering analyses/Licensing in progress Finalize modification scope - early 2009 Submit LAR to NRC - March 2011 2011 and 2012 Re-Fueling Outages (RFO)

Component modifications Uprated condition following 2012 RFO

Project Management Team

Vendor Support Team Fuel & Related Services - AREVA NP NSSS - Westinghouse Balance of Plant - Sargent & Lundy g

y Modification Packages - Sargent & Lundy Equipment - TBD Installation - TBD

Licensing Approach Benchmark Ginna and Waterford 3 License Amendment Request (LAR) prepared per Review Standard RS-001 EPU Project to compile LAR Independent review prior to submittal Expect frequent interface with NRC Member NEI EPU Working Group

PRA Risk Insights Initial EPU impact assessed Potential risk reduction items identified Power Operated Relief Valves (PORVs)

Atmospheric Dump Valves (ADVs)

Procedure enhancements

Plant Impact 3-pump operation (Main feedwater, Condensate)

Reactor coolant system at 2250 psi Increased fuel enrichment (4.95%)

Several modifications required

Activities Completed with EPU Considerations Replaced Steam Generators Replaced Pressurizer Replaced Low Pressure Turbines Replaced Main Condenser Replaced Main Transformer

2011 RFO Modifications New potable water and supplemental emergency feedwater storage tank Heater drain tank and valves Main feedwater regulation valve trim Main feedwater regulation valve trim Turbine cross around relief valves Safety injection pump room cooling Nuclear detector well cooling

2012 RFO Modifications High pressure turbine Main generator rewind Main steam safety valves (MS-291/292) y

(

)

Trippable Group N rods Isophase bus duct cooling Auxiliary feedwater pump and motor Transmission & Distribution No FCS switchyard modifications

Possible Component Modifications Replace Feedwater heaters (FW-14 A & B)

Switchgear room cooling I

h b

d t

Isophase bus duct Larger PORVs ADVs upstream of MSIVs

Project Summary Supports the OPPD Integrated Resource Plan (IRP) for additional power supply by January 2013 Vendor detailed Engineering & Licensing work underway LAR submittal in March 2011 NRC approval in March 2012

Questions/Feedback Questions/Feedback