Fort Calhoun Station Transition to National Fire Protection Association (NFPA) 805 Fire Protection Program January 28, 2009
Agenda Project Overview Plant Impact NFPA 805 & Extended Power Uprate (EPU) Interface (EPU) Interface Summary Questions/Feedback
Project Purpose Transition the OPPD Fort Calhoun Station to the risk informed, performance based NFPA 805 Fire Protection P
i N
l E
I tit t Program using Nuclear Energy Institute (NEI) 04-02 guidance
Project Scope Development of a Fire PRA in accordance with industry and regulatory standards E t bli h t
f li i
b i f Establishment of licensing basis for NFPA 805 FP Program Completion of transition report and FCS document revisions Integrate NFPA 805 & Extended Power Uprate Project
=
Background===
Current license basis of FP Program NFPA 805 enhances OPPD Fort Calhoun Station Fire Protection Program FCS itt d t NFPA 805 T iti FCS committed to NFPA 805 Transition on June 9, 2008
Project Schedule Complete Fire PRA - September 2010 Transition Report - April 2011 Submit NFPA 805 LAR to NRC - June 9, 2011 2011 NFPA 805 LAR approval June 2012
Project Management Team
Vendor Support Team Fire Probabilistic Risk Assessment -
Westinghouse NFPA 805 Transition - Engineering Planning & Management (EPM)
Supplemental Technical Support
Plant Impact NFPA 805 Transition Report Development of NFPA 805 Licensing basis Implementation of Fire PRA Implementation of Fire PRA Revised Operating Procedures Modifications NFPA 805 EPU
NFPA 805 & EPU Interface Develop Fire PRA based on current plant Early identification of cable routing Early Fire PRA insights R
d ti f
EPU j
t Recommendations for EPU project Early Safe Shutdown Fire PRA insights NFPA 805 recommendations Potential beneficial modifications for EPU and NFPA 805
NFPA 805 & EPU Interface NFPA 805 and EPU LARs not dependent on each other NFPA 805 LAR submittal will include 2011 plant and EPU modifications Update NFPA 805 program for 2013 plant and EPU modifications
Project Summary Initiative for risk informed performance based fire protection program NFPA 805 enhances OPPD Fort Calhoun Station Fire Protection Program NFPA 805/EPU integration is risk informed NFPA 805 submittal in June 2011
Questions/Feedback Questions/Feedback