Licensee Slides, January 28, 2009, Meeting with Omaha Public Power District, to Discuss the Fort Calhoun Station'S Transition to National Fire Protection Association (NFPA) 805
ML090370648
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 01/28/2009
From:
Omaha Public Power District
To:
Office of Nuclear Reactor Regulation
Wilkins, L E, NRR/DORL/LPL4, 415-1377
Shared Package
ML090370405 List:
References
TAC ME0591
Download: ML090370648 (13)


Text

Fort Calhoun Station Transition to National Fire Protection Association (NFPA) 805 Fire Protection Program January 28, 2009

Agenda Project Overview Plant Impact NFPA 805 & Extended Power Uprate (EPU) Interface Summary Questions/Feedback

Project Purpose Transition the OPPD Fort Calhoun Station to the risk informed, performance based NFPA 805 Fire Protection P

Program using i N Nuclear l E Energy IInstitute tit t (NEI) 04-02 guidance

Project Scope Development of a Fire PRA in accordance with industry and regulatory standards Establishment E t bli h t off licensing li i b basis i ffor NFPA 805 FP Program Completion of transition report and FCS document revisions Integrate NFPA 805 & Extended Power Uprate Project

=

Background===

Current license basis of FP Program NFPA 805 enhances OPPD Fort Calhoun Station Fire Protection Program FCS committed itt d to t NFPA 805 Transition T iti on June 9, 2008

Project Schedule Complete Fire PRA - September 2010 Transition Report - April 2011 Submit NFPA 805 LAR to NRC - June 9, 2011 NFPA 805 LAR approval June 2012

Project Management Team Vendor Support Team Fire Probabilistic Risk Assessment -

Westinghouse NFPA 805 Transition - Engineering Planning & Management (EPM)

Supplemental Technical Support

Plant Impact NFPA 805 Transition Report Development of NFPA 805 Licensing basis Implementation of Fire PRA Revised Operating Procedures Modifications NFPA 805 EPU

NFPA 805 & EPU Interface Develop Fire PRA based on current plant Early identification of cable routing Early Fire PRA insights R

Recommendations d ti ffor EPU project j t Early Safe Shutdown Fire PRA insights NFPA 805 recommendations Potential beneficial modifications for EPU and NFPA 805

NFPA 805 & EPU Interface NFPA 805 and EPU LARs not dependent on each other NFPA 805 LAR submittal will include 2011 plant and EPU modifications Update NFPA 805 program for 2013 plant and EPU modifications

Project Summary Initiative for risk informed performance based fire protection program NFPA 805 enhances OPPD Fort Calhoun Station Fire Protection Program NFPA 805/EPU integration is risk informed NFPA 805 submittal in June 2011

Questions/Feedback