ML110950596
| ML110950596 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 04/05/2011 |
| From: | Omaha Public Power District |
| To: | Office of Nuclear Reactor Regulation |
| Wilkins, L E, NRR/DORL/LPL4, 415-1377 | |
| References | |
| TAC ME5104 | |
| Download: ML110950596 (24) | |
Text
Fort Calhoun Station Extended Power Uprate (EPU)
Project EPUs Impact on Environmental Qualification Program 1
AGENDA
- Introductions and Overview
Program
- License Amendment Request icense Amendment Request
- Take Aways
- Question and Answer 2
Introductions and Overview 3
Introductions
- Mark Frans Manager Engineering Programs
- Tom Shudak FCS Program Engineer
- Ron Wise Consultant
- Bill Hansher FCS Licensing Supervisor 4
EPU Project Overview
- 17% EPU: 1500 MWt to 1755 MWt 80 MWe
- Engineering & Licensing work in progress
- Submit LAR to NRC: May 31 2011
- Submit LAR to NRC: May 31, 2011
- Plant modifications: 2011/2012 RFOs
- Implement EPU: Post-2012 RFO 5
EPU Impact on Environmental Qualification Program Program 6
EPU Impact on EQ Program EPU Impact on the EQ Program focused on:
- Identifying changes to environmental conditions (normal and accident)
E i
h h EQ P i
ill
- Ensuring that the EQ Program equipment will continue to perform as required following implementation of EPU 7
EPU Impact on EQ Program Licensing Basis Criteria:
- 10 CFR 50.49 / RG 1.89 / SRP 3.11
- DOR Guidelines (Enclosure 4 to IEB 79-01B)
EPU Impact on EQ Program PROCESS USED FOR EVALUATION 9
EPU Impact on EQ Program Method of Evaluation:
- Compared the EPU environments to the current environments and profiles used to demonstrate environmental qualification
- Where EPU profiles exceed the current profiles, then specific parameters were compared against the qualification basis in the EQ File
- Applied Lessons Learned from other utilities 10
EPU Impact on EQ Program Evaluation:
- Containment environmental conditions
- MSLB
- Auxiliary Building environmental conditions
- LOCA
- MSLB / FWLB
- Other
- Normal environmental conditions 11
EPU Impact on EQ Program Results:
Containment
- Peak temperature/pressures are bounded by existing EQ values Q values
- Total integrated doses increased
- Analysis included change in containment spray chemistry up to 2500 ppm boron 12
EPU Impact on EQ Program Results:
Auxiliary Building
- MSLB peak temperatures and pressures in Main Steam Line Room increased Steam ine Room increased
- Flood level from a FWLB in Main Steam Line Room increased 13
EPU Impact on EQ Program Results:
Auxiliary Building
- Post LOCA temperatures in rooms containing sump recirculation piping increased recirculation piping increased
- Total integrated doses increased
- Dose increase did not result in any Mild areas becoming radiation Harsh 14
EPU Impact on EQ Program Impacts:
- Evaluation resulted in the identification of required changes to ensure qualification on a component level
- Changes include:
Changes include:
- Update to EQ Files to reflect new EPU conditions (equipment remains fully qualified)
- New or additional test reports need to be incorporated into the EQ Files
- Equipment replacements identified 15
License Amendment Request
- Licensing Report prepared in accordance with RS-001
- Licensing Report provides a summary of the pre-EPU icensing Report provides a summary of the pre PU and post-EPU environmental parameters 16
Overview of EQ Project and HELB Reconstitution and HELB Reconstitution 17
Overview of EQ Project
- Improvements to Program Infrastructure
- Validating Design Inputs to EQ Program
- Improvements to the EQ Files
- Scope includes reconstituting HELB analysis outside of containment (6/2011) 18
HELB Reconstitution
- Systems being evaluated for HELB reconstitution are:
- Main Steam (complete)
- Feedwater (complete)
- Letdown / Charging
- Steam Generator Blowdown
- Auxiliary Steam 19
HELB Reconstitution
- Being performed to reconstitute and upgrade the HELB analysis
Take Aways 21
Take Aways
- The assessment focused on the changes to the normal and accident environmental normal and accident environmental conditions used by the EQ Program
Take Aways
- Prior to implementation of EPU all EQ Program equipment affected by EPU will be qualified to EPU conditions
- EQ Project and HELB Reconstitution being performed separately but at EPU Conditions and will be completed prior to EPU implementation 23
Questions??
24