ML110950596

From kanterella
Jump to navigation Jump to search

Licensee Slides from 4/5/11 Meeting with Omaha Public Power District to Discuss Its Plans to Submit an Extended Power Uprate for Fort Calhoun Station and Issues Related to Equipment Environmental Qualification
ML110950596
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 04/05/2011
From:
Omaha Public Power District
To:
Office of Nuclear Reactor Regulation
Wilkins, L E, NRR/DORL/LPL4, 415-1377
References
TAC ME5104
Download: ML110950596 (24)


Text

Fort Calhoun Station Extended Power Uprate (EPU)

Project EPUs Impact on Environmental Qualification Program 1

AGENDA

  • Introductions and Overview
  • EPU Impact on Environmental Qualification (EQ)

Program

  • License icense Amendment Request
  • Overview of EQ Project & HELB Reconstitution
  • Take Aways
  • Question and Answer 2

Introductions and Overview 3

Introductions

  • Bernard Van Sant EPU BOP Project Manager
  • Mark Frans Manager Engineering Programs
  • Tom Shudak FCS Program Engineer
  • Ron Wise Consultant
  • Bill Hansher FCS Licensing Supervisor 4

EPU Project Overview

  • 17% EPU: 1500 MWt to 1755 MWt 80 MWe
  • Engineering & Licensing work in progress
  • Submit LAR to NRC: May 3131, 2011
  • Plant modifications: 2011/2012 RFOs
  • Implement EPU: Post-2012 RFO 5

EPU Impact on Environmental Qualification Program 6

EPU Impact on EQ Program EPU Impact on the EQ Program focused on:

  • Identifying changes to environmental conditions (normal and accident)
  • Ensuring E i that h theh EQ PProgram equipment i will ill continue to perform as required following implementation of EPU 7

EPU Impact on EQ Program Licensing Basis Criteria:

  • DOR Guidelines (Enclosure 4 to IEB 79-01B)

EPU Impact on EQ Program PROCESS USED FOR EVALUATION 9

EPU Impact on EQ Program Method of Evaluation:

  • Compared the EPU environments to the current environments and profiles used to demonstrate environmental qualification
  • Where EPU profiles exceed the current profiles, then specific parameters were compared against the qualification basis in the EQ File
  • Applied Lessons Learned from other utilities 10

EPU Impact on EQ Program Evaluation:

  • Containment environmental conditions

- LOCA

- MSLB

  • Auxiliary Building environmental conditions

- LOCA

- MSLB / FWLB

- Other

  • Normal environmental conditions 11

EPU Impact on EQ Program Results:

Containment

  • Peak temperature/pressures are bounded by existing Q values EQ
  • LOCA vapor and sump temperatures profiles increased
  • Total integrated doses increased

EPU Impact on EQ Program Results:

Auxiliary Building

EPU Impact on EQ Program Results:

Auxiliary Building

  • Post LOCA temperatures in rooms containing sump recirculation piping increased
  • Total integrated doses increased

- Dose increase did not result in any Mild areas becoming radiation Harsh 14

EPU Impact on EQ Program Impacts:

  • Evaluation resulted in the identification of required changes to ensure qualification on a component level
  • Changes include:

- Update to EQ Files to reflect new EPU conditions (equipment remains fully qualified)

- New or additional test reports need to be incorporated into the EQ Files

- Equipment replacements identified 15

License Amendment Request

  • Licensing Report prepared in accordance with RS-001
  • Licensing Report content based on lessons learned from previous EPU submittals dealing with EQ
  • Licensing icensing Report provides a summary of the pre pre-EPU PU and post-EPU environmental parameters 16

Overview of EQ Project and HELB Reconstitution 17

Overview of EQ Project

  • The EQ Project is a program improvement plan to improve the EQ Program (12/2011)

- Improvements to Program Infrastructure

- Validating Design Inputs to EQ Program

- Improvements to the EQ Files

  • Scope includes reconstituting HELB analysis outside of containment (6/2011) 18

HELB Reconstitution

  • Systems being evaluated for HELB reconstitution are:

- Main Steam (complete)

- Feedwater (complete)

- Letdown / Charging

- Steam Generator Blowdown

- Auxiliary Steam 19

HELB Reconstitution

  • Being performed to reconstitute and upgrade the HELB analysis
  • The HELB reconstitution is being performed as part of the EQ Project at EPU levels 20

Take Aways 21

Take Aways

  • The EPU Project has assessed the impact on the EQ Program
  • The assessment focused on the changes to the normal and accident environmental conditions used by the EQ Program
  • The EPU assessment has addressed OE from recent submittals related to EQ 22

Take Aways

  • Prior to implementation of EPU all EQ Program equipment affected by EPU will be qualified to EPU conditions
  • EQ Project and HELB Reconstitution being performed separately but at EPU Conditions and will be completed prior to EPU implementation 23

Questions??

24