{{#Wiki_filter:consumers Power company General Offices: 1945 West Parnall Road. Jackson, Ml 49201 * (517) 788-1217 March 26*, 1987 A Bert Davis, Administrator, Region III Nuclear Regulatory Commission . / Attn: Document Control Desk. Washington, DC 20555 DOCKET 50.,.255 LICENSE DPR PLANT -REQUEST FOR.RESTART AUTHORIZATION . _ Frederick W Buckman I/ice .President Nuclear Operations On May 21,.1986, NRC issued a Confirmatory Action Letter which stipulates that approv:al by* the Regional Administrator prior to restart of our Palisades Plant is required.
{{#Wiki_filter:consumers Power                                                 Frederick W Buckman company                                               I/ice .President Nuclear Operations General Offices:                   1945 West Parnall Road. Jackson, Ml 49201 * (517) 788-1217 March 26*, 1987 A Bert Davis, Administrator, Region III Nuclear Regulatory                     .
On March 20, 1987, representatives of Power Company* presented to the Nuclear Regulatory Commission the.current status and plans for -the restart *.
Commission/
* In that meeting, the Commissioners voted to authorize Regional Administrator to pe-nuit re.;.start pending completion of our startup prerequisites.
Attn: Document Control Desk.
This letter is to inform you that Consumers Power Company has completed all prior-to:-startup commitments; except those that will be verified during power Thes*e prior-to-startup (as well as other *commitments related to future plant operations, outages, etc.) were identified in our letters of July 3, i986, December 1, Jan\Jary 21, 1987 and January 28, 1987. The remaining open commitments, to be verified during power escalation, are l:j.:sted on the attachment to this. letter. You will be notified of the status of .these commitments during our power ascension.
Washington, DC 20555 DOCKET 50.,.255 ~ LICENSE DPR P~ISADES PLANT -
You will also be notified of our intent to leave . the power ascension plateaus of 30%, 60% 'and 80% of* full reactor power. The NRC Operational Readiness Audit team has raised the question as to the intent of the integrated testing program described iri Se.ct ion 3. 0 of our January submittal.
REQUEST FOR.RESTART AUTHORIZATION . _
Additional clarification is provided as follows *. Formal integrated testing was performed by proc*edure during the outage test program, . including
On May 21,.1986, NRC issued a Confirmatory Action Letter which stipulates that approv:al by* the Regional Administrator prior to restart of our Palisades Plant is required. On March 20, 1987, representatives of Consum~rs Power Company*
__ five _of.the si:x idei;_i.ti_f  
presented to the Nuclear Regulatory Commission the.current status and plans for -the restart *.
;led_ :i,p __ S_ec_tion: 9
* In that meeting, the Commissioners voted to authorize th~
* __ Pla_nt conditions did not permit integrated testing of the Main Feedwater System. The "inte:._*  
Regional Administrator to pe-nuit re.;.start pending completion of our prior-to-startup prerequisites. This letter is to inform you that Consumers Power Company has completed all prior-to:-startup commitments; except those that will be verified during power escalation~
-grated testing" schedu'led for hot shutdown and during power escalation will address all six systems, and is intended to enhance operator confidence in the performance .of these systems. This testing is less formal and is controlled via a test. plan rather than'. formal *special test procedures.
Thes*e prior-to-startup co~itments (as well as other *commitments related to future plant operations, outages, etc.) were identified in our letters of July 3, i986, December 1, ~986, Jan\Jary 21, 1987 and January 28, 1987. The remaining open commitments, to be verified during power escalation, are l:j.:sted on the attachment to this. letter. You will be notified of the status of .these commitments during our power ascension. You will also be notified of our intent to leave . the power ascension plateaus of 30%, 60% 'and 80% of* full reactor power.
I --. -*-... *. . . ,., .. ** I",. ' r a**
The NRC Operational Readiness Audit team has raised the question as to the intent of the integrated testing program described iri Se.ct ion 3. 0 of our January submittal. Additional clarification is provided as follows *. Formal integrated testing was performed by proc*edure during the outage test program,
87 0._5. 5$:. 1\. :* .*. '*1 I . .. ' ADOC,.... . . ' ' I ' PDR' -, .. ' . .* :. . ' .pDR I ... *, \. p *'.1:.-./':<:1',::-Y,<.;\.'1}' ...  
    . including __ five _of.the si:x _sy~t_ems_ idei;_i.ti_f ;led_ :i,p __S_ec_tion: ~-* 9 *__ Pla_nt conditions did not permit integrated testing of the Main Feedwater System. The "inte:._* -
--. "'; *-'1 *oc038 7 :-_0019C-NL04 Nuclear Regulatory Commission Palisades Plant Request for Restart Authorization March 26, 1987 2 You were notified by two previous letters from Consumers Power Company of a plant operability limitation based on service water temperature of 53&deg;F. Our December 2, 1986 submittal contained a Technical Specification change that imposed the 53&deg;F limit and a subsequent February 25, 1987 letter contained additional information in support of the limit. Although it is our intent to request withdrawal of our December 2, 1986 Technical Specification Change Request; we will comply with the temperature limit until we have submitted and received NRC review and approval of an evaluation that justifies operation at higher service water temperatures.
grated testing" schedu'led for hot shutdown and during power escalation will address all six systems, and is intended to enhance operator confidence in the performance .of these systems. This testing is less formal and is controlled via a test. plan rather than'. formal *special test procedures.
Consumers Power Company considers this 53&deg;F plant operability limitation a commitment and as such may be confirmed by NRC via issuance of a Confirmatory Action Letter (CAL). Consumers Power Company requests approval for the restart of the Palisades Plant.
                                                                                                      *~
Vice President Nuclear Operations CC NRC Resident Inspector  
' r a***70~0*1'0()3g I           --.   -*-...                           *.                 .       . ,., .. ** I",.
-Palisades Attachment OC0387-0019C-NL04
0._5.0 3 2 o o.o~--2. 5$:.
,. Submittal Date 12/01/86 12/01/86 12/01/86 1/28/86 12/01/86 1/28/87 1/28/87 1/28/87 1/28/87 AT0387-0019-NL04 a) b) POWER ESCALATION COMMITMENTS Commitment MCTF-FWS-07:
87                    6          1
Main feedwater pumps -seal water flow returns will be monitored during startup for flow and temperature.
                                                                                            \. :* .*.   '*1 PDR' -, .. ' . .* :. . ' .pDR . -~
MCTF-FWS-15:
ADOC,.... .                                               ' ~-'
Feedwater pump controls loop check/ calibration will have further testing performed at power.* MCTF-MSS-01; SFE #8 -Mainsteam System: Turbine bypass valve will have further testing performed at 30% power to verify operability and flow capacity.
  *, '\.
MCTF-SWS-03:
I    .                .. '                                                                          I p         *'.1:.-./':<:1',::-Y,<.;\.'1}' *~~*- ~: ...~:.:~
Exciter air cooler temperature will have follow-up verification performed after generator is on line. SFE #84 -Turbine Generator:
                      .   "'; *- -~*
Generator RTD temperature checks to be performed during power escalation.
                                                                          ~-i_:  - -
SFE #85 -Turbine Generator:
I            ...
Manual trip to be tested at less than 15% power. SFE #33: Hot Leg RTD Time Delay will be measured at power when vendor arrangements can be made. SFE #71 -Circulating Water System -Cooling Tower Pumps: Trend program will monitor performance during power escalation.
                '1
Additional tests to be performed during power escalation on: Feedwater control voltage regulator, turbine valve, turbine bypass valve, component manipulations to shakedown equipment.
    *oc038 7:-_0019C-NL04
 
Nuclear Regulatory Commission                                                 2 Palisades Plant Request for Restart Authorization March 26, 1987 You were notified by two previous letters from Consumers Power Company of a plant operability limitation based on service water temperature of 53&deg;F. Our December 2, 1986 submittal contained a Technical Specification change that imposed the 53&deg;F limit and a subsequent February 25, 1987 letter contained additional information in support of the limit. Although it is our intent to request withdrawal of our December 2, 1986 Technical Specification Change Request; we will comply with the temperature limit until we have submitted and received NRC review and approval of an evaluation that justifies operation at higher service water temperatures. Consumers Power Company considers this 53&deg;F plant operability limitation a commitment and as such may be confirmed by NRC via issuance of a Confirmatory Action Letter (CAL).
Consumers Power Company requests approval for the restart of the Palisades Plant.
<i!f:/!:f:J~
Vice President Nuclear Operations CC NRC Resident Inspector - Palisades Attachment OC0387-0019C-NL04
 
POWER ESCALATION COMMITMENTS Submittal Date                             Commitment 12/01/86         MCTF-FWS-07: Main feedwater pumps - seal water flow returns will be monitored during startup for flow and temperature.
12/01/86          MCTF-FWS-15: Feedwater pump controls loop check/
calibration will have further testing performed at power.*
,. 12/01/86          MCTF-MSS-01; SFE #8 - Mainsteam System: Turbine bypass 1/28/86          valve will have further testing performed at 30% power to verify operability and flow capacity.
12/01/86          MCTF-SWS-03: Exciter air cooler temperature ~ontrol will have follow-up verification performed after generator is on line.
1/28/87          SFE #84 - Turbine Generator: Generator RTD temperature checks to be performed during power escalation.
1/28/87          SFE #85 - Turbine Generator: Manual trip to be tested at less than 15% power.
1/28/87          SFE #33: Hot Leg RTD Time Delay will be measured at power when vendor arrangements can be made.
1/28/87        a) SFE #71 - Circulating Water System - Cooling Tower Pumps: Trend program will monitor performance during power escalation.
b) Additional tests to be performed during power escalation on: Feedwater control voltage regulator, turbine valve, turbine bypass valve, component manipulations to shakedown equipment.
c) Acceptable performance must be met on feedwater pumps, condensate pumps, cooling tower pumps heater drain
c) Acceptable performance must be met on feedwater pumps, condensate pumps, cooling tower pumps heater drain
* pumps, turbine, generator, main transformer and startup transformer before escalation to next power level can be made.}}
* pumps, turbine, generator, main transformer and startup transformer before escalation to next power level can be made.
AT0387-0019-NL04}}

Latest revision as of 20:34, 21 October 2019

Advises That Util Completed All prior-to-startup Commitments,Per NRC 860521 Confirmatory Action Ltr.Encl Lists Remaining Open Commitments Which Will Be Verified During Power Ascension.Approval for Restart Requested
ML18052A907
Person / Time
Site: Palisades Entergy icon.png
Issue date: 03/26/1987
From: Buckman F
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Davis A
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
CAL, NUDOCS 8704010030
Download: ML18052A907 (3)


Text

consumers Power Frederick W Buckman company I/ice .President Nuclear Operations General Offices: 1945 West Parnall Road. Jackson, Ml 49201 * (517) 788-1217 March 26*, 1987 A Bert Davis, Administrator, Region III Nuclear Regulatory .

Commission/

Attn: Document Control Desk.

Washington, DC 20555 DOCKET 50.,.255 ~ LICENSE DPR P~ISADES PLANT -

REQUEST FOR.RESTART AUTHORIZATION . _

On May 21,.1986, NRC issued a Confirmatory Action Letter which stipulates that approv:al by* the Regional Administrator prior to restart of our Palisades Plant is required. On March 20, 1987, representatives of Consum~rs Power Company*

presented to the Nuclear Regulatory Commission the.current status and plans for -the restart *.

  • In that meeting, the Commissioners voted to authorize th~

Regional Administrator to pe-nuit re.;.start pending completion of our prior-to-startup prerequisites. This letter is to inform you that Consumers Power Company has completed all prior-to:-startup commitments; except those that will be verified during power escalation~

Thes*e prior-to-startup co~itments (as well as other *commitments related to future plant operations, outages, etc.) were identified in our letters of July 3, i986, December 1, ~986, Jan\Jary 21, 1987 and January 28, 1987. The remaining open commitments, to be verified during power escalation, are l:j.:sted on the attachment to this. letter. You will be notified of the status of .these commitments during our power ascension. You will also be notified of our intent to leave . the power ascension plateaus of 30%, 60% 'and 80% of* full reactor power.

The NRC Operational Readiness Audit team has raised the question as to the intent of the integrated testing program described iri Se.ct ion 3. 0 of our January submittal. Additional clarification is provided as follows *. Formal integrated testing was performed by proc*edure during the outage test program,

. including __ five _of.the si:x _sy~t_ems_ idei;_i.ti_f ;led_ :i,p __S_ec_tion: ~-* 9 *__ Pla_nt conditions did not permit integrated testing of the Main Feedwater System. The "inte:._* -

grated testing" schedu'led for hot shutdown and during power escalation will address all six systems, and is intended to enhance operator confidence in the performance .of these systems. This testing is less formal and is controlled via a test. plan rather than'. formal *special test procedures.

  • ~

' r a***70~0*1'0()3g I --. -*-... *. . . ,., .. ** I",.

0._5.0 3 2 o o.o~--2. 5$:.

87 6 1

\. :* .*. '*1 PDR' -, .. ' . .* :. . ' .pDR . -~

ADOC,.... . ' ~-'

  • , '\.

I . .. ' I p *'.1:.-./':<:1',::-Y,<.;\.'1}' *~~*- ~: ...~:.:~

. "'; *- -~*

~-i_: - -

I ...

'1

  • oc038 7:-_0019C-NL04

Nuclear Regulatory Commission 2 Palisades Plant Request for Restart Authorization March 26, 1987 You were notified by two previous letters from Consumers Power Company of a plant operability limitation based on service water temperature of 53°F. Our December 2, 1986 submittal contained a Technical Specification change that imposed the 53°F limit and a subsequent February 25, 1987 letter contained additional information in support of the limit. Although it is our intent to request withdrawal of our December 2, 1986 Technical Specification Change Request; we will comply with the temperature limit until we have submitted and received NRC review and approval of an evaluation that justifies operation at higher service water temperatures. Consumers Power Company considers this 53°F plant operability limitation a commitment and as such may be confirmed by NRC via issuance of a Confirmatory Action Letter (CAL).

Consumers Power Company requests approval for the restart of the Palisades Plant.

<i!f:/!:f:J~

Vice President Nuclear Operations CC NRC Resident Inspector - Palisades Attachment OC0387-0019C-NL04

POWER ESCALATION COMMITMENTS Submittal Date Commitment 12/01/86 MCTF-FWS-07: Main feedwater pumps - seal water flow returns will be monitored during startup for flow and temperature.

12/01/86 MCTF-FWS-15: Feedwater pump controls loop check/

calibration will have further testing performed at power.*

,. 12/01/86 MCTF-MSS-01; SFE #8 - Mainsteam System: Turbine bypass 1/28/86 valve will have further testing performed at 30% power to verify operability and flow capacity.

12/01/86 MCTF-SWS-03: Exciter air cooler temperature ~ontrol will have follow-up verification performed after generator is on line.

1/28/87 SFE #84 - Turbine Generator: Generator RTD temperature checks to be performed during power escalation.

1/28/87 SFE #85 - Turbine Generator: Manual trip to be tested at less than 15% power.

1/28/87 SFE #33: Hot Leg RTD Time Delay will be measured at power when vendor arrangements can be made.

1/28/87 a) SFE #71 - Circulating Water System - Cooling Tower Pumps: Trend program will monitor performance during power escalation.

b) Additional tests to be performed during power escalation on: Feedwater control voltage regulator, turbine valve, turbine bypass valve, component manipulations to shakedown equipment.

c) Acceptable performance must be met on feedwater pumps, condensate pumps, cooling tower pumps heater drain

  • pumps, turbine, generator, main transformer and startup transformer before escalation to next power level can be made.

AT0387-0019-NL04