ML18324A612: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
| issue date = 11/20/2018
| issue date = 11/20/2018
| title = Ltr. 11/20/18 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2019001 and 05000306/2019001 (DRS-N.Feliz-Adorn
| title = Ltr. 11/20/18 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2019001 and 05000306/2019001 (DRS-N.Feliz-Adorn
| author name = Feliz-Adorno N J
| author name = Feliz-Adorno N
| author affiliation = NRC/RGN-III/DRS/EB2
| author affiliation = NRC/RGN-III/DRS/EB2
| addressee name = Sharp S
| addressee name = Sharp S
Line 14: Line 14:
| page count = 8
| page count = 8
}}
}}
See also: [[followed by::IR 05000282/2019001]]
See also: [[see also::IR 05000282/2019001]]


=Text=
=Text=
{{#Wiki_filter:November 20, 2018
{{#Wiki_filter:November 20, 2018
  Mr. Scott Sharp
Mr. Scott Sharp
Site Vice President
Site Vice President
Prairie Island Nuclear Generating Plant
Prairie Island Nuclear Generating Plant
Northern States Power Company, Minnesota
Northern States Power Company, Minnesota
1717 Wakonade Drive East
1717 Wakonade Drive East
Welch, MN
Welch, MN 55089-9642
55089-9642 SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2
SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2
NOTIFICATION OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION REPORT 05000282/2019001 AND 05000306/2019001
            NOTIFICATION OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE
  Dear Mr. Sharp: On Monday, March 4, 2019, the U.S. Nuclear Regulatory Commission (NRC) will begin the onsite portion of the Triennial Heat Sink Performance Inspection at your
            INSPECTION AND REQUEST FOR INFORMATION; INSPECTION
Prairie Island Nuclear Generating Plant, Units 1 and 2. This inspection will be performed in accordance with NRC baseline Inspection Procedure
            REPORT 05000282/2019001 AND 05000306/2019001
71111.07. In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a request for documents needed for the inspection. The document request
Dear Mr. Sharp:
have been divided into three groups.
On Monday, March 4, 2019, the U.S. Nuclear Regulatory Commission (NRC) will begin the
  The first group lists information necessary for our initial inspection scoping activities. This information should be available to the lead inspector no later than January 7, 2019. By January 18, 2019, the lead inspector will communicate the initial selected set of approximately 2
onsite portion of the Triennial Heat Sink Performance Inspection at your Prairie Island Nuclear
-3 risk significant heat exchangers.
Generating Plant, Units 1 and 2. This inspection will be performed in accordance with NRC
  The second group  
baseline Inspection Procedure 71111.07.
is needed to support our in
In order to minimize the impact that the inspection has on the site and to ensure a productive
-office preparation activities. This set of documents, including the calculations associated with the selected heat exchangers, should be available at the Regional Office no later than
inspection, we have enclosed a request for documents needed for the inspection. The
February 18, 2019. This information should be separated for each selected component, especially if provided electronically (e.g., folder with component name that includes calculations, condition reports, maintenance history, etc
document request have been divided into three groups.
.). During the in
    *  The first group lists information necessary for our initial inspection scoping activities.
-office preparation activities, the inspector may identify additional information needed to support the inspection.
        This information should be available to the lead inspector no later than January 7, 2019.
  The last group  
        By January 18, 2019, the lead inspector will communicate the initial selected set of
is the needed additional information identified during our in
        approximately 2-3 risk significant heat exchangers.
-office preparation activities. This information should be available onsite to the inspector on
    *  The second group is needed to support our in-office preparation activities. This set of
March 4, 2019. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the inspector as the documents are generated.
        documents, including the calculations associated with the selected heat exchangers,
 
        should be available at the Regional Office no later than February 18, 2019. This
S. Sharp -2- All requested documents are to be for the time period from the onsite inspection period
        information should be separated for each selected component, especially if provided
back to the documents that were provided in response to the previous
        electronically (e.g., folder with component name that includes calculations, condition
Heat Sink Performance Inspection. If no activities were accomplished in that time period, then the request applies to the last applicable document in the previous time period.
        reports, maintenance history, etc.). During the in-office preparation activities, the
It is important that these documents be as complete as possible, in order to minimize the number of documents requested during the preparation week or during the onsite inspection.
        inspector may identify additional information needed to support the inspection.
  The lead inspector for this inspection is
    *  The last group is the needed additional information identified during our in-office
Néstor J. Féliz Adorno. We understand that our licensing contact for this inspection is Pamela Johnson
        preparation activities. This information should be available onsite to the inspector on
of your organization. If there are any questions about the inspection or the material requested in the enclosure, please
        March 4, 2019. It is also requested that corrective action documents and/or questions
contact the lead inspector at  
        developed during the inspection be provided to the inspector as the documents are
630-829-9739 or via e-mail at Nestor.Feliz
        generated.
-Adorno@nrc.gov
 
This letter does not contain new or amended information collection requirements subject  
S. Sharp                                     -2-
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150
All requested documents are to be for the time period from the onsite inspection period back
-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.   This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading
to the documents that were provided in response to the previous Heat Sink Performance
-rm/adams.html
Inspection. If no activities were accomplished in that time period, then the request applies to the
and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
last applicable document in the previous time period. It is important that these documents be as
  Sincerely, /RA Michael A. Jones Acting fo
complete as possible, in order to minimize the number of documents requested during the
r/  Néstor J. Féliz Adorno , Senior Reactor Engineer
preparation week or during the onsite inspection.
Engineering Branch 2
The lead inspector for this inspection is Néstor J. Féliz Adorno. We understand that our
Division of Reactor Safety
licensing contact for this inspection is Pamela Johnson of your organization. If there are any
  Docket No. 50
questions about the inspection or the material requested in the enclosure, please contact the
-282; 50-306 License No. DPR-42; DPR-60 Enclosure:
lead inspector at 630-829-9739 or via e-mail at Nestor.Feliz-Adorno@nrc.gov.
Document Request for Triennial Heat Sink
This letter does not contain new or amended information collection requirements subject
  Performance Inspection
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
  cc: Distribution via LISTSERV
collection requirements were approved by the Office of Management and Budget, Control
S. Sharp -3- Letter to Scott Sharp
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
from Néstor J. Féliz Adorno
respond to, a request for information or an information collection requirement unless the
dated November 20, 2018. SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2
requesting document displays a currently valid Office of Management and Budget Control
NOTIFICATION OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR INFORMATION; INSPECTION REPORT 05000282/2019001 AND 05000306/2019001
Number.
  DISTRIBUTION
This letter and its enclosure will be made available for public inspection and copying at
: Christopher Cook
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
RidsNrrPMPrairieIsland Resource
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
RidsNrrDorlLpl3
Exemptions, Requests for Withholding.
RidsNrrDirsIrib Resource
                                              Sincerely,
Steven West
                                              /RA Michael A. Jones Acting for/
Darrell Roberts
                                              Néstor J. Féliz Adorno, Senior Reactor Engineer
Jamnes Cameron
                                              Engineering Branch 2
Allan Barker
                                              Division of Reactor Safety
DRPIII DRSIII                           ADAMS Accession Number: ML18324A612
Docket No. 50-282; 50-306
  OFFICE RIII       NAME MJones for  
License No. DPR-42; DPR-60
NFéliz Adorno:cl   DATE 11/20/18   OFFICIAL RECORD COPY
Enclosure:
 
Document Request for Triennial Heat Sink
DOCUMENT REQUEST FOR  
  Performance Inspection
TRIENNIAL HEAT
cc: Distribution via LISTSERV
SINK PERFORMANCE INSPECTION
 
Enclosure Inspection Report
S. Sharp                                     -3-
: 05000282/2019001; 05000306/2019001
Letter to Scott Sharp from Néstor J. Féliz Adorno dated November 20, 2018.
  Inspection Dates
SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2
: March 4, 2019, through March 8, 2019   Inspection Procedure
            NOTIFICATION OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE
: Inspection  
            INSPECTION AND REQUEST FOR INFORMATION; INSPECTION
Procedure 71111.07, "Heat Sink Performance"
            REPORT 05000282/2019001 AND 05000306/2019001
  Lead Inspector
DISTRIBUTION:
: Néstor J. Féliz Adorno
Christopher Cook
630-829-9739 Nestor.Feliz
RidsNrrPMPrairieIsland Resource
-Adorno@nrc.gov
RidsNrrDorlLpl3
  I. Information Requested By January 7, 2019
RidsNrrDirsIrib Resource
  1. List of the Generic Letter (GL) 8
Steven West
9-13, "Service Water System Problems Affecting Safety-Related Equipment,"
Darrell Roberts
heat exchangers in order of risk significance.
Jamnes Cameron
  2. Copy of heat exchanger performance trending data tracked for each GL 89
Allan Barker
-13 heat exchanger.
DRPIII
  3. List of Corrective Action Program
DRSIII
documents (with a short description) associated with GL 89
ADAMS Accession Number: ML18324A612
-13 heat exchangers, heat sinks, silting, corrosion, fouling, or heat exchanger testing, for the previous  
  OFFICE RIII
3 years or since the last Corrective Action Program document list was sent to the
NAME       MJones for NFéliz
U.S. Nuclear Regulatory Commission for the previous heat sink performance inspection.
            Adorno:cl
  4. Copy of any self
DATE       11/20/18
-assessment done on any of GL 89
                                  OFFICIAL RECORD COPY
-13 heat exchangers.
 
  5. Last two System Health Report(s) and maintenance rule system notebooks for all the GL 89-13 heat exchangers.
  DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
  6. List of engineering
Inspection Report:           05000282/2019001; 05000306/2019001
-related operator workarounds
Inspection Dates:           March 4, 2019, through March 8, 2019
(with a short description)
Inspection Procedure:       Inspection Procedure 71111.07, Heat Sink Performance
associated with GL 89
Lead Inspector:             Néstor J. Féliz Adorno
-13 heat exchangers. The requested documents are to be for the time period from the onsite inspection period back to the
                            630-829-9739
documents that were provided in response to the previous
                            Nestor.Feliz-Adorno@nrc.gov
heat sink performance  
I.     Information Requested By January 7, 2019
inspectio n.  7. List of permanent and temporary modifications
      1.   List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting
(with a short description)
            Safety-Related Equipment, heat exchangers in order of risk significance.
associated with GL 89
      2.   Copy of heat exchanger performance trending data tracked for each GL 89-13
-13 heat exchangers. The requested documents are to be for the time period from the onsite inspection period back to the
            heat exchanger.
documents that were provided in response to the previous
      3.   List of Corrective Action Program documents (with a short description)
heat sink performance  
            associated with GL 89-13 heat exchangers, heat sinks, silting, corrosion, fouling,
inspectio n.  8. Provide a list of any design change (with a short description) performed on the Ultimate Heat Sink (UHS) or safety-related service water systems.
            or heat exchanger testing, for the previous 3 years or since the last Corrective
The requested documents are to be for the time period from the onsite inspection period back to the
            Action Program document list was sent to the U.S. Nuclear Regulatory
documents that were provided in response to the previous
            Commission for the previous heat sink performance inspection.
heat sink performance inspectio n.
      4.   Copy of any self-assessment done on any of GL 89-13 heat exchangers.
DOCUMENT REQUEST FOR  
      5.   Last two System Health Report(s) and maintenance rule system notebooks for all
TRIENNIAL HEAT
            the GL 89-13 heat exchangers.
SINK PERFORMANCE INSPECTION
      6.   List of engineering-related operator workarounds (with a short description)
2 9. Electronic copies of Updated Final Safety Analysis Report, Technical Specifications, Technical Specifications Bases, and Technical Requirements Manual. II Information Requested By February 18, 2019
            associated with GL 89-13 heat exchangers. The requested documents are to be
  1. Copies of the GL 89
            for the time period from the onsite inspection period back to the documents that
-13 responses.
            were provided in response to the previous heat sink performance inspection.
  2. Copies of procedures developed to implement the recommendations of GL 89
      7.   List of permanent and temporary modifications (with a short description)
-13 (e.g., the GL 89-13 Heat Exchanger Program description).
            associated with GL 89-13 heat exchangers. The requested documents are to be
  3. Copies of the selected corrective action program documents.
            for the time period from the onsite inspection period back to the documents that
  4. Copies of the selected modifications, if any.
            were provided in response to the previous heat sink performance inspection.
  5. For the specific heat exchangers selected:
      8.   Provide a list of any design change (with a short description) performed on
  a. Copy of system description and design basis document for the heat exchangers (as applicable).
            the Ultimate Heat Sink (UHS) or safety-related service water systems. The
  b. Copy of the construction code, Design Specification, heat exchanger data sheets, and vendor documents including component drawings applicable for the heat exchangers.
            requested documents are to be for the time period from the onsite inspection
  c. Copy of the following calculations for each selected heat exchanger
            period back to the documents that were provided in response to the previous
that: i. establish the limiting design basis heat load required to be removed by each of these heat exchangers;
            heat sink performance inspection.
  ii. demonstrate the heat exchangers capacity to remove the limiting heat load; iii. correlate surveillance testing and/or inspection results from these heat exchangers with design basis
                                                                                      Enclosure
heat removal capability (e.g., basis for surveillance test and/or inspection acceptance criteria);
 
  iv. evaluate the potential for water hammer in each heat exchanger or associated piping; and  
  DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
  v. evaluate excessive tube vibration in each heat exchanger.
    9.   Electronic copies of Updated Final Safety Analysis Report, Technical
  d. Copy of any operability determinations or other documentation of degradation associated with the heat exchangers or the systems that support the operation for the selected heat exchangers.
          Specifications, Technical Specifications Bases, and Technical Requirements
  e. Copies of normal, abnormal, and emergency operating procedures associated with the selected heat exchangers.
          Manual.
  f. Copy of the operating procedure that ensures that the maximum cooling water system inlet temperature limit is not exceeded.
II   Information Requested By February 18, 2019
 
    1.   Copies of the GL 89-13 responses.
DOCUMENT REQUEST FOR  
    2.   Copies of procedures developed to implement the recommendations of GL 89-13
TRIENNIAL HEAT
          (e.g., the GL 89-13 Heat Exchanger Program description).
SINK PERFORMANCE INSPECTION
    3.   Copies of the selected corrective action program documents.
3 g. Copies of those documents that describe the methods taken to control water chemistry in the heat exchangers
    4.   Copies of the selected modifications, if any.
h. Copies of the two most recent completed tests and evaluation data confirming thermal performance for those heat exchangers which are performance tested.
    5.   For the specific heat exchangers selected:
  i. Documentation and procedures that identify the types, accuracy, and location
          a. Copy of system description and design basis document for the heat
of any special instrumentation used for the two most recently completed thermal performance tests for the heat exchangers (e.g., high accuracy ultrasonic flow instruments or temperature instruments). Include calibration records for the instruments used during these tests.
                exchangers (as applicable).
  j. Information regarding any alarms which monitor on
          b. Copy of the construction code, Design Specification, heat exchanger data
-line performance.
                sheets, and vendor documents including component drawings applicable for
  k. Copy of the periodic flow testing at or near maximum design flow. The
                the heat exchangers.
requested documents are to be for the time period from the onsite inspection period back to the
          c. Copy of the following calculations for each selected heat exchanger that:
documents that were provided in response to the previous
                i. establish the limiting design basis heat load required to be removed by
heat sink performance  
                    each of these heat exchangers;
inspectio nl. Copy of the document which identifies the current number of tubes in service for each heat exchanger and the supporting calculation which establishes the maximum number of tubes which can be plugged in each heat exchanger
                ii. demonstrate the heat exchangers capacity to remove the limiting heat
m. Copy of the document establishing the repair criteria (plugging limit) for degraded tubes which are identified in each heat exchanger
                    load;
n. Copies of the documents that verify the structural integrity of the heat exchanger (e.g., eddy current summary sheets, ultrasonic testing results, and visual inspection results)
              iii. correlate surveillance testing and/or inspection results from these heat
o. The cleaning and inspection maintenance schedule for each heat exchanger for the next 5 years.
                    exchangers with design basis heat removal capability (e.g., basis for
   6. For the UHS and the safety
                    surveillance test and/or inspection acceptance criteria);
-related service water system (or equivalent):
              iv. evaluate the potential for water hammer in each heat exchanger or
  a. Copy of system description and design basis document (as applicable).
                    associated piping; and
  b. Copy of any operability determinations or other documentation of degradation associated with the UHS and the safety
                v. evaluate excessive tube vibration in each heat exchanger.
-related service water system
          d. Copy of any operability determinations or other documentation of degradation
c. Copy of the document (e.g., Technical Requirements Manual, procedure) that states the maximum cooling water system inlet temperature limit that still allows full licensed power operation of the nuclear reactor.
                associated with the heat exchangers or the systems that support the
  d. Copy of the construction code and Design Specification.
                operation for the selected heat exchangers.
  e. Copies of normal, abnormal, and emergency operating procedures associated with the UHS and safety
          e. Copies of normal, abnormal, and emergency operating procedures
-related service water systems including procedures for loss of these systems.
                associated with the selected heat exchangers.
 
          f.   Copy of the operating procedure that ensures that the maximum cooling
DOCUMENT REQUEST FOR  
                water system inlet temperature limit is not exceeded.
TRIENNIAL HEAT
                                              2
SINK PERFORMANCE INSPECTION
 
4 f. Copies of corrective action documents associated with waterhammer or hydraulic transients in the service water system since the last Heat Sink Inspection.
DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
  g. If available, provide an electronic copy of piping and instrumentation diagrams for the service water system, including the intake structure.
      g. Copies of those documents that describe the methods taken to control water
  h. Provide a list of calculations (with a short description), which currently apply to UHS and safety-related service water system.
          chemistry in the heat exchangers.
  i. Provide a list of instruments (with a short description) associated with automatic or alarm functions for the safety
      h. Copies of the two most recent completed tests and evaluation data
-related service water system and/or UHS.
          confirming thermal performance for those heat exchangers which are
  j. Copies of calculations and surveillances that determine the UHS reservoir capacity and heat transfer capability.
          performance tested.
  k. Copies of the documents associated with the monitoring, trending, and remediation of silt accumulation at the
      i. Documentation and procedures that identify the types, accuracy, and location
service water pump bay.
          of any special instrumentation used for the two most recently completed
  l. Copies of surveillance procedures and testing results performed
          thermal performance tests for the heat exchangers (e.g., high accuracy
on the instrumentation relied upon to determine UHS reservoir capability. The requested documents are to be for the time period from the onsite inspection period back to the documents that were provided in response to the previous
          ultrasonic flow instruments or temperature instruments). Include calibration
heat sink performance  
          records for the instruments used during these tests.
inspectio n.  m. Inspections and/or maintenance related to preventing macrofouling (e.g.
      j. Information regarding any alarms which monitor on-line performance.
, silt, dead mussel shells, or debris) and biotic fouling (e.g.
      k. Copy of the periodic flow testing at or near maximum design flow. The
, fish, algae, grass, or kelp). The requested documents are to be for the time period from the onsite inspection period back to the
          requested documents are to be for the time period from the onsite inspection
documents that were provided in response to the previous
          period back to the documents that were provided in response to the previous
heat sink performance  
          heat sink performance inspection.
inspectio n.  n. Copies of documents associated with the monitoring of pump performance for potential strong
      l.  Copy of the document which identifies the current number of tubes in service
-pump vs. weak
          for each heat exchanger and the supporting calculation which establishes the
-pump interaction.
          maximum number of tubes which can be plugged in each heat exchanger.
  o. Copies of the last two performance tests, such as the American Society of Mechanical Engineers
      m. Copy of the document establishing the repair criteria (plugging limit) for
in-service test, for the pumps and valves. If the components are not performance tested, please provide documentation verifying performance by the methods actually used.
          degraded tubes which are identified in each heat exchanger.
  p. Copies of the documents that demonstrate that flow balance testing was performed during the last  
      n. Copies of the documents that verify the structural integrity of the heat
3 years. If the last flow test was performed longer than 3 years, then provide the last flow test.
          exchanger (e.g., eddy current summary sheets, ultrasonic testing results,
  q. Copies of procedures used to monitor interface valves between the safety-related section of the service water system and the nonsafety-related section and the associated results. The requested documents are to be for the time period from the onsite inspection period back to the
          and visual inspection results).
documents that were provided in response to the previous
      o. The cleaning and inspection maintenance schedule for each heat exchanger
heat sink performance  
          for the next 5 years.
inspectio n.  
   6. For the UHS and the safety-related service water system (or equivalent):
DOCUMENT REQUEST FOR  
      a. Copy of system description and design basis document (as applicable).
TRIENNIAL HEAT
      b. Copy of any operability determinations or other documentation of degradation
SINK PERFORMANCE INSPECTION
          associated with the UHS and the safety-related service water system.
5 r. Copies of the procedures that verify the performance of risk significant  
      c. Copy of the document (e.g., Technical Requirements Manual, procedure) that
non-safety functions and the associated results. The requested documents are to be for the time period from the onsite inspection period back to the
          states the maximum cooling water system inlet temperature limit that still
documents that were provided in response to the previous heat sink performance  
          allows full licensed power operation of the nuclear reactor.
inspectio n.  s. Copies of the testing, inspection, or monitoring program procedures for buried or inaccessible piping and the associated results. The requested documents are to be for the time period from the onsite inspection period back to the
      d. Copy of the construction code and Design Specification.
documents that were provided in response to the previous
      e. Copies of normal, abnormal, and emergency operating procedures
heat sink performance  
          associated with the UHS and safety-related service water systems including
inspectio nt. History of any thru wall pipe leak on the system. The requested documents are to be for the time period from the onsite inspection period back to th
          procedures for loss of these systems.
e documents that were provided in response to the previous
                                        3
heat sink performance  
 
inspectio n.  u. Copies of the documents associated with the Periodic Inspection Program used to detect protective coating failure, corrosion, and erosion.
DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
  v. Copies of the  
      f. Copies of corrective action documents associated with waterhammer or
in-service test vibration monitoring results and operational history for deep draft vertical pumps, if applicable. The requested documents are to be for the time period from the onsite inspection period back to the
          hydraulic transients in the service water system since the last Heat Sink
documents that were provided in response to the previous heat sink performance  
          Inspection.
inspectio n.  7. A schedule of all inspections, cleanings, maintenance, or testing of  
      g. If available, provide an electronic copy of piping and instrumentation
any safety-related plant
          diagrams for the service water system, including the intake structure.
heat exchanger to be performed during the onsite portion  
      h. Provide a list of calculations (with a short description), which currently apply
of the inspection
          to UHS and safety-related service water system.
III Information Requested to be Available on First Day of Inspection, March 4, 2019
      i. Provide a list of instruments (with a short description) associated with
  1. During the in
          automatic or alarm functions for the safety-related service water system
-office preparation activities, the team will be making final selections and may identify additional information needed to support the inspection. The lead inspector will provide a list of  
          and/or UHS.
any additional information needed during the week of February 25, 2019.
      j. Copies of calculations and surveillances that determine the UHS reservoir
  If you have questions regarding the information requested, please contact the lead inspector.
          capacity and heat transfer capability.
      k. Copies of the documents associated with the monitoring, trending, and
          remediation of silt accumulation at the service water pump bay.
      l. Copies of surveillance procedures and testing results performed on the
          instrumentation relied upon to determine UHS reservoir capability. The
          requested documents are to be for the time period from the onsite inspection
          period back to the documents that were provided in response to the previous
          heat sink performance inspection.
      m. Inspections and/or maintenance related to preventing macrofouling (e.g., silt,
          dead mussel shells, or debris) and biotic fouling (e.g., fish, algae, grass, or
          kelp). The requested documents are to be for the time period from the onsite
          inspection period back to the documents that were provided in response to
          the previous heat sink performance inspection.
      n. Copies of documents associated with the monitoring of pump performance for
          potential strong-pump vs. weak-pump interaction.
      o. Copies of the last two performance tests, such as the American Society of
          Mechanical Engineers in-service test, for the pumps and valves. If the
          components are not performance tested, please provide documentation
          verifying performance by the methods actually used.
      p. Copies of the documents that demonstrate that flow balance testing was
          performed during the last 3 years. If the last flow test was performed longer
          than 3 years, then provide the last flow test.
      q. Copies of procedures used to monitor interface valves between the
          safety-related section of the service water system and the nonsafety-related
          section and the associated results. The requested documents are to be for
          the time period from the onsite inspection period back to the documents that
          were provided in response to the previous heat sink performance inspection.
                                        4
 
    DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION
              r. Copies of the procedures that verify the performance of risk significant
                  non-safety functions and the associated results. The requested documents
                  are to be for the time period from the onsite inspection period back to the
                  documents that were provided in response to the previous heat sink
                  performance inspection.
              s. Copies of the testing, inspection, or monitoring program procedures for buried
                  or inaccessible piping and the associated results. The requested documents
                  are to be for the time period from the onsite inspection period back to the
                  documents that were provided in response to the previous heat sink
                  performance inspection.
              t.  History of any thru wall pipe leak on the system. The requested documents
                  are to be for the time period from the onsite inspection period back to the
                  documents that were provided in response to the previous heat sink
                  performance inspection.
              u. Copies of the documents associated with the Periodic Inspection Program
                  used to detect protective coating failure, corrosion, and erosion.
              v. Copies of the in-service test vibration monitoring results and operational
                  history for deep draft vertical pumps, if applicable. The requested documents
                  are to be for the time period from the onsite inspection period back to the
                  documents that were provided in response to the previous heat sink
                  performance inspection.
        7.     A schedule of all inspections, cleanings, maintenance, or testing of any
              safety-related plant heat exchanger to be performed during the onsite portion
              of the inspection.
III     Information Requested to be Available on First Day of Inspection, March 4, 2019
            1. During the in-office preparation activities, the team will be making final selections
              and may identify additional information needed to support the inspection. The
              lead inspector will provide a list of any additional information needed during the
              week of February 25, 2019.
If you have questions regarding the information requested, please contact the lead inspector.
                                                  5
}}
}}

Latest revision as of 11:24, 20 October 2019

Ltr. 11/20/18 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2019001 and 05000306/2019001 (DRS-N.Feliz-Adorn
ML18324A612
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 11/20/2018
From: Nestor Feliz-Adorno
NRC/RGN-III/DRS/EB2
To: Sharp S
Northern States Power Company, Minnesota
References
IR 2019001
Download: ML18324A612 (8)


See also: IR 05000282/2019001

Text

November 20, 2018

Mr. Scott Sharp

Site Vice President

Prairie Island Nuclear Generating Plant

Northern States Power Company, Minnesota

1717 Wakonade Drive East

Welch, MN 55089-9642

SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2

NOTIFICATION OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE

INSPECTION AND REQUEST FOR INFORMATION; INSPECTION

REPORT 05000282/2019001 AND 05000306/2019001

Dear Mr. Sharp:

On Monday, March 4, 2019, the U.S. Nuclear Regulatory Commission (NRC) will begin the

onsite portion of the Triennial Heat Sink Performance Inspection at your Prairie Island Nuclear

Generating Plant, Units 1 and 2. This inspection will be performed in accordance with NRC

baseline Inspection Procedure 71111.07.

In order to minimize the impact that the inspection has on the site and to ensure a productive

inspection, we have enclosed a request for documents needed for the inspection. The

document request have been divided into three groups.

  • The first group lists information necessary for our initial inspection scoping activities.

This information should be available to the lead inspector no later than January 7, 2019.

By January 18, 2019, the lead inspector will communicate the initial selected set of

approximately 2-3 risk significant heat exchangers.

  • The second group is needed to support our in-office preparation activities. This set of

documents, including the calculations associated with the selected heat exchangers,

should be available at the Regional Office no later than February 18, 2019. This

information should be separated for each selected component, especially if provided

electronically (e.g., folder with component name that includes calculations, condition

reports, maintenance history, etc.). During the in-office preparation activities, the

inspector may identify additional information needed to support the inspection.

  • The last group is the needed additional information identified during our in-office

preparation activities. This information should be available onsite to the inspector on

March 4, 2019. It is also requested that corrective action documents and/or questions

developed during the inspection be provided to the inspector as the documents are

generated.

S. Sharp -2-

All requested documents are to be for the time period from the onsite inspection period back

to the documents that were provided in response to the previous Heat Sink Performance

Inspection. If no activities were accomplished in that time period, then the request applies to the

last applicable document in the previous time period. It is important that these documents be as

complete as possible, in order to minimize the number of documents requested during the

preparation week or during the onsite inspection.

The lead inspector for this inspection is Néstor J. Féliz Adorno. We understand that our

licensing contact for this inspection is Pamela Johnson of your organization. If there are any

questions about the inspection or the material requested in the enclosure, please contact the

lead inspector at 630-829-9739 or via e-mail at Nestor.Feliz-Adorno@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

/RA Michael A. Jones Acting for/

Néstor J. Féliz Adorno, Senior Reactor Engineer

Engineering Branch 2

Division of Reactor Safety

Docket No. 50-282; 50-306

License No. DPR-42; DPR-60

Enclosure:

Document Request for Triennial Heat Sink

Performance Inspection

cc: Distribution via LISTSERV

S. Sharp -3-

Letter to Scott Sharp from Néstor J. Féliz Adorno dated November 20, 2018.

SUBJECT: PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2

NOTIFICATION OF AN NRC TRIENNIAL HEAT SINK PERFORMANCE

INSPECTION AND REQUEST FOR INFORMATION; INSPECTION

REPORT 05000282/2019001 AND 05000306/2019001

DISTRIBUTION:

Christopher Cook

RidsNrrPMPrairieIsland Resource

RidsNrrDorlLpl3

RidsNrrDirsIrib Resource

Steven West

Darrell Roberts

Jamnes Cameron

Allan Barker

DRPIII

DRSIII

ADAMS Accession Number: ML18324A612

OFFICE RIII

NAME MJones for NFéliz

Adorno:cl

DATE 11/20/18

OFFICIAL RECORD COPY

DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION

Inspection Report: 05000282/2019001; 05000306/2019001

Inspection Dates: March 4, 2019, through March 8, 2019

Inspection Procedure: Inspection Procedure 71111.07, Heat Sink Performance

Lead Inspector: Néstor J. Féliz Adorno

630-829-9739

Nestor.Feliz-Adorno@nrc.gov

I. Information Requested By January 7, 2019

1. List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting

Safety-Related Equipment, heat exchangers in order of risk significance.

2. Copy of heat exchanger performance trending data tracked for each GL 89-13

heat exchanger.

3. List of Corrective Action Program documents (with a short description)

associated with GL 89-13 heat exchangers, heat sinks, silting, corrosion, fouling,

or heat exchanger testing, for the previous 3 years or since the last Corrective

Action Program document list was sent to the U.S. Nuclear Regulatory

Commission for the previous heat sink performance inspection.

4. Copy of any self-assessment done on any of GL 89-13 heat exchangers.

5. Last two System Health Report(s) and maintenance rule system notebooks for all

the GL 89-13 heat exchangers.

6. List of engineering-related operator workarounds (with a short description)

associated with GL 89-13 heat exchangers. The requested documents are to be

for the time period from the onsite inspection period back to the documents that

were provided in response to the previous heat sink performance inspection.

7. List of permanent and temporary modifications (with a short description)

associated with GL 89-13 heat exchangers. The requested documents are to be

for the time period from the onsite inspection period back to the documents that

were provided in response to the previous heat sink performance inspection.

8. Provide a list of any design change (with a short description) performed on

the Ultimate Heat Sink (UHS) or safety-related service water systems. The

requested documents are to be for the time period from the onsite inspection

period back to the documents that were provided in response to the previous

heat sink performance inspection.

Enclosure

DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION

9. Electronic copies of Updated Final Safety Analysis Report, Technical

Specifications, Technical Specifications Bases, and Technical Requirements

Manual.

II Information Requested By February 18, 2019

1. Copies of the GL 89-13 responses.

2. Copies of procedures developed to implement the recommendations of GL 89-13

(e.g., the GL 89-13 Heat Exchanger Program description).

3. Copies of the selected corrective action program documents.

4. Copies of the selected modifications, if any.

5. For the specific heat exchangers selected:

a. Copy of system description and design basis document for the heat

exchangers (as applicable).

b. Copy of the construction code, Design Specification, heat exchanger data

sheets, and vendor documents including component drawings applicable for

the heat exchangers.

c. Copy of the following calculations for each selected heat exchanger that:

i. establish the limiting design basis heat load required to be removed by

each of these heat exchangers;

ii. demonstrate the heat exchangers capacity to remove the limiting heat

load;

iii. correlate surveillance testing and/or inspection results from these heat

exchangers with design basis heat removal capability (e.g., basis for

surveillance test and/or inspection acceptance criteria);

iv. evaluate the potential for water hammer in each heat exchanger or

associated piping; and

v. evaluate excessive tube vibration in each heat exchanger.

d. Copy of any operability determinations or other documentation of degradation

associated with the heat exchangers or the systems that support the

operation for the selected heat exchangers.

e. Copies of normal, abnormal, and emergency operating procedures

associated with the selected heat exchangers.

f. Copy of the operating procedure that ensures that the maximum cooling

water system inlet temperature limit is not exceeded.

2

DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION

g. Copies of those documents that describe the methods taken to control water

chemistry in the heat exchangers.

h. Copies of the two most recent completed tests and evaluation data

confirming thermal performance for those heat exchangers which are

performance tested.

i. Documentation and procedures that identify the types, accuracy, and location

of any special instrumentation used for the two most recently completed

thermal performance tests for the heat exchangers (e.g., high accuracy

ultrasonic flow instruments or temperature instruments). Include calibration

records for the instruments used during these tests.

j. Information regarding any alarms which monitor on-line performance.

k. Copy of the periodic flow testing at or near maximum design flow. The

requested documents are to be for the time period from the onsite inspection

period back to the documents that were provided in response to the previous

heat sink performance inspection.

l. Copy of the document which identifies the current number of tubes in service

for each heat exchanger and the supporting calculation which establishes the

maximum number of tubes which can be plugged in each heat exchanger.

m. Copy of the document establishing the repair criteria (plugging limit) for

degraded tubes which are identified in each heat exchanger.

n. Copies of the documents that verify the structural integrity of the heat

exchanger (e.g., eddy current summary sheets, ultrasonic testing results,

and visual inspection results).

o. The cleaning and inspection maintenance schedule for each heat exchanger

for the next 5 years.

6. For the UHS and the safety-related service water system (or equivalent):

a. Copy of system description and design basis document (as applicable).

b. Copy of any operability determinations or other documentation of degradation

associated with the UHS and the safety-related service water system.

c. Copy of the document (e.g., Technical Requirements Manual, procedure) that

states the maximum cooling water system inlet temperature limit that still

allows full licensed power operation of the nuclear reactor.

d. Copy of the construction code and Design Specification.

e. Copies of normal, abnormal, and emergency operating procedures

associated with the UHS and safety-related service water systems including

procedures for loss of these systems.

3

DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION

f. Copies of corrective action documents associated with waterhammer or

hydraulic transients in the service water system since the last Heat Sink

Inspection.

g. If available, provide an electronic copy of piping and instrumentation

diagrams for the service water system, including the intake structure.

h. Provide a list of calculations (with a short description), which currently apply

to UHS and safety-related service water system.

i. Provide a list of instruments (with a short description) associated with

automatic or alarm functions for the safety-related service water system

and/or UHS.

j. Copies of calculations and surveillances that determine the UHS reservoir

capacity and heat transfer capability.

k. Copies of the documents associated with the monitoring, trending, and

remediation of silt accumulation at the service water pump bay.

l. Copies of surveillance procedures and testing results performed on the

instrumentation relied upon to determine UHS reservoir capability. The

requested documents are to be for the time period from the onsite inspection

period back to the documents that were provided in response to the previous

heat sink performance inspection.

m. Inspections and/or maintenance related to preventing macrofouling (e.g., silt,

dead mussel shells, or debris) and biotic fouling (e.g., fish, algae, grass, or

kelp). The requested documents are to be for the time period from the onsite

inspection period back to the documents that were provided in response to

the previous heat sink performance inspection.

n. Copies of documents associated with the monitoring of pump performance for

potential strong-pump vs. weak-pump interaction.

o. Copies of the last two performance tests, such as the American Society of

Mechanical Engineers in-service test, for the pumps and valves. If the

components are not performance tested, please provide documentation

verifying performance by the methods actually used.

p. Copies of the documents that demonstrate that flow balance testing was

performed during the last 3 years. If the last flow test was performed longer

than 3 years, then provide the last flow test.

q. Copies of procedures used to monitor interface valves between the

safety-related section of the service water system and the nonsafety-related

section and the associated results. The requested documents are to be for

the time period from the onsite inspection period back to the documents that

were provided in response to the previous heat sink performance inspection.

4

DOCUMENT REQUEST FOR TRIENNIAL HEAT SINK PERFORMANCE INSPECTION

r. Copies of the procedures that verify the performance of risk significant

non-safety functions and the associated results. The requested documents

are to be for the time period from the onsite inspection period back to the

documents that were provided in response to the previous heat sink

performance inspection.

s. Copies of the testing, inspection, or monitoring program procedures for buried

or inaccessible piping and the associated results. The requested documents

are to be for the time period from the onsite inspection period back to the

documents that were provided in response to the previous heat sink

performance inspection.

t. History of any thru wall pipe leak on the system. The requested documents

are to be for the time period from the onsite inspection period back to the

documents that were provided in response to the previous heat sink

performance inspection.

u. Copies of the documents associated with the Periodic Inspection Program

used to detect protective coating failure, corrosion, and erosion.

v. Copies of the in-service test vibration monitoring results and operational

history for deep draft vertical pumps, if applicable. The requested documents

are to be for the time period from the onsite inspection period back to the

documents that were provided in response to the previous heat sink

performance inspection.

7. A schedule of all inspections, cleanings, maintenance, or testing of any

safety-related plant heat exchanger to be performed during the onsite portion

of the inspection.

III Information Requested to be Available on First Day of Inspection, March 4, 2019

1. During the in-office preparation activities, the team will be making final selections

and may identify additional information needed to support the inspection. The

lead inspector will provide a list of any additional information needed during the

week of February 25, 2019.

If you have questions regarding the information requested, please contact the lead inspector.

5