ML20217M57120 October 1999Forwards Insp Repts 50-445/99-15 & 50-446/99-15 on 990822- 1002.Two Severity Level IV Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy
ML20217K90915 October 1999Forwards SER Accepting Util 990609 Relief Request RR-ENG-2-3 from ASME Code,Section Xi,Nondestructive Exam Requirements Applicable to South Texas Project,Units 1 & 2, Pressurizer Support Attachment WeldsNondestructive Examination
ML20217K93415 October 1999Forwards SER Accepting Util 990609 Relief Request RR-ENG-2-4 for Relief from ASME Code,Section XI, Nondestructive Exam Requirements Applicable to Stp,Units 1 & 2,reactor Vessel Closure Head Nuts
ML20217C3227 October 1999Forwards Insp Repts 50-498/99-16 & 50-499/99-16 on 990808-0918.No Violations Noted.Insp Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Careful Radiological Work Controls
ML20212L2891 October 1999Discusses Closeout of GL 97-06, Degradation of Steam Generator Internals. Purpose of GL Was to Obtain Info That Would Enable NRC to Verify That Condition of Licensee SG Internals Comply with Current Licensing Bases
ML20212L16530 September 1999Responds to STP Nuclear Operating Co 981012 & s Which Provided Update to TS Bases Pages B 3/4 8-14 Through B 3/4 8-17.NRC Staff Found Change Consistent with TS 3/4.8.2 DC Sources. Staff Found & Deleted Typographical ErrorBattery sizing
ML20212J71429 September 1999Forwards Insp Repts 50-498/99-15 & 50-499/99-15 on 990920-24 at South Texas Project Electric Generating Station.No Violations Noted.Insp Covered Requalification Training Program & Observation of Requalification Activities
ML20212J06527 September 1999Discusses Licensee 980330 Response to GL 97-06, Degradation of SG Internals. Concludes That Response to GL Provides Reasonable Assurance That Condition of SG Internals in Compliance with Current Licensing Bases for Facility
ML20212F74824 September 1999Forwards SER Authorizing Relief from Exam Requirement of 1986 Edition ASME Code,Section XI Pursuant to 10CFR50.55a(a)(3)(ii) for Relief Request A-3 & 10CFR50.55a(g)(6)(i) for Relief Requests B15,16,17 & C-4
ML20212F17924 September 1999Discusses 990923 Meeting Conducted in Region IV Ofc Re Status of Activities to Support Confirmatory Order, ,modifying OL & to Introduce New Director,Safety Quality Concerns Program.List of Attendees Encl
ML20212F10423 September 1999Requests That NRC Be Informed of Any Changes in Scope of Y2K System Deficiencies Listed or Util Projected Completion Schedule for Comanche Peak Steam Electric Station,Units 1 & 2
ML20212E90923 September 1999Discusses GL 98-01, Year 2000 Readiness of Computer Sys at Npps, Supplement 1 & STP Nuclear Operating Co Response for STP Dtd 990629.Understands That at Least One Sys or Component Listed May Have Potential to Cause Transient
ML20212F21122 September 1999Forwards Review of SG 90-day Rept, South Texas Unit-2 Cycle 7 Voltage-Based Repair Criteria Rept, Submitted by Util on 990119
ML20212E66621 September 1999Advises That Info Contained in Application & Affidavit, (CAW-99-1342) Re WCAP-15009,Rev 0, Comache Peak Unit 1 Evaluation for Tube Vibration Induced Fatigue, Will Be Withheld from Public Disclosure
ML20212D91116 September 1999Informs That on 990818,NRC Completed Midcycle PPR of CPSES & Did Not Identify Any Areas in Which Performance Warranted Insp Beyond Core Insp Program.Core Insp Plan at Facility Over Next 7 Months.Insp Plan Through March 2000 Encl
ML20212D91716 September 1999Informs That on 990818,NRC Completed Midcycle PPR of South Texas Project & Identified No Areas in Which Performance Warranted Insp Beyond Core Insp Program.Details of Insp Plan Through Mar 2000 & Historical Listing of Plant Issues,Encl
ML20216F54715 September 1999Discusses 990914 Meeting Conducted at Region Iv.Meeting Was Requested by Staff to Introduce New Management Organization to Region IV & to Discuss General Plant Performance & Mgt Challenges
ML20212A76014 September 1999Forwards Insp Repts 50-445/99-14 & 50-446/99-14 on 990707-0821.Four Violations Occurred & Being Treated as Ncvs.Conduct of Activities Was Generally Characterized by safety-conscious Operations & Sound Radiological Controls
IR 05000498/199901214 September 1999Forwards Insp Repts 50-498/99-12 & 50-499/99-12 on 990816-19.Three Violations Occurred & Being Treated as Ncvs. Areas Examined During Insp Included Portions of Access Authorization & Physical Security Programs
ML20211P8209 September 1999Forwards SE Authorizing 990224 Submittal of First 10-year Interval ISI Program Plan - Relief Request RR-ENG-24,from ASME Section XI Code,Table IWC-2500-1
ML20211P7879 September 1999Forwards Safety Evaluation Re First 10-yr Interval Inservice Insp Program Plan Request for Relief RR-ENG-31Hydrostatic
ML20211P7679 September 1999Forwards SER Authorizing Licensee 990517 Alternative Proposed in Relief Request RR-ENG-2-8 to Code Case N-491-2 for Second 10-year Insp Interval of South Texas Project, Units 1 & 2,pursuant to 10CFR50.55a(a)(3)(i)
ML20211P3767 September 1999Ack Receipt of Ltr Dtd 990615,transmitting Rev 30 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required
IR 05000498/19990143 September 1999Forwards Insp Repts 50-498/99-14 & 50-499/99-14 on 990627-0807.Apparent Violations Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy
ML20211J38027 August 1999Forwards Corrected TS Page 3.8-26 to Amend 66 to Licenses NPF-87 & NPF-89,respectively.Footnote on TS Page 3.8-26 Incorrectly Deleted
ML20212A43527 August 1999Discusses Investigation Rept OI-4-1999-009 Re Activites at South Texas Project.Oi Investigation Initiated in Response to Alleged Employment Discrimination Complaint. Allegation Not Substantiated.No Further Action Planned
ML20211J25126 August 1999Discusses Proposed TS Change on Replacement SG Water Level Trip Setpoint for Plant,Units 1 & 2
ML20211F44224 August 1999Forwards SE Authorizing Licensee 990513 Request for Relief RR-ENG-2-13,seeking Relief from ASME B&PV Code Section Xi,Exam Vessel shell-to-flange Welds for Second ISI Intervals
ML20211F50323 August 1999Forwards SE Authorizing Licensee 990315 Request for Relief RR-ENG-30,seeking Relief from ASME B&PV Code,Section Xi,Nde Requirements Applicable to Stp,Unit 2 SG WeldsNondestructive Examination
ML20211B28618 August 1999Forwards Insp Repts 50-445/99-13 & 50-446/99-13 on 990720- 23.No Violations Noted.Insp Included Implementation of Licensee Emergency Plan & Procedures During Util Biennial Emergency Preparedness Exercise
ML20211C46618 August 1999Discusses Proprietary Info Re Thermo-Lag.NRC Treated Bisco Test Rept 748-105 as Proprietary & Withheld It from Public Disclosure,Iaw 10CFR2.790
ML20212A43917 August 1999Discusses Investigation Rept OI-4-1999-023 Re Activities at South Texas Project.Oi Investigation Initiated in Response to Alleged Employment Discrimination for Initiating Condition Report to Document Unauthorized Work Practices
ML20211C45716 August 1999Forwards Omitted Subj Page of Contractor TER
ML20210U12716 August 1999Forwards Insp Repts 50-498/99-08 & 50-499/99-08 on 990517-21 & 0607-10.No Violations Noted.Corrective Action Program Was Reviewed
ML20211A95012 August 1999Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl
ML20210R22212 August 1999Forwards Insp Repts 50-445/99-10 & 50-446/99-10 on 990510-0628.Violations Noted & Being Treated as Ncvs, Consistent with App C of Enforcement PolicyEnforcement Discretion
Temporary Modification
Fire Protection Program
ML20211B78810 August 1999Transmits Summary of Two Meetings with Risk-Informed TS Task Force in Rockville,Md on 990514 & 0714Shutdown Margin
Missed surveillance
Large early release frequency
ML20210L1463 August 1999Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for ExamsGeneric Fundamentals Examination
ML20210K23229 July 1999Forwards Insp Repts 50-445/99-12 & 50-446/99-12 on 990530-0710.No Violations Noted
ML20210F38526 July 1999Forwards Exam Repts 50-498/99-301 & 50-499/99-301 on 990706- 15.Exam Included Evaluation of 9 Applicants for SO Licenses & 8 Applicants for RO Licenses
ML20210D82323 July 1999Forwards Safety Evaluation of Relief Requests Re Use of 1998 Edition of Subsections IWE & Iwl of ASME Code for Containment InspIncorporated by reference
ML20210D90123 July 1999Forwards Safety Evaluation Re Inservice Testing Plan Request for Relief RR-5 Component Cooling Water & Safety Injection Sys Containment Isolation Check Valve Closure Test Frequency
ML20210C21121 July 1999Forwards Insp Repts 50-498/99-13 & 50-499/99-13 on 990516-0626.Two Severity Level IV Violations Occurred & Being Treated as Noncited Violations
ML20209H92316 July 1999Discusses South Texas Project,Units 1 & 2 Updated Response to GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity. Staff Revised Info for Plant in Rvid & Being Released as Rvid Version 2
ML20210C33316 July 1999Forwards Exam Repts 50-445/99-301 & 50-446/99-301 on 990618- 24.Exam Included Evaluation of Six Applicants for Senior Operator Licenses
ML20209H75015 July 1999Forwards Safety Evaluation on GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Comanche Peak Steam Electric Station,Units 1 & 2
ML20209G7428 July 1999Forwards SER Concluding That Licensee Individual Plant Exam of External Events Process Capable of Identifying Most Likely Severe Accidents & Severe Accident Vulnerabilities & IPEEE Met Intent of Supp 4 to GL 88-20High winds
ML20196L0128 July 1999Forwards Safety Evaluation Granting First 10-Year Interval Inservice Insp Requests for Relief B-6 (Rev 2),B-7 (Rev 2), B-12,B-13,B-14 & C-9,pursuant to Tile 10CFR50.55a(g)(6)(i)
ML20207H6268 July 1999Responds to Re 2nd 10 Yr Interval ISI Program Plan Request to Use ASME Section XI Code Case N-546, Alternative Requirements for Qualification of VT-2 Exam Personnel,Section Xi,Division 1.Forwards SEVT-2
ML20196K6772 July 1999Ack Receipt of & Encl Scenario for Comanche Peak Steam Electric Station Emergency Plan Exercise Scheduled for 990721-22.Determined That Exercise Scenario Sufficient to Meet Emergency Plan Requirements & Exercise Objectives