PLA-0059, November 2005 Operating Report for Susquehanna, Units 1 and 2

From kanterella
Jump to navigation Jump to search
November 2005 Operating Report for Susquehanna, Units 1 and 2
ML053630255
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 12/12/2005
From: Saccone R
Susquehanna
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PLA-005998
Download: ML053630255 (7)


Text

I it a *4 Robert A. Saccone Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem /Boulevard Berwick, PA 18603 IN.m--pp T Tel. 570.542.3959 Fax 570.542.1504 .. TM RASaccone pplweb.com December 12,2005 U. S. Nuciear Regulatory Commission Attn: Document Control Desk Maii Stop O-PI-17 Washington, D.C. 20555-0001 SUSQUEHANNA STEAM ELECTRIC STATION MONT}IIL.Y OPERATING REPORTS

'Docket Nos. 50-387/NPF-14 and 50-388/NPF-22 PlA 005998 a The November 20u0 Monthly Operating Reports for Susquehanna SES Units I and. 2 are attached.

Vct-*, tril.v u~rsi.;,,, .

Poe. Sccone JJf '^cnrmm cc: NRC Region I NRC Sr. Resident Inspector, Mr. Brice Bickett NRC Project Manager, Mr. R V. Guzman j,,es,-)4

OPERATING DATA REPORT DOCKET NO. 50-387 UNIT , One DATE 12/12/2005 COMPLETED BY J. J. Hennings TELEPHONE (570) 542-3747 OPERATING STATUS

1. Unit Name: Susguehanna Steam Electric Station (Ul)
2. Reporting Period: November 2005
3. Design Electrical Rating (Net MWe): 1177
4. Maximum Dependable Capacity (Net MWe): 1135 This Month Yr.-to-Date Cumulative
5. Hours in Reporting Period 720 8,016.0 197,089.0
6. Number of Hours Reactor Was Critical 414.9 . 7,645.6 *165,633.5
7. Hours Generator On-Line 390.0 7613.1 163,213.1
8. Unit Reserve Shutdown Hours 0 0 *0
9. Net Electrical Energy Generated (MWH) 412,547 8,577,856 169,218,298 NOTES:

Page 1 of I

U 'U TD O. WNS At UNIT SHUTDOWNS DOCKET NO. 50-387 UNIT One

. . DATE - ' 12/12/2005 COMPLETED BY J. J. Hennings TELEPHONE (570) 542-3747 REPORT MONTH November 2005 Cause & Corrective Action To Prevent Recurrence On 10/29/05 a planned Reactor shutdown started a Maintenance Outage established for measurement of fuel channels and replacement of those not meeting pre-established criteria. The Maintenance Outage was completed on November 14,2005.

Summary: During the ramp up from the October Maintenance Outage, a planned power reduction of 24% was performed for a Control Rod Pattern adjustment on November 17. 100% power was achieved on 11/18/05.

1. 2. 3.

F. Forced Reason: Method:

S. Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continuation from previous month E - Operator Training & Licensee Exam 5 - Other F - Administrative G - Operational Error (Explain)

Page 1 of I

SUSQUEHANNA STEAM ELECTRIC STATION Docket Number: 50-387 Date: 12/12/05 Completed by: J. J. Hennings Telephone: (570) 542-3747 Challenges to Main Steam Safety Relief Valves None.

'r k OPERATING DATA REPORT DOCKET NO. 50-388 UNIT Two DATE 12/12/05 COMPLETED BY J. J. Hennings TELEPHONE (570) 542-3747 OPERATING STATUS

5. Unit Name: Susguehanna Steam Electric Station (U2)
6. Reporting Period: November 2005
7. Design Electrical Rating (Net MWe): 1182
8. Maximum Dependable Capacity (Net MWe): 1140 This Month Yr.-to-Date Cumulative
5. Hours in Reporting Period 720 8,016.0 182,329.0
6. Number of Hours Reactor Was Critical 720 7247.9 159,927.7
7. Hours Generator On-Line 720 7,156.8 157,849.5
8. Unit Reserve Shutdown Hours 0 0 0
9. Net Electrical Energy Generated (MWH) 835,844 8,021,239 166,836,379 NOTES:

Page I of 1

M t A I SH UT'D W NS e UNIT SHUTDOWNS DOCKET NO. 50-388 UNIT Two DATE 12/12/05 COMPLETED BY J. J. Hennings TELEPHONE, (570) 542-3747 REPORT MONTH November 2005 No. Date Type Duration Reason Method of Cause & Corrective Action I (Hours) 2 Shutting to Prevent Recurrence Down Reactor 3

No reactor shutdowns this month.

Summary: No power changes greater than 20% this month.

1. 2. 3.

F. Forced Reason: Method:

S. Scheduled A- Equipment Failure (Explain) I - Manual B- Maintenance or Test 2 - Manual Scram C- Refueling 3 - Automatic Scram D- Regulatory Restriction 4 - Continuation from previous month E - Operator Training & Licensee Exam 5 - Other F - Administrative G - Operational Error (Explain)

Page 1 of I

SUSQUEHANNA STEAM ELECTRIC STATION Docket Number: 50-388 Date: 12/12//05 Completed by: J. J. Hennings Telephone: (570) 542-3747 Challenges to Main Steam Safety Relief Vabes None.