ML060530412

From kanterella
Jump to navigation Jump to search
Monthly Operating Reports for January 2006
ML060530412
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 02/13/2006
From: Saccone R
Susquehanna
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PLA-006016
Download: ML060530412 (7)


Text

A V I I*

  • ~

st... 1# 6 4

i ' m 3 m- -

I 4 T

TM Robert A. Saccone Vice President - Nuclear Operations PPL Susquehanna, LUC 769 Salem /Boulevard Berwick, PA 18603 Tel. 570.542.3959 Fax 570.542.1504 RASaccone@pplweb.com February 13, 2006 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop C)-P1-17 Washington, D.C. 20555-0001 SUSQUEHANNA STEAM ELECTRIC STATION MONTHLY OPERATING REPORTS Docket Nos. 30-387/NPF-14 and 50-388/NPF-22 PLA - 006016 The January 2006 Monthly Operating Reports for Susquehanna SES Units 1 and 2 are attached.

Very truly yours, Ro er Saccone JJHicmm cc: NRC Ragion I NRC Sr. Resident Inspector, Mr. Alan Blamey NRC Project Manager, Mr. R V. Guzman

+

'

C-- -0 I

OPERATING DATA REPORT DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-387 One 02/13/2006 J. J. Hennings (570) 542-3747 OPERATING STATUS

1. Unit Name:

Susguehanna Steam Electric Station (U1)

2.

Reporting Period:

January 2006

3.

Design Electrical Rating (Net MWe):

1177

4.

Maximum Dependable Capacity (Net MWe):

1135

5.

Hours in Reporting Period

6.

Number of Hours Reactor Was Critical

7.

Hours Generator On-Line

8.

Unit Reserve Shutdown Hours

9.

Net Electrical Energy Generated (MWH)

This Month 744 744 744 0

860,463 Yr.-to-Date 744 744 744 0

860,463 Cumulative 198,577.0 167,121.5 164,701.1 0

170,943,521 NOTES:

Page 1 of I

UNIT SHUTDOWNS DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-387 One 02/13/2006 J. J. Hennings (570) 542-3747 REPORT MONTH January 2006 No.

Date Type Duration Reason Method of Cause & Corrective Action (Hours) 2 Shutting To Prevent Recurrence Down R eactor 3 No reactor shutdowns this month.

Summary: Power reductions greater than 20% this month:

01/07/06 - reduction of 26% for rod pattern adjustment until 01/08/06.

01/21/06 - reduction of 20% for rod pattern adjustment until 01/22/06.

01/28/06 - reduction of 22% for rod pattern adjustment until 01/30/06.

1.

F. Forced S. Scheduled 2.

Reason A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & Licensee Exam F - Administrative G - Operational Error (Explain) 3.

Method:

1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation from previous month 5 - Other Page 1 of 1

SUSOUEHANNA STEAM ELECTRIC STATION Docket Number:

50-387 Completed by:

J. J. Hennings Challenges to Main Steam Safety Relief Valves None.

Date:

02/13/06 Telephone:

(570) 542-3747

OPERATING DATA REPORT DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 02/13/06 J. J. Hennings (570) 542-3747 OPERATING STATUS

5.

Unit Name:

Susguehanna Steam Electric Station (U2)

6. Reporting Period:

January 2006

7.

Design Electrical Rating (Net MWe):

1182

8.

Maximum Dependable Capacity (Net MWe):

1140

5.

Hours in Reporting Period

6.

Number of Hours Reactor Was Critical

7.

Hours Generator On-Line

8.

Unit Reserve Shutdown Hours

9.

Net Electrical Energy Generated (MWH)

NOTES:

This Month 744 744 744 0

867,469 Yr.-to-Date 744 744 744 0

867,469 Cumulative 183,817.0 161,415.7 159,337.5 0

168,568,343 Page 1 of 1

UNIT SHUTDOWNS DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE 50-388 Two 02/13/2006 J. J. Hennings (570) 542-3747 REPORT MONTH January 2006 No.

Date Type Duration Reason Method of Cause & Corrective Action I

(Hours) 2 Shutting to Prevent Recurrence Down Reactor 3

No reactor shutdowns this month.

1.

2.

3.

F. Forced S. Scheduled Reason:

A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & Licensee Exam F - Administrative G - Operational Error (Explain)

Method:

1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation from previous month 5 - Other Page 1 of I

SUSQUEHANNA STEAM ELECTRIC STATION Docket Number:

50-388 Date:

02/13/06 Completed by: J. J. Hennings Telephone:

(570) 542-3747 Challenmes to Main Steam Safety Relief Valves None.