MONTHYEARNRC 2024-0007, Ile Post-Exam Submittal Letter2024-03-18018 March 2024 Ile Post-Exam Submittal Letter NRC-2024-0026, Ile Proposed Exam Submittal Letter2023-12-20020 December 2023 Ile Proposed Exam Submittal Letter NRC 2023-0013, Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-07-0707 July 2023 Response to Regulatory Information Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations NRC 2023-0006, Post-Exam Submittal Cover Letter2023-03-0101 March 2023 Post-Exam Submittal Cover Letter NRC 2023-0005, Report of Changes to Emergency Plan2023-02-21021 February 2023 Report of Changes to Emergency Plan NRC 2022-0032, Sixth 10-Year Interval Inservice Testing (1ST) Program Plan2022-09-30030 September 2022 Sixth 10-Year Interval Inservice Testing (1ST) Program Plan NRC 2022-0025, License Amendment Request 295, Beacon Power Distribution Monitoring System2022-09-26026 September 2022 License Amendment Request 295, Beacon Power Distribution Monitoring System NRC 2022-0019, Report of Changes to Emergency Plan2022-07-13013 July 2022 Report of Changes to Emergency Plan NRC 2022-0022, Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2,2022-07-11011 July 2022 Response to Request for Supplemental Information (Rsi) Regarding License Amendment Request (LAR) 297, Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, NRC 2022-0015, Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report2022-04-27027 April 2022 Fall 2021 Unit 2 (U2R38) Steam Generator Tube Inspection Report NRC 2022-0014, 2021 Annual Monitoring Report2022-04-14014 April 2022 2021 Annual Monitoring Report NRC 2021-0012, Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41)2022-04-0707 April 2022 Core Operating Limits Report (COLR) Unit 1 Cycle 41 (U 1 C41) NRC 2022-0003, License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process2022-03-25025 March 2022 License Amendment Request 296, Application for Technical Specification Improvement to Eliminate Requirements for Post-Accident Systems Using the Consolidated Line Item Improvement Process NRC 2022-0006, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2022-02-22022 February 2022 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections NRC 2022-0004, Report of Changes to Emergency Plan2022-02-0909 February 2022 Report of Changes to Emergency Plan NRC 2022-0005, Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2022-02-0101 February 2022 Refueling Outage U2R38 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2022-0001, Report of Changes to Emergency Plan2022-01-11011 January 2022 Report of Changes to Emergency Plan NRC 2021-0046, Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40)2021-10-28028 October 2021 Core Operating Limits Report (COLR) Unit 2 Cycle 39 (U2C39) and Changes to Unit 1 COLR Unit 1 Cycle 40 (U1C40) NRC 2021-0031, Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-0562021-07-15015 July 2021 Registration of Holtec Hi STORM Casks HI-STORM-37-054, HI-STORM-37-055, and HI-STORM-37-056 NRC 2021-0027, Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-0532021-06-30030 June 2021 Registration of Holtec Historm Casks HISTORM-37-051, HISTORM-37-052, and HISTORM-37-053 NRC 2021-0028, Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism2021-06-23023 June 2021 Generic Letter 2004-02 Containment Sump Debris Transport Calculation Non-Conservatism NRC 2021-0021, 2020 Annual Monitoring Report2021-04-29029 April 2021 2020 Annual Monitoring Report NRC 2021-0019, Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to Regulatory Information Summary 2021-01 Preparation and Scheduling of Operator Licensing Examinations NRC-2021-0010, CFR 50.59 Evaluation and Commitment Change Summary Report2021-04-0202 April 2021 CFR 50.59 Evaluation and Commitment Change Summary Report NRC-2021-0011, Technical Specification Bases and Technical Requirement Manual Change Summary2021-04-0202 April 2021 Technical Specification Bases and Technical Requirement Manual Change Summary NRC 2021-0006, Report of Changes to Emergency Plan2021-03-18018 March 2021 Report of Changes to Emergency Plan NRC 2021-0005, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-022021-02-11011 February 2021 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 2004-02 NRC 2021-0002, Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2021-01-21021 January 2021 Refueling Outage U1 R39 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2021-0003, Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report2021-01-21021 January 2021 Refueling 39 (U1 R39) Reactor Coolant Pump Analytical Evaluation Report NRC 2021-0001, Report of Changes to Emergency Plan2021-01-13013 January 2021 Report of Changes to Emergency Plan NRC 2020-0044, Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise2020-12-0808 December 2020 Response to Request for Additional Information Request for Exemption from 10 CFR 73, Appendix B, Section VI Regarding Annual Force-On-Force Exercise NRC 2020-0032, Application for Subsequent Renewed Facility Operating Licenses2020-11-16016 November 2020 Application for Subsequent Renewed Facility Operating Licenses NRC 2020-0039, Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40)2020-11-0202 November 2020 Core Operating Limits Report (COLR) Unit 1 Cycle 40 (U1 C40) NRC 2020-0031, NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-0812020-10-0505 October 2020 NextEra Energy Point Beach, LLC Response to Apparent Violation in NRC Inspection Report 05000266/2020012, 05000301/2020012: EA-20-081 NRC 2020-0029, Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-09-15015 September 2020 Supplement to License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0024, Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements2020-08-17017 August 2020 Response to Request for Additional Information Request for Exemption from Certain Operator Requalification Requirements NRC 2020-0020, License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-08-13013 August 2020 License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0023, NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations2020-08-12012 August 2020 NextEra Energy Point Beach, LLC - Revised Response to Regulatory Information Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations NRC 2020-0021, Response to NRC Inspection Report and Preliminary White Finding2020-08-12012 August 2020 Response to NRC Inspection Report and Preliminary White Finding NRC 2020-0018, Report of Changes to Emergency Plan2020-07-15015 July 2020 Report of Changes to Emergency Plan NRC-2020-0016, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-12012 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic NRC 2020-0012, Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations2020-05-20020 May 2020 Refueling Outage U2R37 Owner'S Activity Report for Class 1, 2, 3 and Mc ISI Examinations NRC 2020-0008, Report of Changes to Emergency Plan2020-04-0606 April 2020 Report of Changes to Emergency Plan NRC 2020-0007, Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38)2020-03-27027 March 2020 Core Operating Limits Report (COLR) Unit 2 Cycle 28 (U2C38) NRC 2020-0003, License Amendment Request 289: Tornado Missile Protection Licensing Basis2020-02-0606 February 2020 License Amendment Request 289: Tornado Missile Protection Licensing Basis NRC 2020-0001, Pressure Temperature Limits Report (PTLR)2020-01-0909 January 2020 Pressure Temperature Limits Report (PTLR) NRC 2019-0044, Report of Changes to Emergency Plan2019-11-0101 November 2019 Report of Changes to Emergency Plan NRC 2019-0036, Submittal of 2018 Update to Final Safety Analysis Report2019-10-18018 October 2019 Submittal of 2018 Update to Final Safety Analysis Report NRC 2019-0037, Technical Specification Bases Change Summary2019-10-18018 October 2019 Technical Specification Bases Change Summary NRC 2019-0034, Technical Requirements Manual Change Summary2019-10-18018 October 2019 Technical Requirements Manual Change Summary 2024-03-18
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARL-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-113, License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections2024-07-24024 July 2024 License Amendment Request 294, Application to Revise Technical Specifications to Adopt TSTF- 577, Revised Frequencies for Steam Generator Tube Inspections L-2024-105, License Amendment Request 300, Modify Containment Average Air Temperature Requirements2024-06-26026 June 2024 License Amendment Request 300, Modify Containment Average Air Temperature Requirements L-2024-093, Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision2024-06-10010 June 2024 Steam Generator Divider Plate Assemblies Bounding Analysis Evaluation for Aging Management Commitment 14 Revision L-2023-128, License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program2023-09-19019 September 2023 License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program L-2022-177, Subsequent License Renewal Application - Second Annual Update2022-11-28028 November 2022 Subsequent License Renewal Application - Second Annual Update L-2022-160, Station,, Point Beach Units 1 and 2, License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22022-10-0404 October 2022 Station,, Point Beach Units 1 and 2, License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 NRC 2022-0025, License Amendment Request 295, Beacon Power Distribution Monitoring System2022-09-26026 September 2022 License Amendment Request 295, Beacon Power Distribution Monitoring System ML22193A1142022-09-12012 September 2022 Issuance of Amendment Nos. 270 and 272 Elimination of the Requirements to Maintain the Post-Accident Sampling System L-2021-221, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 10 Responses Supplement 12021-11-19019 November 2021 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 10 Responses Supplement 1 L-2021-147, Subsequent License Renewal Application - Aging Management Supplement 3 Revision 12021-07-26026 July 2021 Subsequent License Renewal Application - Aging Management Supplement 3 Revision 1 L-2021-129, Ssubsequent License Renewal Application: Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 1 Responses2021-07-0808 July 2021 Ssubsequent License Renewal Application: Aging Management Requests for Confirmation Of/Additional Information (Rci/Rai) Set 1 Responses L-2021-113, Subsequent License Renewal Application - Aging Management Supplement 32021-05-27027 May 2021 Subsequent License Renewal Application - Aging Management Supplement 3 NRC-2021-0011, Technical Specification Bases and Technical Requirement Manual Change Summary2021-04-0202 April 2021 Technical Specification Bases and Technical Requirement Manual Change Summary ML20329A2642020-11-16016 November 2020 Enclosure 4, Non-proprietary Reference Documents and Redacted Versions of Proprietary Reference Documents (Public Version) ML20329A2142020-11-16016 November 2020 Enclosure 1, Point Beach Nuclear Plant Units 1 and 2 Subsequent License Renewal Application Enclosures Summary ML20329A2192020-11-16016 November 2020 Enclosure 2, Affidavits Supporting Withholding Proprietary Information from Public Disclosure Pursuant to 10 CFR 2.390 ML20329A2482020-11-16016 November 2020 Enclosure 3, Attachment 2, Appendix E Applicant'S Environmental Report Subsequent Operating License Renewal Point Beach Nuclear Plant Units 1 and 2 NRC 2020-0032, Application for Subsequent Renewed Facility Operating Licenses2020-11-16016 November 2020 Application for Subsequent Renewed Facility Operating Licenses NRC 2020-0020, License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss2020-08-13013 August 2020 License Amendment Request (LAR) 293, One-Time Extension of Renewed Facility Operating License Condition 4.1, Containment Building Construction Truss NRC 2020-0003, License Amendment Request 289: Tornado Missile Protection Licensing Basis2020-02-0606 February 2020 License Amendment Request 289: Tornado Missile Protection Licensing Basis NRC 2018-0028, NextEra Energy Point Beach, LLC (NextEra) - License Amendment Request 290, Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements2018-07-30030 July 2018 NextEra Energy Point Beach, LLC (NextEra) - License Amendment Request 290, Application to Revise Technical Specifications to Adopt TSTF-547, Clarification of Rod Position Requirements NRC 2018-0001, Transmittal of Construction Truss License Amendment Request Document2018-04-12012 April 2018 Transmittal of Construction Truss License Amendment Request Document NRC 2018-0018, License Amendment Request 288, Request to Extend Containment Leakage Rate Test Frequency2018-03-30030 March 2018 License Amendment Request 288, Request to Extend Containment Leakage Rate Test Frequency NRC 2017-0043, License Amendment Request 287, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, System, and Components (Sscs) for Nuclear Power Plants2017-08-31031 August 2017 License Amendment Request 287, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, System, and Components (Sscs) for Nuclear Power Plants NRC 2017-0028, License Amendment Request 286, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors.2017-06-23023 June 2017 License Amendment Request 286, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors. NRC 2017-0017, License Amendment Request 278, Risk-Informed Approach to Resolve Construction Truss Design Code Nonconformances2017-03-31031 March 2017 License Amendment Request 278, Risk-Informed Approach to Resolve Construction Truss Design Code Nonconformances NRC 2016-0030, License Amendment Request for H: Alternate Repair Criteria for Steam Generator Tube Sheet Expansion Region2016-07-29029 July 2016 License Amendment Request for H: Alternate Repair Criteria for Steam Generator Tube Sheet Expansion Region NRC-2016-0009, License Amendment Request 2821 Modify the Wording of Surveillance Requirement 3.4.12.7 Associated with the Power-operated Relief Valves2016-03-10010 March 2016 License Amendment Request 2821 Modify the Wording of Surveillance Requirement 3.4.12.7 Associated with the Power-operated Relief Valves NRC 2016-0002, License Amendment Request 280, Removal of Completed License Conditions and Change to the Ventilation Filter Testing Program2016-02-12012 February 2016 License Amendment Request 280, Removal of Completed License Conditions and Change to the Ventilation Filter Testing Program NRC 2015-0075, License Amendment Request 279, Elimination of Technical Specification 3.7.14, Primary Auxiliary Building Ventilation2016-01-15015 January 2016 License Amendment Request 279, Elimination of Technical Specification 3.7.14, Primary Auxiliary Building Ventilation NRC 2015-0004, LAR 266 to Revise Technical Specifications to Adopt TSTF-51 0, Revision 2, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line Item Improvement Process2015-03-27027 March 2015 LAR 266 to Revise Technical Specifications to Adopt TSTF-51 0, Revision 2, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line Item Improvement Process NRC 2014-0075, Supplement to License Amendment Request 273 Application for Technical Specification Change Regarding Risk-Informed Justifications for the Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Prog2014-12-0808 December 2014 Supplement to License Amendment Request 273 Application for Technical Specification Change Regarding Risk-Informed Justifications for the Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Prog NRC 2014-0003, License Amendment Request 273 Re Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program2014-07-0303 July 2014 License Amendment Request 273 Re Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program NRC-2014-0035, License Amendment Request (LAR) 275, Application to Revise Technical Specifications Task Force (TSTF) Traveler TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process2014-07-0202 July 2014 License Amendment Request (LAR) 275, Application to Revise Technical Specifications Task Force (TSTF) Traveler TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process NRC 2013-0092, License Amendment Request 271 Supplement 1 Transition to 10 CFR 50.48(c)- NFPA 8052013-09-16016 September 2013 License Amendment Request 271 Supplement 1 Transition to 10 CFR 50.48(c)- NFPA 805 NRC 2013-0028, Point Beach Nuclear Plant, Units 1 and 2: License Amendment Request 271 - Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Part 22013-06-26026 June 2013 Point Beach Nuclear Plant, Units 1 and 2: License Amendment Request 271 - Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Part 2 of 3 ML13182A3502013-06-26026 June 2013 License Amendment Request 271 - Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Part 2 of 3 NRC 2013-0028, License Amendment Request 271 - Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Part 1 of 32013-06-26026 June 2013 License Amendment Request 271 - Transition to 10 CFR 50.48(c) - NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Part 1 of 3 NRC 2013-0051, License Amendment Request 272, Exemption Request - Optimized Zirlo Fuel Rod Cladding2013-06-0404 June 2013 License Amendment Request 272, Exemption Request - Optimized Zirlo Fuel Rod Cladding NRC 2013-0022, Supplement to License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2013-03-0101 March 2013 Supplement to License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) NRC 2013-0005, License Amendment Request 252, Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2013-01-15015 January 2013 License Amendment Request 252, Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) NRC 2012-0073, License Amendment Request 269, Revised License Pages Cyber Security Plan Implementation Schedule Milestone Change2012-09-17017 September 2012 License Amendment Request 269, Revised License Pages Cyber Security Plan Implementation Schedule Milestone Change NRC 2012-0065, License Amendment Request 270, Operations Manager Qualification Requirements2012-08-16016 August 2012 License Amendment Request 270, Operations Manager Qualification Requirements NRC 2012-0040, License Amendment Request 269, Cyber Security Plan Implementation Schedule Milestone Change2012-06-18018 June 2012 License Amendment Request 269, Cyber Security Plan Implementation Schedule Milestone Change NRC 2011-0066, License Amendment Request 254, Removal of the Table of Contents from Technical Specifications2011-06-23023 June 2011 License Amendment Request 254, Removal of the Table of Contents from Technical Specifications NRC 2010-0189, License Amendment Request 261, Extended Power Uprate Response to Request for Clarification2010-12-21021 December 2010 License Amendment Request 261, Extended Power Uprate Response to Request for Clarification NRC 2010-0154, License Amendment Request 261 - Extended Power Uprate - Response to Request for Additional Information2010-09-28028 September 2010 License Amendment Request 261 - Extended Power Uprate - Response to Request for Additional Information NRC 2010-0146, License Amendment Request 261, Extended Power Uprate, Withdrawal of Proposed Technical Specifications for Reactor Protection System and Engineered Safety Features Setpoints Not Associated with Extended Power Uprate2010-09-28028 September 2010 License Amendment Request 261, Extended Power Uprate, Withdrawal of Proposed Technical Specifications for Reactor Protection System and Engineered Safety Features Setpoints Not Associated with Extended Power Uprate 2024-09-25
[Table view] |
Text
Kewaunee Nuclear Power Plant Point Beach Nuclear Plant N490 Highway 42 6610 Nuclear Road Kewaunee, WI 54216-9511 Two Rivers, WI 54241 920.755.2321 NMC Committed to Nuclear Excellence 920.388.2560 Kewaunee / Point Beach Nuclear Operated by Nuclear Management Company, LLC NRC 2002-0060 10 CFR 50.90 July 12, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Dockets 50-266 and 50-301 Point Beach Nuclear Plant, Units 1 and 2 Clarification of Information License Amendment Request 227 Technical Specification LCO 3.8.1, AC Sources - Operating By submittal dated May 29, 2002, Nuclear Management Company, LLC (NMC) requested an amendment to the Technical Specifications (TS) for Point Beach Nuclear Plant, Units 1 and 2.
The proposed amendment would revise TS 3.8.1, AC Sources - Operating, to allow portions of surveillance requirement (SR) 3.8.1.5 to be performed with the unit in Mode 1, 2, 3 or 4. This proposed amendment is consistent with changes made to NUREG-1431, Standard Technical Specifications, Westinghouse Plants, by TSTF-283, Revision 3.
During a conference call between NMC representatives and NRC staff on July 8, 2002, NRC staff requested clarifying information regarding certain aspects of the submittal. Attachment 1 of this letter provides the NMC response to the staffs questions. The information provided does not require any changes to the proposed Technical Specifications nor their Bases.
We have determined that this clarification of information for the proposed amendments does not involve a significant hazards consideration, authorize a significant change in the types or total amounts of effluent release, or result in any significant increase in individual or cumulative occupational radiation exposure. Therefore, we conclude that the proposed amendments meet the categorical exclusion requirements of 10 CFR 51.22(c)(9) and that an environmental impact appraisal need not be prepared.
NMC requests approval of the proposed License Amendment by August 31, 2002, with the amendment being implemented within 60 days. The approval date was administratively selected to allow for NRC review but the plant does not require this amendment to allow continued safe full power operation.
In accordance with 10 CFIR 50.91, a copy of this application, with attachments, is being provided to the designated Wisconsin Official.
NRC 2002-0060 Page 2 To the best of my knowledge and belief, the statements contained in this document are true and correct. In some respects, these statements are not based entirely on my personal knowledge, but on information furnished by cognizant NMC employees and consultants. Such information has been reviewed in accordance with company practice and I believe it to be reliable.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on July 12, 2002.
wt JG/kmd
Attachment:
1 - Clarification of Information cc: NRC Regional Administrator NRC Project Manager NRC Resident Inspector PSCW
NRC 2002-0060 Page 1 of 4 CLARIFICATION OF INFORMATION LICENSE AMENDMENT REQUEST 227 TECHNICAL SPECIFICATION LCO 3.8.1, AC SOURCES - OPERATING POINT BEACH NUCLEAR PLANT, UNITS I AND 2
NRC 2002-0060 Page 2 of 4 The following information is provided in response to the Nuclear Regulatory Commission staff's request for clarifying information on NMC's May 29, 2002 License Amendment Request (LAR),
as discussed during telephone conferences between NRC and NMC staff on July 8, 2002. The LAR would modify Technical Specification (TS) 3.8.1, AC Sources - Operating, to allow portions of surveillance requirement (SR) 3.8.1.5 to be performed in MODE 1, 2, 3, or 4.
The NRC requested clarification regarding what portions of SR 3.8.1.5 would be performed in MODE 1, 2, 3, or 4; examples of the types of circumstances that would necessitate performing this SR in MODE 1, 2, 3, or 4; and further explanation of the process that would be employed to perform this SR in MODE 1, 2, 3, or 4.
As stated in NMC's May 29, 2002 LAR, the onsite standby emergency power system is comprised of four emergency diesel generators (EDGs) that directly supply the 4.16 kV safeguards electrical distribution buses. Normally, all four EDGs are operable and aligned to their normal bus; however, the EDGs can be aligned such that only one EDG per safeguards train is required operable to support one or both units. In addition, either EDG may be manually connected to one or both of its respective trains' 4.16 kV safeguards distribution buses. The TS only require two of the four EDGs onsite to be operable for full power operation of both units.
Because of this unique EDG configuration and capability, SR 3.8.1.5 must be completed on each EDG separately for each reactor unit (i.e., SR 3.8.1.5 must be performed on all four EDGs while they are aligned to Unit 1 and then must be completely reperformed on all four EDGs while they are aligned to Unit 2. This has normally been done during each respective reactor unit's refueling outage. Consequently, SR 3.8.1.5 is performed on each EDG twice during the required 18-month interval (rather than once, as would be required in a standard design plant).
During the spring 2002 refueling outage of Unit 2, SR 3.8.1.5 was satisfactorily performed on EDGs G-01, G-03 and G-04 for Unit 2. EDG G-02 was not available for testing at that time; therefore, SR 3.8.1.5 was only partially completed on this diesel for Unit 2. Specifically, SR 3.8.1.5 sections 'a' and 'b' (de-energization of buses and load shedding from buses) were satisfactorily completed since this portion did not require the EDG. Those portions of SR 3.8.1.5.c.2 that did not require EDG G-02 were also performed. Please note that SR 3.8.1.5 is met for Unit 1 on G-02 since it was successfully completed during the previous Unit 1 refueling outage.
This particular situation at Point Beach, regarding the necessity to perform SR 3.8.1.5 with Unit 2 at power, arose because EDG G-02 was off-site for testing during the regularly scheduled performance of SR 3.8.1.5 for Unit 2. Unexpected complications resulted in EDG G-02 being offsite and unavailable for performance of its associated portions of the SR during the entire span of the Unit 2 refueling outage. SR 3.8.1.5 is normally only performed during scheduled refueling outages of the associated unit.
NRC 2002-0060 Page 3 of 4 NMC is planning to complete SR 3.8.1.5.c on EDG G-02 for Unit 2 with Unit 2 in MODE 1.
Currently, SR 3.8.1.5 is modified by a note that this surveillance not be performed with the associated unit in MODE 1, 2, 3 or 4. In discussing this note, the current TS Bases state, "The reason for the Note is that the performance of the Surveillance would remove a required offsite source from service, perturb the electrical distribution system and challenge safety systems".
However, because of the redundancy of EDGs at Point Beach, one EDG may be realigned such that it is not associated with, nor required by, either unit. Testing may then be performed on this EDG without removing a required offsite source from service or perturbing the electrical distribution system. The ESF loads on this bus were already loaded onto the safeguards bus (while powered by the other EDG) and tested during the spring 2002 Unit 2 refueling outage.
The current TS Bases also state, "The requirement to verify the connection and power supply of permanent and autoconnected loads is intended to satisfactorily show the relationship of these loads to the standby emergency power source loading logic. In certain circumstances, many of these loads cannot actually be connected or loaded without undue hardship or potential for undesired operation. For instance, Emergency Core Cooling Systems (ECCS) injection valves are not desired to be stroked open, or high pressure injection systems are not capable of being operated at full flow, or residual heat removal (RHR) systems performing a decay heat removal function are not desired to be realigned to the ECCS mode of operation. In lieu of actual demonstration of connection and loading of loads, testing that adequately shows the capability of the standby emergency power source systems to perform these functions is acceptable. This testing may include any series of sequential, overlapping, or total steps so that the entire connection and loading sequence is verified."
The above TS Bases statements provide the reason for performing SR 3.8.1.5. They also provide an allowance for simulating portions of the test which may cause "undue hardship or potential for undesired operation." Therefore, "...in lieu of actual demonstration of connection and loading of loads", such as the requirement to demonstrate the emergency standby power source "...energizes permanently connected loads and energizes auto-connected emergency loads through load logic sequencer", the SR can be performed through "...testing that adequately shows the capability of the standby emergency power source systems to perform these functions."
The proposed Bases for TS 3.8.1 state, "This restriction from normally performing the Surveillance in MODE 1, 2, 3 or 4 is further amplified to allow portions of the Surveillance to be performed for the purpose of reestablishing OPERABILITY (e.g., post work testing following corrective maintenance, corrective modification, deficient or incomplete surveillance testing, and other unanticipated OPERABILITY concerns) provided an assessment determines plant safety is maintained or enhanced" (emphasis added). The proposed modification to the note will enhance the ability of Point Beach to take advantage of its redundant EDGs for completing SR 3.8.1.5 without the risk of an unnecessary plant shutdown. Equivalent reactor safety is maintained by the proposed addition to the TS of a precondition for performing this SR in MODE 1,2,3 or 4. This condition stipulates that this SR may only be performed in these Modes if an assessment determines that the safety of the plant is maintained or enhanced.
NRC 2002-0060 Page 4 of 4 Proposed Testing Outline Part of the surveillance testing may be performed using an inductive and resistive programmable load bank that can simulate both motor starting and running loads. The load bank is nominally rated at 5000 kW resistive and 4500 kVAR inductive. Alternately, this part of the surveillance may be performed by sequencing and loading Unit 1 loads onto the diesel while Unit 1 is shutdown for refueling. The Unit 1 emergency load profile bounds the Unit 2 load profile (for loads powered by G-02).
The portions of SR 3.8.1.5 associated with Unit 2 for EDG G-02 that have already been completed during the spring 2002 Unit 2 refueling outage are not proposed to be repeated with Unit 2 at power.
SR 3.8.1.5.c.3 and 3.8.1.5.c.4, and the incomplete portion of SR 3.8.1.5.c.2, are planned to be checked either via a programmable load bank capable of simulating the KW AND KVAR load profile associated with the emergency load sequencing, or by actually sequencing and loading Unit 1 loads onto the diesel (while Unit 1 is in MODE 5 or 6). The Unit 2 portion of these particular tests is planned to be performed with Unit 2 at power.
SR 3.8.1.5.c.1 and 3.8.1.5.c.5 are planned to be checked using a special test procedure that would start and operate "A" Train Safety Related Loads. These loads can be operated safely with the units at power and their operation in this condition is permitted by technical specifications. The EDG would then be paralleled to the bus and, after nulling current through the normal feeder breaker; the normal feeder breaker would be opened. The "A" Train loads would then be operated on the EDG for greater than 5 minutes. Operators would then parallel across and re-close the normal feeder breaker, transfer the loads from the EDG to the offsite power supply and secure the EDG. This portion of the surveillance testing would use actual plant loads (rather than a load bank).
Because of the unique EDG configuration and capability at Point Beach, the addition of the proposed Note to the SR only enhances the ability of Point Beach to take advantage of its redundant EDGs for completing SR 3.8.1.5 safely. Any potential for perturbation of the electrical distribution system or challenges to safety systems are only minimally affected by the addition of this Note.
Routine use of this Note to defer the SR is neither planned nor envisioned. In the future, the Note would allow completion of portions of the SR outside of refueling outages should unexpected conditions preclude performing those portions of the SR during the refueling outage. Only those portions of the SR that could be evaluated as being able to be safely performed under the plant operating conditions would be performed. This would eliminate the need for unnecessary shutdowns of a unit. The Note would also facilitate coordinating portions of the SR between Unit 1 and Unit 2 refueling outages such that unnecessary duplication of SR steps is eliminated and thereby wear on the EDGs is reduced.