NRC-89-0254, Monthly Operating Rept for Nov 1989 for Fermi 2.W/891215 Ltr

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Nov 1989 for Fermi 2.W/891215 Ltr
ML20011D146
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 11/30/1989
From: Anthony P, Orser W
DETROIT EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CON-NRC-89-0254, CON-NRC-89-254 NUDOCS 8912210069
Download: ML20011D146 (4)


Text

I1 1

. .,, . .*. ?::

^

i

. Wilhem s. Orser - l

$['IE!?e% tion. Reg Guide 1.16 lI- r rmi24 b].

. e,4oo worin omie H.ph*ay Nuclear ISOn Newport Michigan 481f4 O'3)655* December 15. 1989 Generation NRC-89-0254 4

U. S. . Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555

Reference:

Fermi 2 NRC Dochet No. 50-341 NRC Operating License No. NPF-43 i

Subject:

Menthly Operating Status Report ,

for November, 1989 Enclosed for your.information and use is the Fermi 2 Honthly Operating Status Report for November, 1989. This report includes the Operating Data Report. Average Daily Unit Power Level, and the Summary of Unit Shutdowns and Power Reductions identified in NRC Regulatory Guide 1.16 and Fermi 2 Technical Specification 6.9.1.6.

If.you have-any. questions, please contact Patricia-Anthony at (313)' 586-1617.

Sincerely. j c

l.

/

l i.

l.

Enclosure cc: A. B. Davis l

J. R. Eckert D. R. Hahn

! R. W. Defayette/W. L. Axelson L T. R. Quay l

W. G. Rogers 8912210069 891130

'PDR ADOCK.05000341 PDC

-[/2 f L iR /' i g

-o

e

-7 OPERATING DATA REPORT DOCKET NO. 50-341 COMPLETED BY P. M. Anthony DATE December 15, 1989 TELEPHONE (313)586-1617 OPERATING STATUS Fermi 2 l Notes: l

1. UNIT NAME: l
2. REPORTING PERIOD: November, 1989 l l 3 LICENSED THERMAL POWER (MWt): 3292 l # To be determined i
4. NAMEPLATE RATING (GROSS MWe): 1154 l l
5. DESIGN ELECT RATING (Net MWe): 1093 I l
6. MAX DEPENDABLE CAP (GROSS MWe): # l l 7 MAX DEPENDABLE CAP (Net MWE): # I l
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE  ;

LAST REPORT, GIVE REASONS: None

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (MWe Net): None
10. REASONS FOR RESTRICTION, IF ANY: None  !

THIS MONTH YR TO DATE CUMULATIVE I

11. HRS IN REPORTING PERIOD 720 8016 16,262
12. HRS REACTOR WAS CRITICAL 0 5613 10,635 5
13. REACTOR RESERVE SHUTDOWN HRS 0 0 0
14. HOURS GENERATOR ON-LINE O 5290.2 10,011
15. UNIT RESERVE SHUTDOWN HOURS 0 0 0
16. GROSS THERMAL ENERGY GEN (MWH) 0 15,854,286 28,883,738
17. GROSS ELECT ENERGY GEN (MWH) 0 5,343,904 9,622,608

-18. NET ELECT ENERGY GEN (MWH) 0 5,117,826 9,199,960

19. IchlT SERVICE FACTOR 0 66.0 _ 61.6
20. UNIT AVAILABILITY FACTOR 0 66.0 61.6 ,,
21. UNIT CAP FACTOR (USING MDC NET) # # #
22. UNIT CAP FACTOR (USING DER NET) _ 0 58.4 51.8
23. UNIT FORCED OUTAGE RATE O 10.7 17.6
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE. DURATION OF EACH)

The first refueling outage began on September 5, 1989. The unit achieved criticality on December 8, 1989.

25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED INITIAL CRITICALITY N/A N/A INETIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A

r.

,8 .

.r

l
  • AVERAGEDAILY'UNiTPOWERLEVEL  ;
r. .

DOCKET NO. 50-341 UNIT FERMI 2 ,

DATE December 15, 1989 f

COMPLETED BY P. M. Anthony TELEPHONE (313) 586-1617 Month. November, 1989 DAY ' AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net). (MWe-Net) s 1 0 17 0 2 0 18 0

.3 0 19 0 4' O 20 0 5 0 21 0 6 0 22 0 7 0 23 0

. 8' O 24 0 9- 0 25 0 10 0 26 0

!- 11 0 27 0 12 0 28 0 13 0 29 0 14 0 30 0 15 0 31 N/A _

16 0

~ ~'

" R ,.$

~

(-k?"

" ^

. .; 3 <

- - . C-'

"1

. UNIT SHUTDOWNS AND POWER REDUCTIONS s _

Y ..

DOCKET NO. 50-341 D AT E.. . December 15. '999

  • s[

.f g

- UNIT NAME ~ Fermi 2 COMPLETED ev.. p. u. Anthon< *

. 5 TELEPH3NE (313)586-1617- ...

REPORT MONTH November, 1989 l- i I 'I i i i  !. . .

I' 1 1 t usTHOD OF I 'LER ' SY S l COMP 1 CAUSE & CORRECTIVE 1 NOs DATE l TVPE l. DUR REASON .I SHUTTING DOWN I NO. CODE' CODE l- 'ACTIOM TO PREVENT

] i (1). 1 (HRS) (2) THE-REACTOR (4) (5) .I AECURRENCE I l (3)

N/A ---- ' Continuec m'th refueling activities09-011 -! 09/05/89 . S 720 C 4- .

l { l I. i including leak rate testing, j l l l  ! tureire inspection and repair and l l l I I fuel handling.

I l i f 1 I I 'l (1) F: FORCED (2) REASON: (3) METHOD: ( 4 )' EXHIBIT.G - INSTRUCT!CNS 5: SCMEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA B - MAINTENANCE OR TEST 2 - MANUAL SCRAM ENTRY SHEETS FOR LICENSEE.

C - REFUELING 3 - AUTOMATIC SCRAu EVENT REPORT (LER) FILE D - REGULATORY RESTRICTION 4 - CONTINUED (NUREG-0161)

E- OPERATOR TRAINING & LICENSE EXAMINATION 5 - REDUCED LOAD F - ADMINISTRATIVE 9 - OTHER G.- OPERATIONAL ERROR (EAPLAIN)

H - OTHER (EXPLAIN)' (5) EXHIBIT 1 - SAME SOURCE