NL-15-026, Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation

From kanterella
Jump to navigation Jump to search

Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation
ML15065A123
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 02/27/2015
From: Coyle L
Entergy Nuclear Northeast
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-051, NL-15-026, TAC MF0737, TAC MF0738
Download: ML15065A123 (17)


Text

Enterav Nuclear Northeast SEntergy Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel 914 254 6700 Lawrence Coyle Site Vice President NL-1 5-026 February 27, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike, OWFN-2FL Rockville, MD 20852-2738

SUBJECT:

Indian Point Energy Center's Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (TAC Nos.

MF0737 and MF0738)

Indian Point Unit Numbers 2 and 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64

References:

1. NRC Order Number EA-1 2-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12054A682)
2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012
3. NEI 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, "To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation", Revision 1, dated August 2012
4. Entergy letter to NRC (NL-12-145), Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated October 29, 2012
5. Entergy letter to NRC (NL-13-043), Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated February 27, 2013 Aoolý pt4 4

NL-15-026 Dockets 50-247 and 50-286 Page 2 of 3

6. Entergy letter to NRC (NL-1 3-109), Indian Point Energy Center's First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0737 and MF0738), dated August 27, 2013
7. Entergy letter to NRC (NL-14-029), Indian Point Energy Center's Second Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0737 and MF0738), dated February 27, 2014
8. Entergy letter to NRC (NL-14-109), Indian Point Energy Center's Third Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0737 and MF0738), dated August 27, 2014

Dear Sir or Madam:

On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission")

issued an order (Reference 1) to Entergy. Reference 1 was immediately effective and directed Entergy to install reliable spent fuel pool level instrumentation. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2.

Reference 4 provided the Entergy initial status report regarding spent fuel pool instrumentation. Reference 5 provided the Entergy overall integrated plan.

Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the fourth six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The attached report provides an update of milestone accomplishments since the last status report (Reference 8), including any changes to the compliance method, schedule, or need for relief and the basis, if any.

There are no new commitments identified in this submittal. If you have any questions concerning the content of this letter, please contact Mr. Robert Walpole, Manager, Regulatory Assurance at (914) 254-6710.

NL-15-026 Dockets 50-247 and 50-286 Page 3 of 3 I declare under penalty of perjury that the foregoing is true and correct. Executed on February D._, 2015.

Sincerely, LC/sp

Attachment:

Indian Point Energy Center's Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation cc: Mr. Douglas V. Pickett, Senior Project Manager, NRC NRR DORL Mr. Daniel H. Dorman, Regional Administrator, NRC Region 1 NRC Resident Inspectors Office Mr. John B. Rhodes, President and CEO, NYSERDA Ms. Bridget Frymire, New York State Dept. of Public Service Ms. Jessica A. Kratchman NRC NSIR DPR DDEP IRIB

ATTACHMENT TO NL-1 5-026 ENTERGY'S FOURTH SIX-MONTH STATUS REPORT FOR THE IMPLEMENTATION OF ORDER EA-12-051 MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION ENTERGY NUCLEAR OPERATIONS, INC.

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 and 3 DOCKET NOS. 50-247 and 50-286

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 1 of 13 Indian Point Energy Center's (IPEC) Fourth Six Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation

1. Introduction Entergy Nuclear Operations, Inc. (Entergy) developed an Overall Integrated Plan (Reference 1) for Indian Point Energy Center (IPEC), documenting the requirements to install reliable spent fuel pool level instrumentation (SFPI), in response to Reference 2.

This attachment provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2. Milestone Accomplishments The following milestone(s) have been completed since August 27, 2014 and are current as of January 31, 2015.

0 Respond to ISE RAIs dated November 8, 2013 - Complete.

3. Milestone Schedule Status The following provides a line item update to milestone schedule to support the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

Revised Target Milestone Target Completion Activity Status Completion Date Date Unit 3 Reliable SFPI Installed Spring 2015 Refueling In Progress N/A Outage Unit 2 Reliable SFPI Installed Spring 2016 Refueling In Progress N/A Outage Respond to NRC RAIs August 23, 2013 Complete N/A (Received June 25, 2013)

(Reference 3)

Respond to ISE RAIs dated September 30, 2014 Complete N/A November 8, 2013 (Reference 4)

4. Changes to Compliance Method There are no additional changes to the compliance method.

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 2 of 13

5. Need for Relief/Relaxation and Basis for the Relief/Relaxation IPEC expects to comply with the Order implementation date and no relief/relaxation is required at this time.
6. Open Items from Overall Integrated Plan and Interim Staff Evaluation IPEC has received an Interim Staff Evaluation (Reference 4) that includes 15 RAIs. There were 3 additional RAIs received prior to the October 2014 NRC Audit Visit (Reference 6), for a total of 18 RAIs. The following table provides the status of these 18 RAIs. The RAI responses provided are applicable to both Unit 2 and Unit 3. However, the NRC Audit Visit Report (Reference 6) indicates that it would be determined in the future if another audit visit is necessary for Unit 2, therefore, all of the Unit 2 RAIs are considered open until that determination is made.

RAI # IP2 Response Status IP3 Response Status 1 Submitted in Reference 7 Closed During NRC Audit (Reference 6) 2 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 3 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 4 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 5 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 6a Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 6b Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 6c Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 7 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 8 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 9 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 10 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 11 Submitted in Reference 7 Closed During NRC Audit (Reference 6) 12 Submitted in Reference 7 Closed During NRC Audit (Reference 6) 13 Uploaded to e-portal September 30, 2014 Closed During NRC Audit (Reference 6) 14 See Section 9 (See Note) See Section 9 (See Note) 15a Submitted in Reference 7 Closed During NRC Audit (Reference 6) 15b Submitted in Reference 7 Closed During NRC Audit (Reference 6) 16 See Section 9 Closed During NRC Audit (Reference 6) 17 See Section 9 Closed During NRC Audit (Reference 6) 18a See Section 9 (See Note) See Section 9 (See Note) 18b See Section 9 (See Note) See Section 9 (See Note) 18c See Section 9 (See Note) See Section 9 (See Note)

Note: These RAIs were listed as Open Items in the NRC Audit Visit Report (Reference 6).

7. Potential Interim Staff Evaluation Impacts There are no additional potential impacts to the Interim Staff Evaluation identified at this time except for those identified in Section 6.

Attachment to NL-15-026 Dockets 50-247 and 50-286 Page 3 of 13

8. References The following references support the updates to the overall integrated plan described in this attachment.
1. Entergy letter to NRC (NL-13-043), "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated February 27, 2013 (ADAMS Accession No. ML13072A082).
2. NRC Order Number EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12054A682).
3. "Request for Additional Information Overall Integrated Plan in Response to Order EA 051, 'Reliable Spent Fuel Pool Instrumentation' Entergy Operations, Order No. EA-12-051 (TAC Nos. MF0737 and MF0738)," dated June 25, 2013 (ADAMS Accession No. ML13169A127).
4. "Indian Point Nuclear Generating Unit Nos. 2 and 3 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0737 and MF0738)," dated November 8, 2013 (ADAMS Accession No. ML13298A805).
5. "Summary of the November 26, 2013, Public Meeting to Discuss Industry Responses to Staff Interim Evaluations for Spent Fuel Pool Instrumentation," dated December 26, 2013 (ADAMS Accession No. ML13347B030).
6. "Indian Point Nuclear Generating Unit Nos. 2 and 3 - Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EAI-12-051 (TAC NOS. MF0744, MF0745, MF0737, AND MF0738)", dated December 9, 2014 (ADAMS Accession No. ML14335A642)
7. Entergy letter to NRC (NL-14-109), Indian Point Energy Center's Third Six-Month Status Report for the Implementation of Order EA-1 2-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0737 and MF0738), dated August 27, 2014
8. Donald C. Cook Nuclear Plant, Units 1 and 2 - Report for the Onsite Audit of MOHR Regarding Implementation of Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-051 (TAC NOS. MF0761 and MF0762) dated August 27, 2014 (ADAMS Accession No. ML14216A362)

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 4 of 13

9. Responses to the Interim Staff Evaluation Requests for Additional Information RAI #14 Please provide a list of the procedures addressing operation (both normal and abnormal response), calibration, test, maintenance, and inspection procedures that will be developed for use of the spent SFP instrumentation. The licensee is requested to include a brief description of the specific technical objectives to be achieved within each procedure.

The immediately following replaces what was provided to the NRC during the audit based on the open item identified in the audit report (Reference 6).

The following operations procedure has been developed for IPEC Unit 3; a comparable procedure is planned for Unit 2:

Procedure Description 3-FSG-0 11, Alternate New procedure which provides actions to restore Spent Fuel Pit Makeup and Cooling (SFP) level using an alternate makeup source for a Beyond Design Basis External Event (BDBEE) resulting in an Extended Loss of AC Power (ELAP). This procedure includes remote Spent Fuel Pool Level Indicator operation, the location of the displays, and cautionary statements such as an EMI/RFI exclusion zone around the displays.

The following table is a list of Preventative Maintenance (PM) tasks planned to be developed for the Entergy fleet:

Task Name Objective Frequency of Occurrence Channel Calibration To validate that the MOHR instruments (both 2Y Check channels) are displaying the correct spent fuel pool level within the accuracy of the instruments.

Channel Check/Panel To check each channel against each other for 1Y Functional Check comparison and to perform functional assessments of each panel.

Operator Rounds/System Operator Rounds is intended to observe the As Required Engineering Walkdown system status via panel display, switch positions and indicating lights, to validate the MOHR instrumentation system is operating satisfactorily from its intended power source, and to detect obvious external signs of deterioration.

Signal Processor Clock To prevent failure of the onboard clock battery and 1OY Battery Replacement adverse impact to the signal processor operating system.

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 5 of 13 SFPI RAI #16 Describe actions taken to verify electromagnetic compatibility with the vendor's limited test.

Note: The following response was provided for NRC review during the October 2014 NRC Audit Visit; this RAI was closed by the NRC Audit Team (Reference 6).

The NRC Audit of MOHR was in conjunction with the NRC's review of D.C. Cook's SFPI OIP, however the audit report also applies to other licensees using the MOHR technology to comply with the requirement of Order EA-12-051 (Reference 8). In this report, the NRC stated:

As a result of the NRC staff's evaluation of the EMC testing results, the staff identified a generic open item applicable to all licensees using this technology to identify any additionalmeasures, site-specific installationinstructionsor position taken to address the potential effect of an EMC event on the SFPI equipment To address this concern, Ops procedure 3-FSG-01 1, Section 4, notes includes a cautionary statement to preclude radio usage within close proximity to the displays when taking a reading.

In addition, no system voltages being affected or installed are greater than 125 Volts, and new instrumentation cables in the Fuel Storage Building and Fanhouse are being installed in rigid steel conduit where practical to limit the amount of EMI emitted by the new wiring. The isolation transformer being installed in the power circuit of each SFPI circuit will limit the introduction of any noise or harmonics (typically referred to as "total harmonic distortion," or THD) into the safety related instrument buses that may be generated by the new equipment.

SFPI RAI #17 Please provide a final configurations of the IP2 and IP3 SFP area, clearly depicting the SFP monitoring Level 1, 2, and 3, the planned locations/placement of the primary and back-up SFP level sensor/probe, and the proposed routing of the cables that will extend from the sensors toward the location of the read-out/display device.

Note: The following response was provided for NRC review during the October 2014 NRC Audit Visit; this RAI was closed by the NRC Audit Team (Reference 6); however, the first sentence of the original response has been revised below for clarification purposes (the changes are editorial only).

Figure 1 & Figure 2 depict an elevation view of the Unit 2 & Unit 3 final SFP Monitoring Levels.

As stated in IPEC's Third Six-Month Status Report (Reference 7), there were several changes made to the probe locations and channel routing shown in Attachments 1 and 3 of the OIP (Reference 1). For both units, the Channel A probe is shown where the Channel B probe is located, and the Channel B probe is shown where the Channel A probe is located. Additionally for Unit 2, the location of the Channel B probe in the SFP and the routing of both channels has been altered from the OIP. Updated cable routing and probe locations are shown below in Figure 3 through Figure 6.

Attachment to NL-15-026 Dockets 50-247 and 50-286 Page 6 of 13 ELEVATION REFERENCE 9321-F-2514-19 FSB General Arrangement Plans & Elev.

-..---- - I-.Sm------------ .943 --------------- 2-ARP-SGF (Alarm Response Procedure) & 9321 -F-7043

--- Lu ---------------------------- 933 9321-F-2514-19 FSB General Arrangemmnt Plans & Elev 9321-F-7043 (LC-050 in Section B-B)

W&IR--------------- ------------- ------------- 9X3-3 2-ARP-SGF (Alarm Response Procedure) & 9321 -F-7043


l-- ------------- 9 2-2--------------- TS 3.7.11 Spent Fuel Pit Level 9321-F-2577, FSB Aux Coolant System Sections, Section C-C


- --------------------- -- - 80814 NEI 12-02 (Level 3 + 10')

-B------ . .------------------- L* - -. 7o-8114-

-- - - ----------------------- ------------- 70(-5 14 Bottom Min. Sensitive Range. 3' below LEVEL 3 upper limit 9321-F-1388 & HOLTEC #397 to 408 11 II00LEV 67-81/4-M---------


54'-7" 9321-F-2514-19 FSB General Arrangement Plans & Elev.

i Figure 1: Unit 2 SFP Elevation View with Levels Indicated

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 7 of 13 ELEVATION REFERENCE

..... 9-<0" 93211-F-202T7 RO Fuel Storage Bidding El. 96'-O Plans, Sections and Details Mehdanical N 94' 3-ARP.013 (Aarm Response Procedure) &9321-F-70433

-I-

. 93' -. 9321-F-20277 RO Fuel Storage Building El. 95'-0 Plans, Sections and Details Mechanical 9321 -F-70443 (LC-650 in Section B-B)

.-.........- 9T 3-ARP-013 (Alarm Response Procedure) &9321-F-70433


TS 3.7.14 Spent Fuel Pit Level

.... - -5 3W8

,--------------*--------- 9321-F-25773, FSB Aux Coolant System Sections (Plan 7, Section C-C) 8W-7 1l2I -----------------

NEI 12-02 (Level 3

  • 10')

f.*T_ .----------- ----- R..W-... 70-7 1W2 D II 11111-- 70-4 1/2" OW-7 1/2" Bottom Min. S-Sensitive Range. 3' below LEVEL 3 upper limit IP3V-1604-0004, IP3V-1684-.0032 54V-7' 9321-C-11023 RI Proposed FSB MeL Pre-Permit Congt.

Figure 2: Unit 3 SFP Elevation View with Levels Indicated

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 8 of 13 6

D 0 C C a 0 M- Wit - UM CIW. v

- MAN -MP 0M (Na

$FP1NONELPCAI(NM PLAN AT EL.95'-O" A A SFPI GENERAL ARRAIWOEMENTs GENERAL ARRANGEMENT 1P2 DRAWING 9321-F-.2514 DI SK-EIPX042-C X 6 1 7 I 1 6 3 1 2 Figure 3: Unit 2 SFPI General Arrangement Drawing 1

Attachment to NL-15-026 Dockets 50-247 and 50-286 Page 9 of 13 6 r I e 5 1 4 31 2 1 0 0 C C a a

- 31 MW MEW xW oMRIN ME -Wm 0-3W SPI POO LoC4T1ow A A SFPI CONCEPTUAL DESIG#4I 1P2 ~W~nk GENERAL IPEC2 ARRANGEWMET MI2.F.3080. 9321-F-1332

- EK6NTIPXG42:'Z ZE.

a I II aI 5 I 3 2 Figure 4: Unit 2 SFPI General Arrangement Drawing 2

Attachment to NL-15-026 Dockets 50-247 and 50-286 Page 10 of 13 a i ? i 6 5 4 i3i 2 1 1 D 0 C C 5 a

- MM ME - gn, Ouea. W

- "nNK- SM 0$- WRBI C) "E, E ON~

A A SFPI OEFIERALAMFIPNEKETi GENE=~ ARRAMIEVENT

-IPEC3 MINAING 9321-F-20277 a a 1 2 Figure 5: Unit 3 SFPI General Arrangement Drawing I

Attachment to NL-15-026 Dockets 50-247 and 50-286 Page 11 of 13 a 7 1 f 1 5 13 1 2 D, 0 C C a a

- RED M~E - ý 'EIcIA:

- R IREM- DSI OI$WEL SF44 Pr4K LOCA1g(NM A A SFPI GENERAkL ARRAJAGEAEFGTs GeNEMAL ARKVIGEEUNT

-IPEC3 DRAWING 9321-F-31503-DjKEMEPX042,-G=ýX 9 I i e a S 4 3 i 2 1I Figure 6: Unit 3 SFPI General Arrangement Drawing 2

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 12 of 13 SFPI RAI #18 Please provide the following:

a) A description of the plans for ensuring that necessary channel checks, functional tests, periodic calibration, and maintenance will be conducted for the level measurement system and its supporting equipment.

b) Information describing compensatory actions when both channels are out-of-order, and the implementation procedures.

c) Additional information describing expedited and compensatory actions in the maintenance procedure to address when one of the instrument channels cannot be restored to functional status within 90 days The immediately following replaces what was provided to the NRC during the audit based on the open item identified in the audit report (Reference 6).

a) SFPI channel/equipment maintenance/preventative maintenance and testing program requirements to ensure design and system readiness are established in accordance with Entergy's processes and procedures and in consideration of vendor recommendations to ensure that appropriate regular testing, channel checks, functional tests, periodic calibration, and maintenance is performed. See response to SFPI RAI #14 for a list of procedures and PM tasks being developed.

b) Both primary and backup SFPI channels incorporate permanent installation (with no reliance on portable, post-event installation) of relatively simple and robust augmented quality equipment. Permanent installation coupled with stocking of adequate spare parts reasonably diminishes the likelihood that a single channel (and greatly diminishes the likelihood that both channels) is (are) out-of-service for an extended period of time.

Control of compensatory actions for out of service SFPI channel(s) will be controlled by inclusion in the Plant's Technical Requirements Manual (TRM); the following is the draft proposed TRM for SFPI:

TRM 3.10 BEYOND DESIGN BASES COMPONENTS TRM 3.10.C Spent Fuel Pool Level Instrumentation TRO 3.10.C The primary and back-up spent fuel pool level instruments shall be OPERABLE.

APPLICABILITY: At all times.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. The primary or back-up A. 1 Restore spent fuel pool 90 days spent fuel pool level level instrument to instrument does not meet OPERABLE status the OPERABLE requirements. AND

Attachment to NL-1 5-026 Dockets 50-247 and 50-286 Page 13 of 13 A.2 If not restored within two 14 Days weeks, present a report to OSRC giving why out of service and plan to repair B. Action A.1 completion B.1 Initiate actions to Immediately time not met. implement compensatory measures such as use of alternate suitable equipment or supplemental personnel C. The primary and back-up C.1 Restore one of the 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> spent fuel pool level channels of instruments do not meet instrumentation.

the OPERABLE requirements.

D. Required Action and D.1 Initiate actions to Immediately associated Completion Implement compensatory Time of Condition C not measures such as use of met alternate suitable equipment or supplemental personnel Note: Compensatory measures under consideration are use of alternate suitable equipment or supplemental personnel.

c) The requested information is provided in the RAI-18.b response.